Investor Presentation
Released
Released
Announcement PDF
Advancing the
Sorby Hills
Lead-Silver Project
Toward a Final Investment Decision
13 October 2023
Boab Metals Limited ASX:BML
Boab Metals Limited ASX:BML
1
Disclaimer
Forward-Looking Statements
Compliance Statement
Certain statements in the presentation are or may be “forward-looking statements” and
represent the Company’s intentions, projections, expectations or beliefs concerning, among
other things, future operating and exploration results or the Company’s future performance.
These forward-looking statements speak, and the presentation generally speaks, only at the
date hereof. The projections, estimates and beliefs contained in such forward-looking
statements necessarily involve known and unknown risks and uncertainties, and are
necessarily based on assumptions, which may cause the Company’s actual performance
and results in future periods to differ materially from any express or implied estimates or
projections.
The Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore
Reserves (the ‘JORC Code’) sets out minimum standards, recommendations and guidelines
for Public Reporting in Australasia of Exploration Results, Mineral Resources and Ore
Reserves.
General Disclaimer
The information in this presentation remains subject to change without notice. This
presentation may contain information (including information derived from publicly
available sources) that has not been independently verified by the Company.
Not an Offer
This presentation is for information purposes only. The presentation does not comprise a
prospectus, product disclosure statement or other offering document under Australian law.
The presentation does not constitute or form part of any invitation, offer for sale or
subscription or any solicitation for any offer to buy or subscribe for any shares in Boab
Metals Limited.
No Liability
Boab Metals Limited has prepared this document based on information available at the
time of preparation. No representation or warranty, express or implied is made as to the
fairness, accuracy or completeness of the information, opinions and conclusions contained
in this presentation. To the maximum extent permitted by law, Boab Metals Limited, its
related bodies corporate and the officers, directors, employees, advisers and agents of those
entities do not accept any responsibility or liability for any loss arising from the use of the
presentation or its contents or otherwise arising in connection with it.
Boab Metals Limited ASX:BML
Information included in this presentation relating to Exploration Results has been extracted
from the ASX Announcements titled “Amended Drilling Announcement” dated 4
September 2023”, “Assays Confirm Further Positive Outcome for Sorby” dated 23 January
2023, “High-Grade Lead-Silver Confirmed at Beta Deposit” dated 1 February 2022, and “Sorby
Hills DFS Metallurgical Testwork Results” dated 19 November 2021 available to view at
www.boabmetals.com.au. The Company confirms that it is not aware of any new
information or data that materially affects the information included in these
announcements. The Company confirms that the form and context in which the
Competent Person’s findings are presented have not been materially modified from the
form in which they were first presented.
Information included in this presentation relating to Mineral Resources has been extracted
from the Mineral Resource Estimate dated 17 December 2021, available to view at
www.boabmetals.com.au. The Company confirms that it is not aware of any new
information or data that materially affects the information included in the Mineral Resource
Estimate and that all material assumptions and technical parameters underpinning the
estimates, continue to apply and have not materially changed. The Company confirms that
the form and context in which the Competent Person’s findings are presented have not
been materially modified from the Mineral Resource Estimate.
Information included in this presentation relating to Ore Reserves, Production Targets and
Financial Forecasts has been extracted from the Sorby Hills Definitive Feasibility Study and
dated 19 January 2023, available to view at www.boabmetals.com.au. The Company
confirms that it is not aware of any new information or data that materially affects the
information included in the Ore Reserve Statement and that all material assumptions and
technical parameters underpinning the estimates, production targets and financial
forecasts continue to apply and have not materially changed. The Company confirms that
the form and context in which the Competent Person’s findings are presented have not
been materially modified from the Ore Reserves Statement.
2
Boab Metals Limited
Corporate Summary
Capital structure (9 October 2023)
Market Cap
A$17.4 million
Cash
A$3.0 million (30 September 2023)
Performance Rights
8,300,000
4.0
0.40
3.5
0.35
3.0
0.30
2.5
0.25
2.0
0.20
1.5
0.15
1.0
0.10
0.5
0.05
0.0
0.00
Share Price (A$/share)
Shares on Issue
174 million shares
Debt
Nil
Volume (million shares)
Share Price
A$0.10 / share
Share Price History
Top 4 Shareholders
#
Holder Name
1
Villiers Queensland PL
8.74%
2
Zero Nominees Pty Limited
4.33%
3
Citicorp Nominees Pty Limited
3.38%
4
Brent Connolly
2.52%
Boab Metals Limited ASX:BML
9 October 2023
Volume
• ASX-listed base and
precious metals
developer and explorer.
Share Price
• Board & Management
team with a proven track
record in development.
• Advancing toward Final • Top 20 shareholders hold
Investment Decision on
36% of issued capital.
Sorby Hills.
3
Pb Lead
The Proven Battery Metal
The primary component of the 12V batteries found in traditional and electric vehicles.
• Demand growth underpinned by mature and emerging vehicle technologies.
• Supported by rapid growth in utility and renewable energy storage1.
1. www.batteryinnovation.org/resources/lead-battery-market-data/
Source: Wood Mackenzie LME Forum 2022 Presentation October 2022
Boab Metals Limited ASX:BML
4
Ag Silver
The Most Conductive Metal on Earth
Ideal metal for use in solar cells and the electronic components of electric vehicles.
•
Silver‘s traditional role as a storer
of wealth is complemented by its
increasing industrial demand.
•
The use of Silver in solar cells has
increased nearly 150% (8.3% CAGR)
to 127Moz over the past 10 years1.
•
Sorby Hills and Boab Metals offers
rare ASX exposure to Silver metal
demand.
1. www.silverinstitute.org/silver-supply-demand/
Boab Metals Limited ASX:BML
5
Sorby Hills Project
A near-term producer of Lead and Silver
•
Located 50km northeast of Kununurra in the East
Kimberley Region of Western Australia
•
High quality Mineral Resource with significant near
mine and greenfields exploration upside
•
150km by existing sealed roads to the Wyndham Port
•
Definitive Feasibility Study complete
•
Conventional open pit mining and flotation process
plant producing a high-grade Lead-Silver concentrate
•
Initial production target underpinned by 83% Reserves
•
Heads of Agreement to secure clean energy from the
Ord River Hydroelectric Plant
•
Heads of Agreement with local shire for Kununurrabased accommodation facility executed
•
Front End Engineering & Design complete
•
Offtake negotiations nearing completion and
Engagement with Financiers ongoing
•
Project advancing toward a Final Investment Decision
Boab Metals Limited ASX:BML
Figure: Location of the Sorby Hills Project
1. See Slide 7 for Resource breakdown 2. See Appendix for Lead Equivalent calculation method
6
Sorby Hills Project
DFS results support progress toward a Decision to Mine1
A$245m preproduction Capex
underpinned 75%
by tendered pricing
C1 cash cost
US$0.39/lb payable Pb
Incl. net Silver credit of
US$0.38/lb payable Pb
Average Annual Production
103kt Lead-Silver concentrate
67kt Lead and 2.2Moz Silver
NPV8 A$370m
IRR 35%
Strong pre-tax
economics
Lead
543 thousand payable tonnes
A$1,790 Million Revenue
2.25Mtpa
8.5 Year
Mine Life
A$1.0bn Operating Cash Flow
Silver
A$119m p.a. Average EBITDA
17.2 million payable ounces
A$692 Million Revenue
1. See Appendix for Revenue Assumptions
Boab Metals Limited ASX:BML
7
Sorby Hills Project
High Quality Mineral Resource Estimate
Deposit
A
B
Omega
Norton
Alpha
Beta
Total
Resource
Figure: Sorby Hills Resource relative to mining leases and local geology.
Boab Metals Limited ASX:BML
Grade
Classification
Tonnes
(Mt)
Pb
Inferred
0.6
Sub Total
0.6
Measured
1.4
Contained Metal
PbEq1
Pb
Zn
Ag
g/t
%
kt
kt
koz
23
6.1%
31
6
427
31
6
427
52
4
859
Zn
Ag
%
%
5.3%
1.0%
5.3%
0.1%
23
6.1%
3.8%
0.3%
19
4.5%
Indicated
1.3
3.4%
0.3%
21
4.1%
44
4
862
Sub Total
2.7
3.6%
0.3%
20
4.3%
97
8
1,720
Measured
8.5
3.3%
0.4%
37
4.6%
279
32
9,995
Indicated
5.8
3.5%
0.4%
34
4.7%
205
25
6,331
Inferred
2.9
2.7%
0.4%
26
3.6%
76
13
2,414
Sub Total
17.2
3.3%
0.4%
34
4.5%
566
71
18,948
Measured
2.8
4.1%
0.3%
75
6.7%
112
9
6,668
Indicated
2.1
3.2%
0.5%
38
4.5%
68
11
2,617
Inferred
16.2
2.5%
0.5%
27
3.4%
402
75
14,039
Sub Total
21.1
2.8%
0.4%
34
4.0%
590
96
24,090
Indicated
0.7
2.6%
0.5%
41
4.0%
18
4
923
Inferred
0.8
3.6%
1.2%
86
6.6%
27
9
2,052
Sub Total
1.5
3.1%
0.9%
64
5.3%
45
13
2,975
Indicated
1.0
4.1%
0.2%
42
5.6%
42
2
1,382
Inferred
3.2
3.4%
0.4%
43
4.9%
109
14
4,474
Sub Total
4.2
3.6%
0.4%
43
5.1%
151
17
5,856
Measured
12.6
3.5%
0.4%
43
5.0%
444
45
17,521
Indicated
11.0
3.4%
0.4%
34
4.6%
377
46
12,114
Inferred
23.6
2.7%
0.5%
31
3.8%
645
117
23,406
Total
47.3
3.1%
0.4%
35
4.3%
1,465
207
53,042
See ASX announcement 17 December 2021
1. See Appendix for Lead Equivalent calculation method
8
Sorby Hills Project
Production Target and Reserve Estimate
DFS Production Target
Pit
Total
(Mt)
Waste
(Mt)
ROM
(Mt)
Pb
(%)
Ag
(g/t)
PbEq
(%)
Strip
Ratio
Pit A
4.1
3.7
0.5
3.7
16.4
4.3%
8.1
Pit B
14.8
12.6
2.3
3.2
17.4
3.8%
5.5
Omega South
21.1
18.3
2.8
2.9
29.5
3.9%
6.5
Omega Main
57.7
50.3
7.4
3.6
38.7
5.0%
6.8
Norton
21.4
19.5
1.9
4.0
78.5
6.8%
10.0
Beta
35.6
32.2
3.4
3.3
41.5
4.8%
9.5
Total Production
154.8
136.5
18.3
3.4
38.8
4.8%
7.5
Figure: DFS pit shells with respect to the Resource block model
1. See Appendix for Lead Equivalent calculation method
Ore Reserve Statement
Ore Reserve
Category
Ore
(Mt)
Proved
Grade
Contained Metal
Pb (%)
Ag (g/t)
Pb (kt)
Ag (Moz)
10.4
3.5%
42
358
14.1
Probable
4.9
3.5%
32
172
5.0
Total Ore Reserve
15.2
3.5%
39
531
19.1
Production Target
underpinned 83% by
Measured and Indicated
Resources.
17%
26%
57%
Including 95% Measured
and Indicated Resources
over the first 7 years of
production.
Measured
Indicated
Inferred
See ASX announcement 19 January 2023
Boab Metals Limited ASX:BML
9
Sorby Hills Project
Process Flow Sheet
▪ Conventional Process Plant design
supported by extensive metallurgical
testwork and process engineering.
▪ GR Engineering Services (“GRES”)
selected as preferred tender for
Process Plant EPC.
▪ Feed Capacity of 2.25Mtpa (a 50%
increase on that included in the
Sorby Hills PFS).
▪ Average 103ktpa Lead-Silver
Concentrate production.
Figure: Sorby Hills Process Flow Sheet. Conventional Crush Mill Float Process Plant
Boab Metals Limited ASX:BML
10
Sorby Hills Project
Path to Market
Agreement for Access and Stevedoring
Service executed with Cambridge Gulf with
respect to Wyndham Port.
Term extending to April 2034 with an
automatic rollover on a 12-monthly basis.
Wyndham Port is located 150km by existing
sealed road from Sorby Hills.
Wyndham Port is the only deep-water port
between Broome and Darwin.
Port operations and management are
currently overseen by Cambridge Gulf.
Concessional Loading application to
reduce mine to port haulage costs.
Figure: Wyndham Port (Courtesy of Cambridge Gulf / Ben Broady).
Boab Metals Limited ASX:BML
11
Sorby Hills Project
Project Optimisation Workstreams
▪
Boab is undertaking a series of Project Optimisation Workstreams in conjunction with Front-End Engineering and
Design (“FEED“) to explore opportunities further improve Project economics ahead of a Final Investment Decision.
1.
an updated tailings strategy to allow for the higher-grade Norton deposit to be mined earlier thus bringing
forward increased metal production and revenue;
2.
completion of FEED resulting in a more detailed process plant design and optimised plant layout;
3.
updated tendered pricing for the process plant from GR Engineering Services (“GRES”) based on the FEED
outcomes and current raw material and labour costs. The update is a negligible change from the DFS pricing;
4. additional metallurgical test work to refine conservative metal recoveries at the Norton Deposit that were
necessarily adopted for the DFS due to limited core availability at the time;
▪
5.
updated power strategy that reduces, and possibly removes, the requirement for a fully sized diesel plant on-site
generated back up on site, thus further reducing power costs and exposure to diesel fuel price fluctuations; and
6.
updated tendered pricing for mining and bulk earthworks contracts. The mining and bulk earthworks contracts
were tendered for the DFS at the height of post COVID inflation. The Company is confident the updated tenders
will deliver more competitive pricing.
The results of the Project Optimisation Workstreams will be incorporated into a FEED Study with the intention that
this study is released to the market in Q1 2024.
Boab Metals Limited ASX:BML
12
Sorby Hills Project
Updated Tailings Strategy to enhance Metal Production
20,000,000
1,000,000
Cumulative Payable Lead / Silver
18,000,000
900,000
High grade Silver from the
Norton deposit delivered earlier
in the production schedule.
800,000
14,000,000
700,000
12,000,000
600,000
10,000,000
500,000
8,000,000
400,000
6,000,000
300,000
4,000,000
200,000
2,000,000
100,000
-
1
3
5
7
9
11
13
15
17
19
21
23
25
27
29
31
33
35
37
39
41
43
-
Cumulative Payable Lead (tonnes)
Cumulative Payable Silver (ounces)
16,000,000
▪ The DFS tailings strategy incorporated both
above-ground tailings storage within an
integrated waste landform (“IWL”) and in-pit
tailings deposition.
▪ Boab has determined that the footprint of
the proposed IWL is sufficient to support
additional raises that will provide capacity for
approximately 6 years of above-ground
tailings storage.
▪ The updated strategy allows for higher
grades from the Omega and Norton pits to
be mined earlier thus replacing the lower
grade ore from the Omega South pit in the
Mining Schedule
Production Quarter
Cumulative Payable Silver - Updated Schedule
Cumulative Payable Silver - DFS
Cumulative Payable Lead - Updated Schedule
Cumulative Payable Lead - DFS
See ASX announcement 19 January 2023
Boab Metals Limited ASX:BML
13
13
Sorby Hills Project
Detailed Design and Optimised Plant Layout
▪ GRES has completed FEED
Workstreams
Primary Crusher
▪ FEED output has resulted in:
Flotation
Circuit
Filter Press
SAG Mill
•
detailed plant design;
•
optimised site layout;
•
the issue of tender packages
for long-lead items; and
•
updated EPC pricing
consistent with EPC pricing
adopted in the DFS.
Ball Mill
Tailings
Thickener
•
Options to reduce costs have
been identified by GRES.
•
EPC Contract Award upon FID.
Concentrate Container Loading
Figure: 3D Model of the Sorby Hills Process Plant produce by GRES during FEED.
Boab Metals Limited ASX:BML
14
14
Sorby Hills Project
Metallurgical Testwork to enhance Metal Recoveries
▪ Phase VII Drilling Program completed. Assay results
targeted for late October / early November 2023.
▪ Metallurgical drill holes completed at the Norton
Deposit. New testwork will target a significant increase to
the conservative metal recoveries adopted in the DFS.
▪ Testwork Program expected to be completed Q1 2024. If
successful, this will allow reoptimistion of the Norton pit
design to increase mine life.
Summary of DFS metal recoveries
Ore Type
Figure: Location of previous drilling and Phase VII drilling relative to
an outline of the currently proposed Norton Deposit open pit design.
Boab Metals Limited ASX:BML
Avg. Pb Recovery
Avg. Ag Recovery
A Pit
95%
84%
B Pit
94%
84%
Norton
78%
78%
Omega
93%
70%
Beta
90%
87%
Overall Average
91%
82%
15
15
Sorby Hills Project
Clean Power Solution
▪ Heads of Agreement executed with Horizon Power
with respect to a future Power Purchase
Agreement for Sorby Hills.
▪ Key Indicative Terms
•
Delivery of firm power over a 10-year term with
a purchaser option to extend; and
•
Cleaner, cheaper electricity sourced from Ord
River hydroelectric plant modelled to provide
+90% of power to the Project.
▪ Optimised solution being investigated whereby
the need for diesel power back-up assumed in the
DFS is reduced or potentially removed.
▪ Opportunity to enhance the clean energy credentials
of the Project with lower operating costs.
Figure: Members of the Boab and Horizon Power
teams on site at the Ord-Hydro Power station.
Boab Metals Limited ASX:BML
16
Sorby Hills Project
Updated tenders to reprice key contract packages
DFS C1 Operating Costs (%)
Lead Treatment Charge, 12%
Mining Costs
Processing, 29%
Logistics, 9%
G&A, 7%
Mining, 44%
▪
Mining comprised 44% of the DFS Operating Costs.
▪
Tenders for the Mining Contract were received in 2022 during the
height of post-COVID inflation.
▪
A refreshed mining tender based on the updated tailings strategy
and mining schedule is ongoing.
EPC and Earthwork Capital Costs
DFS Pre-production Capital Costs (A$m)
Pre Production
Opex, A$15m
Contingency,
A$21m
Other, A$13m
▪
Tendered EPC and Earthworks Packages comprised nearly 70% of the
DFS Pre-Production Capex.
▪
Updated tendered pricing from GRES for the EPC Contract on the
back of FEED has delivered a result consistent with the DFS.
▪
Retendering for the Earthworks Package based on an optimised site
layout and bundling with the Mining Package is ongoing.
Water Management,
A$5m
EPC Package,
A$131m
Owners Costs,
A$25m
Earthworks
Package,
A$36m
Boab Metals Limited ASX:BML
The Company is confident the updated tender processes will deliver
more competitive pricing.
17
Sorby Hills Project
Near-term opportunity to upgrade Mineral Resource
Phase V – 15 holes not yet included in Mineral Resource Estimate
▪ SHRC_123 (Beta): 27m @ 3.47% Pb & 37g/t Ag from 34m:
▪ Incl. 3m @ 7.04% Pb & 95g/t Ag from 35m; 5m @ 5.60% Pb & 44g/t Ag from 45m;
and 6m @ 4.50% Pb & 49g/t Ag from 55m.
▪ SHRC_124 (Beta): 17m @ 3.51% Pb & 46g/t Ag from 49m:
▪ Incl. 8m @ 6.93% Pb & 90g/t Ag from 57m.
▪ SHRC_129 (Wildcat): 6m @ 5.37% Pb & 21g/t Ag from 12m down hole.
Phase VI – 28 holes not yet included in mineral Resource Estimate
▪ SHRC_157 (Beta): 7m @ 19.17% PbEq, (16.23% Pb & 82g/t Ag) from 72m
▪ Incl. 3m @ 41.38% PbEq, (35.26% Pb & 174g/t Ag) from 72m.
▪ SHRC_136 (Beta): 20m @ 7.39% PbEq, (5.58% Pb & 52g/t Ag) from 65m
▪ Incl. 8m @ 13.86% PbEq, (10.49% Pb & 96g/t Ag) from 77m.
▪ SHRC_151 (Beta): 5m @ 5.13% PbEq, (3.70% Pb & 41g/t Ag) from 45m.
▪ SHRC_163 (Beta): 13m @ 2.90% PbEq, (2.26% Pb & 18g/t Ag) from 49m.
▪ SHRC_149 (Norton): 2m @ 16.64% PbEq, (10.92% Pb & 163g/t Ag) from 103m
(terminated in mineralisation).
▪ SHRC_147 (Norton): 11m @ 5.74% PbEq, (3.84% Pb & 54g/t Ag) from 86m.
▪ SHRC_143 (Norton): 13m @ 4.06% PbEq, (2.82% Pb & 35g/t Ag) from 95m.
▪ Incl. 5m @ 5.35% PbEq, (3.91% Pb & 41g/t Ag) from 95m.
Phase VII (Assays Pending) – 21 holes not yet included in Mineral Resource Estimate
Boab Metals Limited ASX:BML
18
Sorby Hills Project
Near-term opportunity to increase production target
A
B
C
D
Either “Cross
Section” or “cross
section”
Figure: Assay results from recent drill holes not yet included in Mineral Resource
Boab Metals Limited ASX:BML
Figure: Norton deposit cross Section showing the position of recently completed
drill holes, intercepts and reinterpreted outline of the mineral resource envelopes
and the current open pit outline.
19
Sorby Hills Project
Progress towards a Final Investment Decision
•
FEED Workstreams largely complete.
•
Independent Technical due diligence largely complete.
•
Optimisation Workstreams delivering positive results.
•
Mining Leases granted, EPA Approval in place.
•
Independent ESG status review against global environmental
standards including the Equator Principles complete.
•
Boab has engaged BurnVoir Corporate Finance to arrange a
project finance solution for the Sorby Hills Project.
•
The Company is engaged with Australian Government
financing agencies, commercial banks, mining finance
funds and offtakers to secure a fit for purpose project
financing solution that minimises shareholder dilution.
•
Advanced Stage Negotiations with Offtakers including
international and domestic traders and smelters to be
concluded ahead of a Final Investment Decision.
Boab Metals Limited ASX:BML
Figure: Vessel loading activities at Wyndham Port (Image courtesy of
Cambridge Gulf).
20
Boab Metals Limited
Strategic Growth Opportunities
Keep Seismic Target.
▪ 1st drill hole potential discovery hole (2 km south
of existing Sorby Hills reserves)
▪ Possible New Zone with scope for extensive
development of mineralisation
Intersected
▪ Upper Mineralised Zone::~5m of stratiform bands
and disseminated mineralization from 82.5m
▪ Lower Mineralised Zone: ~14m of stratiform MVT
zinc and lead sulphides bands and disseminated
mineralization from 242.5m
Figures: Section of Keep Seismic
Target showing basin margin
faults
and
favorable
stratigraphic horizon. Massive
replacement style sphalerite
(ZnS) and galena (PbS)
Boab Metals Limited ASX:BML
Assays Due
▪ Late October/Early November
Future
▪ Aggressive drill program to test the potential for
an economic mineral deposit.
21
21
Boab Metals Limited
Strategic Growth Opportunities
Boab owns a 100% interest the Eight Mile Creek Exploration Licence E80/5317
Key highlights include:
✓ Exploration Tenements
covering 206 km2 of
relatively underexplored
tenure immediately south
of Sorby Hills.
✓ Scout drilling has confirmed the
existence of a favourable
stratigraphic setting and fluid traps
that may host mineralisation similar
to that observed at Sorby Hills.
✓ 30km of along-strike geology,
highly prospective for
deposits similar to Sorby Hills.
✓ Intercepted anomalous
mineralisation including 9m at
220ppm Pb and about 100ppm Zn in
EMRC_005 from 121m.
✓ Structure and stratigraphic
targets developed based on an
interpretation of new gravity
data, soil sampling and
geological interpretation.
✓ The success at the Keep Seismic
Target has opened the door for
more bold exploration
Figure: Location of Eight Mile Creek Project relative to the Sorby Hills Projects.
Boab Metals Limited ASX:BML
22
22
Boab Metals Limited
Strategic Growth Opportunities
Boab owns a 100% interest in the Manbarrum ZincLead-Silver Project
Key highlights include:
✓ Manbarrum is strategically
located 25km east of the
Sorby Hills Lead-Silver Zinc
Project.
✓ Mineral Resources declared
at two prospects within the
Manbarrum project area1.
✓ Conceptual open pit mining
studies completed by CSA
Global in 2018 identified the
opportunity to improve
project economics via toll
treating at a future plant
located at Sorby Hills.
✓ 175km2 of prospective
tenements (including two
granted mining leases)
covering geology genetically
related to that found at
Sorby Hills allowing for an
effective transfer of technical
knowledge2.
1 Refer to the Todd River Resources prospectus dated 4 April 2017
2 Refer BML Announcement 21 July 2021
Boab Metals Limited ASX:BML
Figure: Location of Manbarrum relative to the Sorby Hills and Eight Mile Creek Projects.
23
23
Boab Metals Limited
Establishing Deep Roots within the Community and supporting better outcomes
Boab is extremely proud to be the Naming Rights
Sponsor of the Ord Valley Muster for
2023 and beyond.
•
Sense of community plays a key role in economic
and social well-being of stakeholders across the
east Kimberley Region.
•
The Ord Valley Muster has been a highlight of
the Kimberley community calendar for 20 years.
Boab is an enthusiastic supporter and active
contributor to the Teach Learn Grow program.
•
Boab Metals has been partnering with Teach
Learn Grow (TLG) since 2021 in the delivery of
their Rural Program which supports one-on-one
tutoring and mentorship to students in East
Kimberley schools.
Boab Metals Limited ASX:BML
Images: Ord Valley Muster 2023 and Simon Noon - Managing Director/CEO with team at Teach Learn Grow,
East Kimberley
24
Boab Metals Limited
Establishing Deep Roots within the Community and supporting better outcomes
Heads of Agreement executed with the Shire of Wyndham
and East Kimberley (“SWEK”) for the construction and longterm lease of a new accommodation Facility located in
Kununurra.
Key Indicative Terms:
• Boab to fund pre-construction work in return for
securing a 10-year lease for the facility with an option
to extend for a further 5 years. Pre-construction costs
will be rebated against leasing costs.
• SWEK will fund and oversee detailed design and
construction of the facility.
The agreement is further evidence of the synergies and
significant economic opportunities between the Sorby
Hills Project and the East Kimberley community.
Boab Metals Limited ASX:BML
Figure: Aerial view of the township of Kununurra in the east
Kimberley Region of Western Australia
25
Sorby Hills Joint Venture
Boab (75% interest)
Henan Yuguang Gold and Lead Co., Ltd
(25% contributing interest)
•
Yuguang Gold and Lead Co., Ltd (“Yuguang”) is
Asia’s largest electrolytic lead producer and
China’s largest Silver producer.1
•
Initially invested in Sorby Hills Joint Venture in 2010.
•
Listed on the Shanghai Stock Exchange (600531).
•
Market Capitalisation of A$1.3B.2
•
3,600 Employees.1
•
Yuguang Lead and Silver products are London Metal
Exchange (“LME”) and the London Bullion Market
Association (“LBMA”) registered.
•
Committed to environmental protection and
development through improvement and innovation.
1.
2.
www.yggf.com.cn
Based on AUD:RMB : 4.74
Boab Metals Limited ASX:BML
26
Sorby Hills Project
Current focus and upcoming Share Price Catalysts
•
•
•
Continue engagement with potential financers.
•
Receive EPA s45c amendment approval and EPBC reconfirmation
based on the updated Project design.
•
Work with GRES and Horizon Power on an enhanced power
strategy that reduces or removes need for diesel back-up on-site.
•
Complete metal recovery optimisation and potential open-pit
enlargement at the Norton deposit.
•
•
•
•
•
Complete Independent Technical Due Diligence for Lenders.
Release Assay Results for the Phase VII Drilling Program.
Receive updated Mining and Bulk Earthworks contracts tenders
based on updated mining schedule and optimised site layout.
Incorporate Project Optimisation results into a FEED Study.
Secure credit approved offer(s) from debt financiers.
Execute Offtake Agreement(s).
Reach a Final Investment Decision.
Boab Metals Limited ASX:BML
27
27
Simon Noon – Managing Director & CEO
info@BoabMetals.com
www.BoabMetals.com
www.linkedin.com/company/boab-metals
Thank You
Appendix
Boab Metals Limited ASX:BML
29
Board and
Management
Gary Comb
Board and Management
with a proven track
record in exploration and
development
Technical Team
Boab Metals Limited ASX:BML
Simon Noon
Richard Monti
Andrew Parker
Chairman
Managing Director
and CEO
Non-Exec. Director
Non-Exec. Director
Engineer with over 30
years’ experience in the
Australian mining
industry, with a strong
track record in
successfully
commissioning and
operating base metal
mines.
Experienced mining
executive with a strong
background in
management, capital
raising and operating
JV’s with mid to top tier
miners in a variety of
commodities.
Geologist with over 30
years’ experience in
technical, commercial,
marketing and finance
within the exploration
and mining industry.
Lawyer with significant
experience in the
exploration and mining
industry. Wealth of
expertise in corporate
advisory, strategic
consultancy and raising
capital.
Paul Hewitt – Project Director
Richard Flanagan – Project Engineer
Simon Dorling - Exploration Manager
Paul has over 25 years in providing senior project
delivery leadership within the Energy and Resource
sectors for process and non-process infrastructure
projects, for the full lifecycle from study phase
through to execution within Australia and
Internationally.
Mining engineer with extensive experience across a
wide range of commodities, including several world
class Silver-Lead-Zinc deposits and covers management
roles across feasibility studies, development,
commissioning and operations.
Geologist with more than 26 years’ experience in
exploration, development and the mining of base
metals, precious metals, energy minerals and
industrial minerals.
30
Sorby Hills Definitive Feasibility Study
Capital Costs
Pre-production
(A$M)
Sustaining
(A$M)
Total
(A$M)
Early Works / Bulk Earthworks / Road Construction
9.9
15.7
25.6
Process Plant and Non-Plant Infrastructure (NPI)
130.5
-
130.5
Tailings Storage and Evaporation Pond
18.0
1.9
19.9
Mine Water Settling Pond & Water Storage Facility
12.4
21.3
33.7
Accommodation refurbishment
4.1
-
4.1
Communications
0.9
-
0.9
Fuel Tanks
-
1.3
1.3
Concentrate Transport & Containers
7.9
-
7.9
Owners Cost
25.3
5.8
31.0
Project Development Contingency
20.9
-
20.9
Pre-Production Operating Costs
14.6
-
14.6
-
9.3
9.3
244.6
55.2
299.8
Tendered Pricing for 75% of
Capital Costs to reduce the
risk of pre-FID cost escalation.
Item
Process Plant EPC comprises:
• $82.9M – Su