Sorby Hills Construction Activities Advancing
Released
Released
Announcement PDF
25 February 2026
Sorby Hills Construction Activities Advancing
Boab Metals Limited (ASX: BML) is pleased to provide an update on construction and
development activities at its 100% owned and fully funded Sorby Hills silver-lead
Project in Western Australia. Following a Final Investment Decision in late 2025, the
Project is advancing toward first production which is targeted for the second half of
2027.
Highlights
• Early works program progressing and on track for completion in early April 2026.
• Mine-site camp pad and first level of the processing plant and non-process
infrastructure pads are now completed.
• Main access road construction is underway, with road base production in
progress.
• Bulk earthworks contract awarded with mobilisation set to commence in March.
• Refurbishment of existing camp infrastructure is underway.
• Key contracts, including those for the dismantling, relocation and rebuild of the
DeGrussa Processing Plant at Sorby Hills, are nearing execution.
• Engineering and planning are underway for process plant relocation.
• Power supply discussions are progressing with Horizon Power.
• First production is targeted for the second half of 2027.
Sorby Hills is a shallow, open pit silver-lead project located approximately 50km from
Kununurra in the East Kimberley region of Western Australia. The Project benefits
from existing infrastructure, including sealed road access and proximity to Wyndham
Port, supporting efficient transport of concentrate to export markets. BML has
environmental approvals in place and project execution underway and once in
production, Sorby Hills is expected to produce an average of 2.2 million ounces of
silver per annum placing it amongst Australia’s largest silver producers.
Early works activities continue to progress well and remain on track for completion in
early April 2026. The camp pad has been completed, and the camp access road sub-
base is now in place. The first level of both the process plant pad and non-process
infrastructure (NPI) pad has also been completed.
Construction of the main access road is underway and is approximately 10% complete.
Crushing of road base material is progressing on site, with approximately 25% of the
required material already produced.
The bulk earthworks contract has been awarded, with initial site establishment
activities completed including the setup of a workshop and site office. Mobilisation of
additional equipment is scheduled to commence in March ahead of a planned start
to bulk earthworks in April.
Refurbishment of accommodation blocks for the mine-site camp is underway. The
camp office and water treatment plant have been purchased and are being prepared
for transport to site, with procurement of additional camp buildings ongoing.
Key project contracts continue to advance, with the early works, bulk earthworks and
camp contracts now executed. Negotiations are progressing with preferred
contractors for the processing plant and NPI work packages. Procurement and
planning activities for the process plant relocation are already underway.
Negotiations are also underway for fuel storage and supply.
Boab Metals Managing Director and CEO Simon Noon said:
“It is very encouraging to see construction activities progressing ahead of schedule
at Sorby Hills. With early works nearing completion and major earthworks set to
commence shortly, the project is continuing to build strong momentum as we move
toward full-scale construction.”
The Company will continue to provide updates as development of the Sorby Hills
Project progresses.
This ASX announcement has been approved by the Managing Director on behalf of
the Board of Boab Metals Limited.
FOR FURTHER INFORMATION, PLEASE CONTACT:
Simon Noon
Managing Director & CEO
Phone: +61 (0)8 6268 0449
Email: info@boabmetals.com
About Boab Metals Limited
Boab Metals Limited (“Boab”, ASX: BML) is a Western Australian (WA)-based base and
precious metals company advancing the fully funded 100%-owned Sorby Hills Silver-
Lead Project in the East Kimberley. The Project, located 50km from Kununurra, has
excellent access to existing sealed roads for transporting concentrate 150km to
Wyndham Port. Following a Final Investment Decision in December 2025, the
Company is advancing the Project toward first concentrate production in H2 2027,
positioning Boab to capitalise on strong silver and lead market fundamentals and
deliver long-term shareholder value.