2025 Annual Report
Released
Released
Announcement PDF
BOAB METALS LIMITED ANNUAL REPORT 2025
ANNUAL
REPORT
2025
CORPORATE DIRECTORY
__________________________________________________
DIRECTORS
Gary Comb (Chairman)
Simon Noon (Managing Director & CEO)
Richard Monti (Non-Executive Director)
Andrew Parker (Non-Executive Director)
COMPANY SECRETARY
Jerry Monzu
REGISTERED OFFICE
4 Clive Street
WEST PERTH WA 6005
Tel: 08 6268 0449
SHARE REGISTRY
Automic Group Pty Ltd
Level 5
191 St Georges Terrace
PERTH WA 6000
Tel: 1300 288 664
BANKERS
Australian and New Zealand Banking Group Limited
239 Murray Street
PERTH WA 6000
AUDITORS
BDO Audit Pty Ltd
Level 9, Mia Yellagonga Tower 2
5 Spring Street
Perth, WA 6000
SECURITIES EXCHANGE LISTING
Boab Metals Limited shares are listed on the
Australian Securities Exchange (Home Branch - Perth)
ASX Code: BML
WEBSITE ADDRESS
www.boabmetals.com
ANNUAL REPORT FOR THE YEAR ENDED 30 JUNE 2025
1
TABLE OF CONTENTS
__________________________________________________
Chairman’s Report
3
Managing Director’s Report
4
Review of Operations
5
Directors’ Report
12
Auditor’s Independence Declaration
27
Consolidated Statement of Profit or Loss & Other Comprehensive Income
28
Consolidated Statement of Financial Position
29
Consolidated Statement of Changes in Equity
30
Consolidated Statement of Cash Flows
31
Notes to the Financial Statements
32
Consolidated Entity Disclosure Statement
57
Directors’ Declaration
58
Independent Auditor’s Report
59
Shareholder Information
63
FORWARD LOOKING STATEMENTS
This Annual Report may contain forward looking statements. Such statements are only predictions, based on certain
assumptions and involve known and unknown risks, uncertainties, and other factors, many of which are beyond the
Company’s control. Actual events or results may differ materially from the events or results expected or implied in any
forward-looking statement. The inclusion of such statements should not be regarded as a representation, warranty, or
prediction with respect to the accuracy of the underlying assumptions or that any forward-looking statements will be or
are likely to be fulfilled. The Company undertakes no obligation to update any forward-looking statement to reflect events
or circumstances after the date of this document (subject to securities exchange disclosure requirements). The information
in this document does not consider the objectives, financial situation or needs of any person. Nothing contained in this
document constitutes investment, legal, tax, or other advice.
ANNUAL REPORT FOR THE YEAR ENDED 30 JUNE 2025
2
CHAIRMAN’S REPORT
__________________________________________________
Dear Shareholders,
On behalf of your Board of Directors, I am pleased to present the 2025 Annual Report and recap the
significant progress that Boab Metals Limited has made over the past financial year at our flagship
Sorby Hills Lead-Silver Project.
Building upon the economically robust results presented in the Sorby Hills FEED Study, the Company
has been steadily and consistently building momentum. Through the execution of a series of strategic
commercial agreements, we now have a pathway to secure 100% ownership of the Project, access to
a high-quality processing plant that will significantly de-risk the project execution schedule, and an
offtake contract with a first-class counterparty, confirming the marketability of the Sorby Hills
concentrate product. Furthermore, we are now in receipt of key state and federal environmental
approvals, permitting Boab to develop the Sorby Hills Project.
At the same time, the broader market dynamics are aligning in our favour. Silver is increasingly
recognised not only as a precious metal but also as a critical material in the global energy transition,
with demand rising from renewable technologies and electrification. With silver prices strong and longterm fundamentals supportive, we believe Boab is advancing Sorby Hills at precisely the right time to
establish itself as a meaningful new silver producer.
On behalf of the Board, I extend my thanks to our shareholders for their continued support and to our
dedicated management team for their commitment and achievements during the year. We look forward
to updating you on our progress as we take the decisive next steps in realising the full potential of Sorby
Hills.
Gary Comb
Chairman
ANNUAL REPORT FOR THE YEAR ENDED 30 JUNE 2025
3
MANAGING DIRECTOR’S REPORT
____________________________________________________
Managing Director’s Overview
The 2025 financial year has been a transformative period for Boab Metals Ltd as we advance towards a
Final Investment Decision for our flagship Sorby Hills Lead-Silver-Zinc Project in the Kimberley, Western
Australia.
Our Front-End Engineering and Design (FEED) Study, released in mid-2024, confirmed the project’s robust
economics, underpinned by low C1 operating costs of US$0.36/lb payable lead (inclusive of silver credits),
a pre-tax NPV8 of A$411 million, and a projected IRR of 37%.
Importantly, silver prices are currently trading approximately 50% higher than those assumed in the FEED
Study, materially enhancing forecast project free cash flow value.
Strategic Milestones
Over the past 12 months, we have executed several critical steps to position Sorby Hills for development:
•
Option to Acquire 100% Project Ownership: Secured an agreement to acquire our JV partner
Yuguang’s 25% interest, paving the way for full control of the project.
•
Offtake and Prepayment Agreement: Entered into a binding agreement with Trafigura for 75% of
concentrate output, securing a US$30 million prepayment facility to support project financing.
•
Processing Infrastructure: Entered into an agreement to acquire the DeGrussa Processing Plant
from Sandfire Resources, reducing capital requirements and de-risking project execution.
•
Regulatory Approvals: Achieved key amendments from the WA EPA and subsequent approval
under the EPBC Act, enabling development in line with the FEED Study.
•
Financing Progress: In addition to the Trafigura facility, we have received non-binding term sheets
from multiple domestic and international financiers, reinforcing confidence in our ability to secure
full project funding.
Corporate Highlights
To support ongoing activities, Boab successfully raised A$6 million via a placement to institutional and
professional investors and utilised our ATM facility to raise a further A$680,000.
Outlook
With major approvals secured and critical infrastructure acquired, and positive discussions within project
financiers progressing, Boab is firmly positioned to make a Final Investment Decision on Sorby Hills in H2
2025. The team remains focused on delivering this milestone and advancing Sorby Hills into construction,
establishing Boab as a significant Australian producer of lead and silver.
I’d like to take this opportunity to acknowledge all of our staff and extend my appreciation to my fellow
Board members for their invaluable guidance over the 2025 financial year. Finally, a big thank you to our
shareholders, both new and old, for their confidence in Boab Metals.
We look forward to an exciting 12 months to come
Simon Noon
Managing Director & CEO
ANNUAL REPORT FOR THE YEAR ENDED 30 JUNE 2025
4
REVIEW OF OPERATIONS
____________________________________________________
OVERVIEW
During the Financial Year to 30 June 2025, Boab Metals Ltd (“Boab”) has made significant progress
toward a Final Investment Decision at its flagship Sorby Hills Lead-Silver-Zinc Project (“Sorby Hills” or
“the Project”), located within the Kimberley Region of Western Australia.
The 2024 Financial Year concluded with the release of the Sorby Hills Front-End Engineering and Design
(“FEED”) Study1. The FEED Study outlined strong pre-tax economics including C1 operating costs of
US$0.36/lb payable Pb (incl. a net silver credit of US$0.37/lb payable Pb), NPV8 of A$411M, IRR of 37%,
A$778M free cash flow, and an average annualised EBITDA of A$126M. Pre-production capital costs were
estimated to be A$264M.
Importantly, the FEED Study demonstrates that with operating costs covered by revenue generated by a
historically non-volatile lead price, the Project free cash flow was exposed to movements in the price of
silver. Silver prices (as at 5 September 2025) are currently 50% higher than those that were assumed in
the FEED Study.
Building on the momentum of the FEED Study, the Company has delivered multiple transformative
milestones over the past 12 months in preparation for a Final Investment Decision. These include:
•
•
•
•
•
•
Execution of an Option Agreement with Joint Venture partner, Henan Yuguang Gold and Lead Co.
to acquire their interest in the Sorby Hills Project.
Execution of an Offtake Agreement for Sorby Hills concentrate and an associated US$30M
Prepayment with global commodities trader Trafigura.
Execution of binding Sale and Purchase Agreement to acquire the DeGrussa Process Plant second
hand from ASX Sandfire Resources for use at Sorby Hills.
Receipt of key amendments to the existing Western Australian Environmental Protection Authority
(EPA) approval for Sorby Hills to facilitate the development of the expanded Project in line with the
FEED Study.
Subsequent to year end, the receipt of approval under Federal Environment Protection and
Biodiversity Conservation Act 1999 (EPBC).
Receipt of non-binding Terms Sheets2 for the development of Sorby Hills from multiple domestic
and international financiers.
SORBY HILLS FEED STUDY
Sorby Hills is the largest undeveloped, near-surface Lead-Silver-Zinc deposit in Australia. The Project
comprises granted mining leases covering six known Lead-Silver-Zinc deposits in the Kimberley Region of
Western Australia, 50km northeast of Kununurra and 90km east of Wyndham Port (Figure 1). A summary
of the FEED Study results is presented in Table 1.
1
2
ASX Release 6 June 2024
Terms sheets are non-binding, discussions remain preliminary and there is no certainty that a binding agreement will be reached.
ANNUAL REPORT FOR THE YEAR ENDED 30 JUNE 2025
5
REVIEW OF OPERATIONS
____________________________________________________
Figure 1: Location of the Sorby Hills Project.
Table 1: FEED Study Results (100% basis)3
Item
Unit
FEED Study
Production Target
M Tonnes
18.3
Lead Grade
% Lead
3.4
Silver Grade
g/t Silver
38.8
Recovered Lead
kt
575
Recovered Silver
Moz
18.6
Concentrate
kt (dry)
873
Upfront Capital Cost
A$M
264
C1 Cost (incl. credits)
US$/lb Pb
0.36
A$M
778
A$M p.a.
126
Pre-Tax NPV8
A$M
411
Pre-Tax IRR
%
37%
Net Cash Flow
LOM Average EBITDA
3
FEED Study Macroeconomic assumptions: Pb 2,252/t, Silver, US$27.8/oz, A$:US$: 0.68, Lead TC US$125/t
ANNUAL REPORT FOR THE YEAR ENDED 30 JUNE 2025
6
REVIEW OF OPERATIONS
____________________________________________________
OPTION TO ACQUIRE 100% OF THE SORBY HILLS PROJECT
During the year, Boab entered into an option agreement to acquire from joint venture partner Henan
Yuguang Gold & Lead Co. Ltd’s (“Yuguang”) their 25% interest in the Sorby Hills Project (ASX release 23
September 2024).
Yuguang has been a committed joint venture partner over the past 7 years of Boab’s involvement in the
Sorby Hills Project. During this period, the joint venture has effectively grown the Mineral Resource and
completed high-quality Feasibility studies on the Project. The option agreement was reflective of this
productive and cooperative relationship and provides a new pathway to advance Sorby Hills toward a Final
Investment Decision.
Key Terms of the Option Agreement
12-month option for Boab to acquire Yuguang’s 25% interest in Sorby Hills, increasing Boab’s current 75%
interest in the Project to 100%.
During the option period, Boab will carry Yuguang’s joint venture expenses and in turn, will have full control
over joint venture budgets and work programs.
Should the option be exercised, Boab will pay Yuguang:
•
Tranche 1: A$12.5M upon exercise of the option and the concurrent acquisition of Yuguang’s 25%
Joint Venture interest;
•
Tranche 2: A$5.5M payable no later than 12 months from the commencement of concentrate
production at Sorby Hills; and
•
Tranche 3: A$5.0M payable no later than 18 months from the commencement of concentrate
production at Sorby Hills.
The ability to exercise the option is subject to Boab reaching a Final Investment Decision on the Sorby Hills
Project within the next 12 months.
Based on the results of the FEED Study, a further 218kt of lead-silver concentrate, 137kt of payable lead,
4.3Moz of payable silver and A$103M of NPV will be attributable to Boab upon exercise of the option and
the acquisition of Yuguang’s 25% interest.
Subsequent to year-end, the Company announced that the parties have mutually agreed to extend the
option period to 31 December 2025 to allow time for Boab to complete the workstreams remaining ahead
of an anticipated Final Investment Decision during Q4 2025.
BINDING PREPAYMENT AND OFFTAKE AGREEMENT
During the year, Boab (via its 100% own subsidiary Sorby Hills Pty Ltd (SHPL)) executed a binding Offtake
Agreement and associated US$30M Prepayment terms sheet with global commodities trader, Trafigura
(ASX release 10 December 2024).
Key Terms of the Prepayment and Offtake Agreements
•
The Prepayment terms include a 5-year term, an interest rate margin of SOFR + 5% and an 18month interest-free period after which repayments will be made via equal monthly instalments.
Financial Close and drawdown of the Prepayment are subject to the execution of full-form
documentation, the finalisation of outstanding due diligence, and the Project being fully-funded.
ANNUAL REPORT FOR THE YEAR ENDED 30 JUNE 2025
7
REVIEW OF OPERATIONS
____________________________________________________
•
Base Offtake terms are for 75% of the Sorby Hills Lead-Silver concentrate up to a minimum of
531,000 tonnes (~7 years based on the FEED Study production schedule) with market standard
metal payabilities, metal pricing based on spot pricing and a lead treatment charge linked to the
quoted annual benchmark.
•
Should Boab utilise alternative financing to the Prepayment or not reach financial close on the
Prepayment, Boab shall have the discretion to reduce the offtake volumes to 50% and 25%
respectively. In each case, lead treatment charges will revert to an average of the prevailing annual
benchmark and the spot lead treatment charge.
The agreements were the result of a highly competitive process including other global traders and smelters
that demonstrated the attractiveness of the Sorby Hills concentrate product and represent a key milestone
towards a Final Investment Decision on Sorby Hills and a cornerstone of Boab’s financing solution for the
Project.
DEGRUSSA PROCESSING PLANT ACQUISITION
During the year, Boab entered into a binding Sale and Purchase Agreement with Sandfire Resources
(ASX:SFR) for the acquisition of the DeGrussa Processing Plant for use at Sorby Hills (ASX release 30
April 2025).
The acquisition of the DeGrussa Processing Plant (Figure 2) represents a significant milestone in the
progression toward a Final Investment Decision at Sorby Hills. This strategic acquisition materially de-risks
the Project by securing critical processing infrastructure and reducing upfront capital expenditure
requirements.
All major components required for the Sorby Hills Processing Plant, as outlined in the FEED Study, have
now been secured through the DeGrussa acquisition (Figure 3). This includes a substantial inventory of
spare parts and processing equipment. Importantly, the plant components are well-matched to the Sorby
Hills flowsheet and are capable of supporting the Project’s targeted average annual concentrate production
of approximately 103ktpa.
The Company has commenced a competitive tender process to finalise pricing for the relocation,
reconstruction, and refurbishment of the plant infrastructure.
ANNUAL REPORT FOR THE YEAR ENDED 30 JUNE 2025
8
REVIEW OF OPERATIONS
____________________________________________________
Table 2: Key Terms of the DeGrussa Processing Plant Acquisition
Term
Details
The Purchase Price for the Assets is A$10.0M comprising
A$1.5M deposit: A$0.5M payable in cash and A$1.0M payable in cash or shares at Boab’s election;
Price
A$6.0M in cash on Completion; and
A$2.5M in cash on or before the date that is 12 months from the date of first sale or other disposal of
Concentrate produced from the Sorby Hills Tenements.
the parties agreeing an appropriate work schedule for the dismantling and removal of the Assets from
the DeGrussa Mine Site (by 15 December 2025 or otherwise agreed);
Conditions
Precedent to
Completion
the Buyer obtaining relevant regulatory approvals (no later than 12 months after the execution date
of the Sale & Purchase Agreement or as otherwise agreed); and
the Buyer confirming to Seller that its Board has approved Final Investment Decision in respect of
the Project.
Post Completion
From Completion and until the commencement of Dismantling Works, Boab will pay the cost of any
ongoing care & maintenance programs (managed by Sandfire in accordance with the Sale &
Purchase Agreement) and applicable insurances.
Figure 2: The DeGrussa Processing Plant.
ANNUAL REPORT FOR THE YEAR ENDED 30 JUNE 2025
9
REVIEW OF OPERATIONS
____________________________________________________
Figure 3: 3D Model of the Sorby Hills Processing Plant showing components of the design that have been
secured via the acquisition of the DeGrussa Processing Plant.
APPROVALS
During the year, the WA EPA provided consent to key amendments to the Sorby Hills Project existing
approval under the Environmental Protection Act (ASX release 23 December 2024).
The amendments provide Boab with scope to implement the Sorby Hills Project in line with the Project’s
FEED study, including an increase to the open pit depth and mining production rate. The amendments also
provide the opportunity for Boab to further reduce capital expenditure through an optimisation of the
proposed water management strategy and rationalisation of associated infrastructure. All EPA
amendments required under Part IV of the Environmental Protection Act to commence the implementation
of the Sorby Hills Project have been received. EPA approval to mine the Beta Pit, which is scheduled to
occur at the end of the current Project mining plan, will be sought subsequent to the commencement of
operations.
Subsequent to the year-end, Boab received approval for the development of Sorby Hills under the Federal
Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act).
PROJECT FINANCE
In addition to the US$30M Prepayment terms sheet secured from Trafigura, the Company also received
non-binding terms sheets from multiple domestic and international financiers
Based on the terms sheets received, Boab is confident of securing a financing solution for Sorby Hills that
achieves the level of gearing targeted by the Company.
The Company is targeting a Final Investment Decision in Q4 2025.
ANNUAL REPORT FOR THE YEAR ENDED 30 JUNE 2025
10
REVIEW OF OPERATIONS
____________________________________________________
CORPORATE ACTIVITIES
A$6M Placement to sophisticated, professional and institutional investors
On 23 June 2025, Boab announced that further to the ASX announcement on 16 June 2025, that it has
allotted and issued a total of 37,500,000 fully paid ordinary shares (Placement Shares) at an issue price of
A$0.16 per Placement Share to professional, sophisticated and institutional investors (Placement) to raise
A$6M(exclusive of costs).
The Placement Shares were issued pursuant to the Company’s available 15% placement capacity under
ASX Listing Rule 7.1 (14,160,490 Placement Shares) and under its additional placement capacity under
ASX Listing Rule 7.1(A) (23,339,510 Placement Shares).
At-the-market (ATM) raise
On 23 June 2025, Boab confirmed it had utilised its ATM subscription agreement (ATM) with Acuity Capital
(see announcements on 22 December 2023 and 3 May 2024) to raise A$680,000 (inclusive of costs)
through the set-off of 4,250,000 Company collateral shares previously issued to Acuity Capital under the
ATM (Set-off Shares). The Set-off shares reduce the 7,770,000 Company collateral shares which Acuity
Capital is otherwise required to return to the Company upon termination or maturity of the ATM. The Set
off Shares have a deemed issue price of A$0.16 and the proceeds will be used for general working capital
purposes.
Payment of deposit to Sandfire
On 30 April 2025, Boab announced it had entered into a binding Sale and Purchase Agreement (SPA) with
Sandfire Resources Limited (ASX: SFR) for the acquisition of the DeGrussa Processing Plant. The
Company has now completed payment of the A$1.5M deposit in accordance with the terms of the SPA
(Table 2). Boab elected to pay A$1.0M of the deposit via the issue shares to Sandfire based on 5-day
VWAP calculated as of the date of execution of the SPA (i.e. A$0.12/sh).
COMPLIANCE STATEMENTS
The Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (the
‘JORC Code”) sets out minimum standards, recommendations and guidelines for Public Reporting in
Australasia of Exploration Results, Mineral Resources and Ore Reserves.
Information included in this report relating to Mineral Resources has been extracted from the Mineral
Resource Estimate dated 17 December 2021.
Information included in this report relating to Ore Reserves, Production Targets and Financial Forecasts
has been extracted from the Sorby Hills Definitive Feasibility Study dated 19 January 2023 and the Sorby
Hills FEED Study dated 6 June 2024.
In each case, the respective announcements are available to view at www.boabmetals.com.au and the
Company confirms that it is not aware of any new information or data that materially affects the information
included and that all material assumptions and technical parameters underpinning the estimates,
production targets and financial forecasts continue to apply and have not materially changed. The
Company further confirms that the form and context in which the Competent Person’s findings are
presented have not been materially modified
ANNUAL REPORT FOR THE YEAR ENDED 30 JUNE 2025
11
DIRECTORS’ REPORT
__________________________________________________
FINANCIAL AND OPERATING REVIEW
FINANCIAL REVIEW
The Group began the financial year with a cash reserve of $5,663,582. During the year, total
exploration and development expenditures incurred by the Group amounted to $2,250,834 (2024:
$1,795,175). In line with the Group’s accounting policies, all exploration expenditure incurred in the
ordinary course of operations was expensed. The result for the year was an operating loss after income
tax of $3,840,535 (2024: $3,321.974). As at 30 June 2025, available cash funds totalled $7,528,528
(2024: $5,663,582).
OPERATING RESULTS
Summarised operating results for the year are as follows:
2025
Geographic Segments
Australia
Revenues and (loss) from ordinary activities before income tax
expense
Colombia
Revenues and profit from ordinary activities before income tax
expense
Revenue/(Loss before income tax)
Shareholder Returns
Basic Loss per share (cents per share)
Revenues
$
Results
$
174,312
(3,829,531)
-
(282)
174,312
(3,829,813)
2025
(1.63)
2024
(1.80)
SIGNIFICANT CHANGES IN THE STATE OF AFFAIRS
During the year there were no significant changes in the state of affairs of the Group other than as
disclosed in this report.
ANNUAL REPORT FOR THE YEAR ENDED 30 JUNE 2025
12
DIRECTORS’ REPORT
__________________________________________________
MATTERS SUBSEQUENT TO THE END OF THE FINANCIAL YEAR
There were no matters subsequent to the end of the financial year that materially affected the financial
accounts and required separate disclosure.
LIKELY DEVELOPMENTS AND EXPECTED RESULTS
The Group will continue exploration and development activities and to assess commercial opportunities
for corporate growth, including the acquisition of interests in projects, as they arise. Due to the
unpredictable nature of these opportunities, developments may occur at short notice.
ENVIRONMENTAL REGULATION AND PERFORMANCE
The Group is subject to substantial environmental regulation regarding its exploration activities. The
Group endeavours to maintain an appropriate standard of environmental care through awareness of,
and compliance with, new and existing environmental legislation. The Directors are not aware of any
breach of environmental legislation for the year under review.
RISK MANAGEMENT
The Board is responsible for ensuring that risks and opportunities are identified on a timely basis and
that activities are aligned with these. At this stage of the Company’s development the Board has not
established a separate risk management committee under the belief that it is crucial for all Board
members to be a part of this process.
ANNUAL REPORT FOR THE YEAR ENDED 30 JUNE 2025
13
DIRECTORS’ REPORT
__________________________________________________
RISK MANAGEMENT (CONTINUED)
The Board has several mechanisms in place to ensure that managements’ objectives are aligned with
Board identified risks. Mechanisms include board approval of a strategic plan (designed to meet
stakeholders’ needs and reduce business risk), and Board approved operating plans and budgets (with
progress monitored by the Board).
Financial Risks
The Group’s activities expose it to a variety of financial risks: market risk (including foreign currency
risk, price risk and interest rate risk), credit risk and liquidity risk. The Group’s overall risk management
program focuses on the unpredictability of financial markets and seeks to minimise potential adverse
effects on the financial performance of the Group.
Various methods are used to measure risks to which the Group is exposed, including sensitivity analysis
for interest rate, foreign exchange and other price risks, and ageing analysis for credit risk. Risk
management is carried out by the accounting team under Board approved policies covering
identification and analysis of risk exposure, risk limits, and appropriate procedures and controls.
Reporting is provided to the Board.
Environmental Risks
The Company's operations and activities are subject to the environmental laws of Australia and any
other places the Company may conduct business. As with most exploration projects, the Company's
operations and activities are expected to have an impact on the environment, particularly if advanced
exploration or mine development proceeds. The Company attempts to conduct its operations and
activities to the highest standard of environmental obligation, including compliance with all
environmental laws and regulations.
Further, the Company is unable to predict the effect of additional environmental laws and regulations
which may be adopted in the future, including whether any such laws or regulations would materially
increase the Company's cost of doing business or affect its operations in any area. There can be no
assurances that new environmental laws, regulations or stricter enforcement policies, once
implemented, will not oblige the Company to incur expenses and undertake investments which could
have a material adverse effect on the Company's operations, financial position and performance.
Regulatory Social Licence Risks
Exploration and prospective production are dependent upon the granting and maintenance of
appropriate licences, permits and regulatory consents and authorisations, which may not be granted
or may be withdrawn or by made subject to limitations at the discretion of government or regulatory
authorities. Although the authorisations may be renewed following expiry or grant (as the case may
be), there can be no assurance that such authorisations will be continued, renewed or granted, or as
to the terms of renewals or grants. If the Company cannot obtain or retain the appropriate
authorisations or there is a material delay in obtaining or renewing them or they are granted subject to
onerous conditions, then the Company's ability to conduct its exploration or development operations
may be affected.
ANNUAL REPORT FOR THE YEAR ENDED 30 JUNE 2025
14
DIRECTORS’ REPORT
__________________________________________________
RISK MANAGEMENT (CONTINUED)
Corporate Governance Risks
The Directors support and adhere to the principles of corporate governance in order to mitigate and
safeguard any potential risks in this area, recognising the need for the highest standard of corporate
behaviour and accountability. The Directors are focused on fulfilling their responsibilities individually,
and as a Board, for the benefit of all Company stakeholders. That involves recognition of, and a need
to adopt, principles of good corporate governance. The Board supports the guidelines on the
‘Principles of Good Corporate Governance and Recommendations – 4th Edition’ established by the
ASX Corporate Governance Council. Given the size and structure of the Group, the nature of its
business activities, the stage of its development and the cost of strict and detailed compliance with all
of the recommendations, it has adopted a range of modified systems, procedures and practices which
enable it to meet the principles of good corporate governance. The Groups’ practices are consistent
with the guidelines and where these do not directly relate to the recommendations in the guidelines
the Group considers that its adopted practices are appropriate. Corporate Governance policies can
be found on the Company website.
INSURANCE OF DIRECTORS AND OFFICERS
During the financial year, the Group has paid an insurance premium in respect of a Directors’ and
Officers’ Liability insurance contract. The insurance premium relates to liabilities that may arise from
an officer’s position, except for conduct involving a wilful breach of duty or improper use of information
or position to gain personal advanta