Capital Cost and Project Delivery Timeline Reductions
Released
Released
Announcement PDF
10 December 2025
Significant Capital Cost and Project Delivery
Time Reductions at Sorby Hills
Boab Metals Limited (ASX: BML) (“Boab” or “the Company”) is pleased to update the
market on capital expenditure savings realised on the Early Works program and positive
results of the Processing Plant tender for the Sorby Hills Lead-Silver Project located in
Western Australia (“Sorby Hills”, the “Project”).
HIGHLIGHTS
• Minimum A$20M reduction in the Processing Plant Capital Cost
o Tender process for the relocation, rebuild and refurbishment of the DeGrussa
Processing Plant at Sorby Hills is now complete.
o The company is now working with a shortlist of contractors and anticipates
executing a contract for the works during January 2026. Based on the tenders
received, Boab is confident a minimum A$20M cost saving can be realised
when compared to building a new plant as designed in the FEED study.
o Significantly, the construction timeline is expected to reduce by 6 months
resulting in further capital cost reductions and earlier revenue.
o The substantial existing infrastructure at the DeGrussa Processing Plant,
combined with its extensive inventory of new spares (originally costing
approximately $8 million), meaningfully reduces project execution risk by
eliminating the uncertainty normally associated with equipment procurement,
lead times, and delivery.
• A$5M reduction in the Early Works Capital Cost
o Early Works continues to progress on site with capital expenditure to date
tracking well below budget.
o Based on contracts executed, the Company expects to deliver a A$5M saving
on the Early Works program, reflecting recent efficiencies in civil design, site
establishment and bulk earthworks.
• The Company has recently secured a binding commitment for a A$236M debt
facility1
and is targeting a Final Investment Decision in coming weeks.
1
ASX Release 27 November 2025
ASX Announcement Page 2
Boab Managing Director and CEO, Simon Noon, stated:
“The combined A$25M reduction in upfront capital costs as well as a shortened
construction timeline, materially enhances the development economics of Sorby Hills.
These savings come at a time when construction inflation continues to challenge new-
build projects – further highlighting the value of the DeGrussa asset to the Project.
With a commitment for project financing now secured and the cost of the Project’s
major capital item now confirmed, the Company is well positioned for a Final Investment
Decision at Sorby Hills in the coming weeks.”
Sorby Hills Project
Sorby Hills is located 50km from the regional centre of Kununurra in the East Kimberley
of Western Australia and has access to existing sealed roads to transport concentrate
150km from the mine site to the facilities at Wyndham Port. On 6 June 2024, Boab
released the results of a Front-End Engineering & Design Study (“FEED Study”)1
on the
Project showing strong pre-tax economics including C1 operating costs of US$0.36/lb
payable Pb (incl. a net Silver credit of US$0.37/lb payable Pb), NPV8 of A$411M, IRR of 37%,
A$778M free cash flow, and an average annualised EBITDA of A$126M2
.
With operating costs covered by the revenue generated by a historically non-volatile
lead price, the free cash flow is exposed to silver. Silver is currently trading at ~US$28/oz,
more than 100% higher than assumed in the FEED Study.
Pre-production capital costs were estimated to be A$264M including A$136M for a new
Processing Plant and A$13M for Early Works.
At least A$25M of capital costs savings and a 6-month reduction in the construction
timeline is anticipated based on contracts executed to date the results of the recently
completed Processing Plant tender
DeGrussa Processing Plant
Located in the Meekatharra region of Western Australia, the world-class DeGrussa
Copper Mine was built and operated by Sandfire as their flagship project between 2011-
2024. The Plant has been on active care and maintenance since operations ceased.
The DeGrussa Processing Plant includes a primary crusher, ore storage bin, ball mill, SAG
mill, flotation circuit, concentrate and tailings thickeners and an extensive list of new
spares - all fit-for-purpose for the proposed Sorby Hills process plant flowsheet and sized
to achieve the targeted 100ktpa concentrate production rate.
An extensive list of new spares was included in the acquisition agreement with an
original cost of around $8 million.
2
ASX Release 6 June 2024
ASX Announcement Page 3
Figure: The DeGrussa Processing Plant
Figure: Early Works Excavation
ASX Announcement Page 4
This announcement has been authorised for release by the Board of Boab Metals
Limited.
FOR FURTHER INFORMATION, PLEASE CONTACT:
Simon Noon
Managing Director & CEO
Phone: +61 (0)8 6268 0449
Email: info@boabmetals.com
About Boab Metals Limited
Boab Metals Limited (“Boab”, ASX: BML) is a Western Australian (WA) based exploration
and development company. The Company is focused on developing the Sorby Hills
Project in WA. Sorby Hills is located 50km from Kununurra in the East Kimberley and has
access to existing sealed roads to transport concentrate the 150km from site to the
facilities at Wyndham Port. Boab owns a 75% interest in the Project with the remaining
25% interest held by Henan Yuguang Gold & Lead Co. Ltd. Boab holds an option to
acquire Yuguang’s interest in the Project upon reaching a Final Investment Decision.
Compliance Statements
The Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves
(the ‘JORC Code’) sets out minimum standards, recommendations and guidelines for Public
Reporting in Australasia of Exploration Results, Mineral Resources and Ore Reserves.
Information included in these activities report relating to Mineral Resources has been extracted
from the Mineral Resource Estimate dated 17 December 2021, available to view at
www.boabmetals.com.au. The Company confirms that it is not aware of any new information or
data that materially affects the information included in the Mineral Resource Estimate and that
all material assumptions and technical parameters underpinning the estimates, continue to
apply and have not materially changed. The Company confirms that the form and context in
which the Competent Person’s findings are presented have not been materially modified from
the Mineral Resource Estimate.
Information included in this announcement relating to Ore Reserves, has been extracted from
the Sorby Hills Definitive Feasibility Study and dated 19 January 2023, Information included in in
this announcement report relating to Production Targets and Financial Forecasts has been
extracted from the Sorby Hills FEED Study and dated 6 June 2024. Announcements are available
to view at www.boabmetals.com.au. The Company confirms that it is not aware of any new
information or data that materially affects the information included in the Ore Reserve Statement
and that all material assumptions and technical parameters underpinning the estimates,
production targets and financial forecasts continue to apply and have not materially changed.
The Company confirms that the form and context in which the Competent Person’s findings are
presented have not been materially modified from the Ore Reserves Statement.