Quarterly Activities and Cashflow Report
Released
Released
Announcement PDF
6 July 2023
Quarterly Activities and Cashflow Report
for the period ending 30 June 2023
Boab Metals Limited (ASX: BML) (“Boab” or “Company”) is pleased to provide the following activity
and cashflow report for the quarter ending 30 June 2023. During the quarter, the Company
continued progress toward reaching a Decision to Mine at its 75% owned Sorby Hills Lead-SilverZinc Project (“Sorby Hills” or “the Project”), located in the Kimberley Region of Western Australia.
HIGHLIGHTS
•
Front End Engineering & Design and Project Optimisation workstreams progress
o
Finalisation of Project Design Criteria, Process Flow Diagrams and, optimised Plant
Layout with preferred EPC Contractor GR Engineering Services (“GRES”);
o
Re-optimisation of Mining Schedule and Tailings Strategy Update to increase
Project cash flows over the initial production years;
o
Rationalisation of Contract Packages to realise cost-saving synergies across the
mining and bulk earthworks activities; and
o
Boab, GRES, and Horizon Power working towards an optimised solution to reduce,
and potentially remove, the need for a diesel-fuelled back-up to the grid power
delivered from the Ord River Hydro Power Plant.
•
Phase VII drill program commenced with 19 diamond holes targeting mine life extensions
and enhanced metallurgical recoveries at the Norton Deposit.
•
Approvals workstreams progressing with positive determinations anticipated to be
received in Q3 ahead of a Final Investment Decision.
•
Construction Financing and Offtake continue to progress.
•
The Company had a cash balance of approximately A$4.6M as at 30 June 2023.
Boab Managing Director and CEO, Simon Noon, stated: “Since completing the DFS earlier in the
year, the Boab team has been heavily focused on examining opportunities to refine and optimise
the Project, to the benefit of our shareholders. As we draw nearer to a Final Investment Decision
on the Project, I am excited to be working closely with all our stakeholders to bring the Sorby Hills
Project to realisation as soon as practicable.”
Background
Boab is developing its 75% owned Sorby Hills Lead-Silver Project located 50km northeast of
Kununurra in the Kimberley Region of Western Australia. In January 2023, Boab released a
Definitive Feasibility Study (“DFS”) on the Project (ASX Announcement 19 January 2023) that
demonstrated robust economics (Figure 1) and supported progress toward a decision to mine.
Figure 1: Highlights of the Sorby Hills Project DFS.
After completing the DFS, Boab has advanced multiple project optimisations, operational
readiness, and financing workstreams in preparation for Final Investment Decision (“FID”).
Early Works and Project Optimisation
Front End Engineering & Design
Following the selection of GRES as the preferred EPC Contractor for the Sorby Hills Project (ASX
Announcement 21 November 2022) and the subsequent execution of an Engineering & Services
Agreement (ASX Announcement 13 March 2023), Boab and GRES have focused on Front End
Engineering & Design (“FEED”) workstreams in preparation for EPC contract award.
Weekly progress meetings with GRES have sought to finalise process design criteria and process
flow diagrams, optimise site layout (Figure 2), and generate 3D models of the Process Plant and
Non-Process Infrastructure (Figure 3). The output has resulted in a refined process plant design
and the issue of tender packages for long-lead items.
Furthermore, the optimised site layout has allowed for an amended bulk earthworks design to be
undertaken by Coffey, and subsequently, a re-estimate of materials quantities that will form the
basis of updated tenders for the Early Earth Works program.
FEED remains on track for completion in Q3 2023.
_____________________________________________________________________________________________________________________________ ____________________
Quarterly Report June 2023
Page 2
Figure 2: Site Layout of the Sorby Hills Process Plant and Non-Process Infrastructure.
Figure 3: 3D Model of the Sorby Hills Process Plant layout looking northward from the ROM Pad
toward the processing facilities and administration buildings.
_____________________________________________________________________________________________________________________________ ____________________
Quarterly Report June 2023
Page 3
Mining Schedule Optimisation and Tailings Strategy Update
The Sorby Hills DFS tailings strategy incorporated both above-ground tailings storage within an
integrated waste landform (“IWL”) and in-pit tailings deposition. The rationale for this decision had
been the opportunity to reduce the IWL footprint and necessitated that the Sorby Hills deposits
were to be mined in a particular sequence that provided sufficient tailings storage capacity as and
when required.
Subsequent to the DFS, Boab has determined that the initial footprint of the IWL is sufficient to
support additional raises that will provide capacity for approximately 6 years of above-ground
tailings storage. The changed strategy does not materially impact pre-production capital costs
and allows for mining of the lower grade zone of the Omega South pit (which was to be completed
and used for tailings deposition from Year 5) to be replaced by higher grades of the Omega and
Norton pits in the mining schedule, thus bringing forward increased metal production and
revenue.
The updated mining schedule developed by Entech Mining Pty Ltd is shown in Figure 4.
Figure 4: Updated Mining Schedule colour coded by pit.
Rationalisation of Contract Packages
The updated mining schedule and tailings strategy has provided Boab with the opportunity to
explore a rationalisation of contract packages, including the bundling of the mining contract with
bulk earthworks activities.
Boab is currently working closely with contractors who have previously tendered for the mining
and bulk earthworks packages to help them refine their pricing based on the updated schedule
and the bundled contract. The Company is confident the updated approach to contracting will
deliver a positive outcome for the Project.
_____________________________________________________________________________________________________________________________ ____________________
Quarterly Report June 2023
Page 4
Power Supply
Boab has executed a Heads of Agreement with Horizon Power to provide a power solution for the
Sorby Hills Project that is underpinned by green energy from the Ord River Hydroelectric Power
Plant (ASX Announcement 22 April 2022). Whilst the availability of power from the hydroelectric
plant is expected to be more than 90%, the DFS conservatively included 100% redundancy in the
form of a 12MW diesel-fuelled back-up power plant located on-site.
In consultation with GRES and Horizon Power, Boab is working towards an optimised solution
whereby the need for diesel power redundancy is both reduced and potentially replaced by an
alternate power source such as an on-site solar farm. A positive outcome would further enhance
the clean energy credentials of the Sorby Hills Project, lower operating costs and reduce exposure
to fluctuations in the price of diesel.
Boab continues to work with Horizon Power on finalising the design of the power solution and the
negotiation of a Power Purchase Agreement.
Approvals
The Sorby Hills Project was first referred under the Environmental Protection and Biodiversity
Conservation Act (“EPBC”) in 2013 and was deemed “Not a Controlled Action”. The Project
subsequently received approval from the WA Environmental Protection Authority (“EPA”) in 2014.
The EPA approval was further renewed in 2019 (ASX Announcement 29 May 2019).
As part of the Sorby Hills DFS and ongoing project execution workstreams, Boab has sought two
sets of amendments to the original EPA Approval primarily relating to changes in the
“development area” with respect to the site access route and refinement of the water
management strategy within the tenements. The first of these amendments was approved in July
2022 (ASX Announcement 1 July 2022). The second amendment process is nearing completion,
with updated water balance modelling from GHD and independent third-party engineering
reports from tailings and water storage specialist Red Earth Engineering supporting the
application.
In light of the EPA amendments, and other design changes to the process plant and site layout,
Boab has decided to re-refer the Project to the Department of Climate Change, Energy, the
Environment and Water (“DCCEEW”) under the EPBC. Self-assessment by Boab utilising the
‘Protected Matters Search Tool’ has been completed on the DCCEEW website and identified no
new potential impacts from the proposed operations, outside those that were assessed previously.
Boab anticipates positive outcomes of the EPA amendment process and EPBC referral to be
received during Q3 2023.
In addition to the key approvals above, the Company continues to advance other permits and
approvals related to construction and operations including EPA Part V Works Approval, Mining
Proposal, Water Extraction Licence and Mining Operational Notification.
_____________________________________________________________________________________________________________________________ ____________________
Quarterly Report June 2023
Page 5
Concentrate Logistics
GHD has recently completed a road safety assessment for the Sorby Hills Project. The final report
will be submitted to the Shire of Wyndham and East Kimberley (SWEK) for review and
subsequently used in the application for concessional loading made to Main Roads Western
Australia. A successful concessional loading application would result in improved haulage costs
from the mine site to Wyndham Port.
During May, Cambridge Gulf Limited (“CGL”), operator of Wyndham Port, submitted a works
approval to the Western Australian Department of Water and Environmental Regulation
(“DWER”) with respect to the storage and handling of concentrate from the Sorby Hills Project.
Boab, via SHPL, has entered a Port Access and Stevedoring Services Agreement with CGL for a
term extending to at least 2034 with an option to roll over on a yearly basis thereafter (ASX
Announcement 31 March 2022).
Phase VII Drilling Program
Boab has recently announced the commencement of its Phase VII drilling campaign at Sorby Hills.
The planned drilling program comprises 2,000m across 19 diamond drill holes focused on the
Norton Deposit (see ASX Announcement 16 June 2023).
Objectives of the Phase VII drill program include enhancing conservative metallurgical recoveries
adopted for the Norton deposit in the Sorby Hills DFS and investigating high-grade mineralisation
adjacent to the current Norton deposit open pit design. The Phase VII drilling program is
anticipated to take approximately 6 weeks to complete with assay results targeted for mid Q3
2023. A successful program could see a significant increase in the metal recovered from the Norton
deposit and an increase in overall mine life. Subject to the successful completion of the drilling
and metallurgical programs Boab will likely commission an update of the Mineral Resource
Estimate in Q4 2023.
Stakeholder Engagement
Ord Valley Muster
Sense of community plays a key role in the economic and social well-being of stakeholders across
the east Kimberley Region. The Ord Valley Muster has been a highlight of the Kimberley
community calendar for 20 years.
Since 2022, Boab Metals has been the proud sponsor of the Ord Valley Muster. The 2023 edition of
the Ord Valley Muster was held between 19th-27th of May 2023 and featured a diverse range of
events & experiences including dining under the stars, music, community fair, comedy,
storytelling, and rodeo. Once again, the Ord Valley Muster was enthusiastically supported by the
Kununurra community and the large numbers of visitors who were attracted to the region and
the event was deemed hugely successful (Figure 5).
With respect to Boab, the support received from the local community for the Sorby Hills Project
has been overwhelming and provides additional impetus for the delivery of the Project.
_____________________________________________________________________________________________________________________________ ____________________
Quarterly Report June 2023
Page 6
Indigenous Engagement
Productive meetings were held with the local indigenous group the, Miriuwung Gajerrong people,
and their representatives during May and June 2023 and have significantly progressed the
definition of a mutual Benefits Agreement and outlined the pathway forward to finalising the
agreement.
Boab is committed to working collaboratively with the local Miriuwung Gajerrong people to
deliver long-term and sustainable benefits, including business and employment opportunities
and skills development.
Figure 5: Boabs Managing Director, Simon Noon speaking at the 2023 Ord Vally Muster
Financing and Offtake
Boab continues to progress constructive discussions with potential project financiers of the Sorby
Hills Project. In parallel, the lender’s Independent Technical Expert is finalising its review of the
Project, including the optimised mining schedule and updated tailings strategy.
Negotiation of offtake terms with multiple Tier-1 counterparties is substantially complete. Boab is
now exploring options for offtaker financing with these groups, to work in tandem with senior
secured debt.
Timeline to Production
Receipt of EPA amendments approval and EPBC referral outcome, completion of FEED, and
awarding of Offtake are all scheduled for completion during Q3 2023, paving the way to finalisation
of project financing arrangements and subsequently a Final Investment Decision.
_____________________________________________________________________________________________________________________________ ____________________
Quarterly Report June 2023
Page 7
Financial and Corporate Overview
The consolidated cash balance of the Company as at 30 June 2023 was A$4.6 million. During the
period, the Company paid $88k to related parties. These payments were made to Directors of Boab
Metals Limited in relation to salaries and directors’ fees, on normal commercial terms.
The Board of Directors have authorised this announcement for release to the market.
FOR FURTHER INFORMATION, PLEASE CONTACT:
Simon Noon
Managing Director & CEO
Phone: +61 (0)8 6268 0449
Email: info@BoabMetals.com
About Boab Metals Limited
Boab Metals Limited (“Boab”, ASX: BML) is a Western Australian based exploration and
development company with interests in Australia and South America. In Australia, the Company
is currently focused on developing the Sorby Hills Lead-Silver-Zinc Joint Venture Project in WA.
Boab owns a 75% interest in the Joint Venture with the remaining 25% (contributing) interest held
by HenanYuguang Gold & Lead Co. Ltd.
Sorby Hills is located 50km from the regional centre of Kununurra in the East Kimberley and has
existing sealed roads to transport concentrate from site to the facilities at Wyndham Port, a
distance of 150km. Established infrastructure and existing permitting allows for fast-track
production.
Compliance Statements
The Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves
(the ‘JORC Code’) sets out minimum standards, recommendations and guidelines for Public
Reporting in Australasia of Exploration Results, Mineral Resources and Ore Reserves.
Information included in this Quarterly Report relating to Exploration Results has been extracted
from the ASX Announcements titled “Assays Confirm Further Positive Outcome for Sorby” dated
23 January 2023, “Sorby Hills DFS Metallurgical Testwork Results” dated 19th November 2021
available to view at www.boabmetals.com.au. The Company confirms that it is not aware of any
new information or data that materially affects the information included in these announcements.
The Company confirms that the form and context in which the Competent Person’s findings are
presented have not been materially modified from the form in which they were first presented.
_____________________________________________________________________________________________________________________________ ____________________
Quarterly Report June 2023
Page 8
Information included in this Quarterly Report relating to Mineral Resources has been extracted
from the Mineral Resource Estimate dated 17 December 2021, available to view at
www.boabmetals.com.au. The Company confirms that it is not aware of any new information or
data that materially affects the information included in the Mineral Resource Estimate and that all
material assumptions and technical parameters underpinning the estimates, continue to apply
and have not materially changed. The Company confirms that the form and context in which the
Competent Person’s findings are presented have not been materially modified from the Mineral
Resource Estimate.
Information included in this Quarterly Report relating to Ore Reserves, Production Targets and
Financial Forecasts has been extracted from the Sorby Hills Definitive Feasibility Study and dated
19 January 2023, available to view at www.boabmetals.com.au. The Company confirms that it is not
aware of any new information or data that materially affects the information included in the Ore
Reserve Statement and that all material assumptions and technical parameters underpinning the
estimates, production targets and financial forecasts continue to apply and have not materially
changed. The Company confirms that the form and context in which the Competent Person’s
findings are presented have not been materially modified from the Ore Reserves Statement.
_____________________________________________________________________________________________________________________________ ____________________
Quarterly Report June 2023
Page 9
Metal Equivalent Calculation Method
The contained metal equivalence formula is based on the Sorby Hills DFS including:
•
•
•
•
•
•
Lead Price US$2,253.19/t;
Lead recovery of 91.0% (weighted average of oxide and fresh Pb recoveries);
Lead Payability rate of 95%;
Silver Price US$27.4/oz;
Silver recovery of 81.8% (weighted average of oxide and fresh Ag recoveries); and
Silver Payability rate of 95%.
It is Boab’s opinion that all elements included in the metal equivalent calculation have a
reasonable potential to be recovered and sold.
The formula used to calculate lead equivalent grade is:
MetalEq (%) = Gpri + (Gpri × [∑i Ri Si Vi Gi ]/(Rpri SpriVpriGpri))
where R is the respective metallurgical metal recovery rate, S is the respective smelter return rate,
V is metal price/tonne or ounce, and G is the metal commodity grade for the suite of potentially
recoverable commodities (i) relative to the primary metal (pri).
Metal equivalents are highly dependent on the metal prices used to derive the formula. Boab
notes that the metal equivalence method used above is a simplified approach. The metal prices
are based on the DFS values adopted and do not reflect the metal prices that a smelter would pay
for concentrate nor are any smelter penalties or charges included in the calculation. Owing to
limited metallurgical data, zinc grades are not included at this stage in the lead equivalent grade
calculation.
DFS Macroeconomic Assumptions
Assumption
Unit
FY2023
FY2024
FY2025
FY2026
FY2027+
Lead Price
US$/t
2,259
2,268
2,269
2,254
2,251
Silver Price
US$/oz
24.8
25.8
26.4
27.3
27.5
Exchange Rate
A$:US$
0.70
0.70
0.70
0.69
0.68
_____________________________________________________________________________________________________________________________ ____________________
Quarterly Report June 2023
Page 10
APPENDIX 1
INTERESTS IN TENEMENTS
Farm-In Agreements/
Projects/Tenements
Sorby Hills Project
M80/196
M80/197
M80/285
M80/286
M80/287
E80/5317
Borroloola West Project
EL31354
EL26938
EL26939
EL28508
EL28658
EL30305
MLN624
Manbarrum Project
EL24395
MA24518
MA26581
Urrao Project
2791
Location
Held at Start of
Quarter
Held at End of
Quarter
75%
75%
75%
75%
75%
100%
75%
75%
75%
75%
75%
100%
100%
51%
51%
51%
51%
51%
51%
100%
51%
51%
51%
51%
51%
51%
NT, Australia
100%
100%
100%
100%
100%
100%
Colombia
100%
100%
WA, Australia
NT, Australia
_____________________________________________________________________________________________________________________________ ____________________
Quarterly Report June 2023
Page 11
Mining Exploration Entity or Oil and Gas Exploration Entity
Quarterly Cash Flow Report
BOAB METALS LIMITED
ABN
43 107 159 713
Consolidated statement of cash flows
1
1.1
1.2
1.3
1.4
1.5
1.6
1.7
Cash flows from operating activities
Receipts from customers
Payments for
(a) exploration & evaluation (if
expensed)
(b) development
(c) production
(d) staff costs
(e) administration and corporate
costs
Dividends
received (see note 3)
Interest received
Interest and other costs of finance paid
Income taxes paid
Government grants and tax incentives
Other
1.8
Recharge of staff costs and other
administration costs to the Sorby JV
1.9
Net cash from / (used in) operating
activities
2
2.1
2.2
2.3
2.4
2.5
2.6
Cash flows from investing activities
Payments to acquire:
(a) entities
(b) tenements
(c) property, plant and
equipment
(d) exploration & evaluation (if
capitalised)
(e) investments
(f)
other non-current assets
Proceeds from the disposal of:
(a) entities
(b) tenements
(c) property, plant and
equipment
(d) investments
(e) other non-current assets
Cash flows from loans to other entities
Dividends received (see note 3)
Other (provide details if material)
Net cash from / (used in) investing
activities
Quarter ended (“current quarter”)
Current
quarter
$A’000
June 2023
Year to date
(12 months)
$A’000
-
-
(1,140)
(3,907)
(197)
(162)
54
-
(774)
(927)
96
-
40
200
(1,405)
(5,312)
--(59)(3)----
(1,734)
-----------(59)-
(1,734)
_____________________________________________________________________________________________________________________________ ____________________
Quarterly Report June 2023
Page 12
3
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
3.10
4
4.1
4.2
4.3
4.4
4.5
4.6
5
5.1
5.2
5.3
5.4
5.5
6
6.1
6.2
Cash flows from financing activities
Proceeds from issues of equity
securities (excluding convertible debt
securities)
Proceeds from issue of convertible
debt securities
Proceeds from exercise of options
Transaction costs related to issues of
equity securities or convertible debt
securities
Proceeds from borrowings
Repayment of borrowings
-
Payments to related parties of the
entity and their associates
Aggregate amount of payments to
related parties and their associates
included in item 1
Aggregate amount of payments to
related parties and their associates
included in item 2
-
-
(313)
--
-
-
5,346
6,082
6,318
(1,405)
(59)
4,618
7,172
7,500
Current
quarter
(5,312)
(1,734)
5,346
4,618
Transaction costs related to loans and
borrowings
Dividends paid
Other (provide details if material)
Net cash from / (used in) financing
activities
Net increase / (decrease) in cash and
cash equivalents for the
Cash
and cash equivalents at
Period
beginning of period
Net cash from / (used in) operating
activities
above)
Net
cash (item
from /1.9)
(used
in) investing
activities
(item
2.6)
above)
Net cash from / (used in) financing
activities
(item 3.10) above)
Effect
of movement
in exchange rates
on cash
held
Cash
and
cash equivalents at end of
period
Reconciliation of cash and cash
equivalents
at the end of the quarter (as shown in
the consolidated statement of cash
flows) to the related items in the
accounts
Bank balances
Call deposits
Bank overdrafts
Other (provide details)
Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
5,659
-
-
$A’000
Previous quarter
$A’000
1,531
3,087
--4,618
2,077
4,005
6,082
Current
quarter
$A'000
(88)*
-
_____________________________________________________________________________________________________________________________ ____________________
Quarterly Report June 2023
Page 13
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly
activity report must include a description of, and an explanation
for, such payments.
*(Salaries and Director fees paid on normal commercial terms.)
APPENDIX 5B
Financing facilities
Total
facility
amount
at quarter
end
Amount drawn
at quarter end
$A’000
$A’000
7
Note: the term “facility’ includes all
forms of financing arrangements
available to the entity.
Add notes as necessary for an
understanding of the sources of
finance available to the entity.
7.1
7.2
7.3
7.4
Loan facilities
Credit standby arrangements
Other (please specify)
Total financing facilities
7.5
Unused financing facilities available at quarter end
Include in the box below a description of each facility above, including the
lender, interest rate, maturity date and whether it is secured or unsecured. If
any additional financing facilities have been entered into or are proposed to be
entered into after quarter end, include a note providing details of those facilities
as well.
7.6
8
8.1
8.2
8.3
8.4
8.5
8.6
8.7
8.8
-
Estimated cash available for future operating activities
Net cash from / (used in) operating activities (Item 1.9)
Capitalised exploration & evaluation (Item 2.1(d))
Total relevant outgoings (Item 8.1 + Item 8.2)
Cash and cash equivalents at quarter end (Item 4.6)
Unused finance facilities available at quarter end
(Itemavailable
7.5)
Total
funding (Item 8.4 + Item 8.5)
Estimated quarters of funding available (Item 8.6
divided by Item 8.3)
-
-
--
$A’000
(1,405)
(1,405)
4,618
4,618
3.28
If Item 8.7 is less than 2 quarters, please provide
answers to the following questions:
8.8.1 Does the entity expect that it will continue to have
the current level of net operating cash flows for the
time being and, if not, why not?
Answer: N/A
_____________________________________________________________________________________________________________________________ ____________________
Quarterly Report June 2023
Page 14
8.8.2 Has the entity taken any steps, or does it propose
to take any steps, to raise further cash to fund its
operations and, if so, what are those steps and how
likely does it believe that they will be successful?
Answer: N/A
8.8.3 Does the entity expect to be able to continue its
operations and to meet its business objectives and, if so,
on what basis?
Answer: N/A
Compliance statement
1
This statement has been prepared in accordance with accounting standards and policies
which comply with Listing Rule 19.11A.
2 This statement gives a true and fair view of the matters disclosed.
Sign here:
............................................................
Date: 06 July 2023
Jerry Monzu (Company Secretary)
Authorised for release by the Board of Directors of Boab Metals Limited
Notes
1.
This quarterly cash flow report and the accompanying activity report provide a basis for
informing the market about the entity’s activities for the past quarter, how they have been
financed and the effect this has had on its cash position. An entity that wishes to disclose
additional information over and above the minimum required under the Listing Rules is
encouraged to do so.
2.
If this quarterly cash flow report has been prepared in accordance with Australian
Accounting Standards, the definitions in, and provisions of, AASB 6: Exploration for and
Evaluation of Mineral Resources and AASB 107: Statement of Cash Flows apply to this report.
If this quarterly cash flow report has been prepared in accordance with other accounting
standards agreed by ASX pursuant to Listing Rule 19.11A, the corresponding equivalent
standards apply to this report.
3.
Dividends received may be classified either as cash flows from operating activities or cash
flows from investing activities, depending on the accounting policy of the entity.
4. If this report has been authorised for release to the market by your board of directors, you
can insert here: “By the board”. If it has been authorised for release to the market by a
committee of your board of directors, you can insert here: “By the [name of board committee
– e.g. Audit and Risk Committee]”. If it has been authorised for release to the market by a
disclosure committee, you can insert here: “By the Disclosure Committee”.
_____________________________________________________________________________________________________________________________ ____________________
Quarterly Report June 2023
Page 15
5.
If this report has been authorised for release to the market by your board of directors and
you wish to hold yourself out as complying with recommendation 4.2 of the ASX Corporate
Governance Council’s Corporate Governance Principles and Recommendations , the board
should have received a declaration from its CEO and CFO that, in their opinion, the financial
records of the entity have been properly maintained, that this report complies with the
appropriate accounting standards and gives a true and fair view of the cash flows of the
entity, and that their opinion has been formed on the basis of a sound system of risk
management and internal control which is operating effectively.
_____________________________________________________________________________________________________________________________ ____________________
Quarterly Report June 2023
Page 16