Two New Ni Sulphide Zones Grows Maibele Resource Potential
Released
Released
Announcement PDF
ABN 96 122 995 073
ASX Code: BML
TO:
COMPANY ANNOUNCEMENTS OFFICE
ASX LIMITED
DATE:
1 JULY 2015
TWO NEW NICKEL SULPHIDE ZONES GROWS MAIBELE NORTH
RESOURCE POTENTIAL
The Board of Botswana Metals Limited is pleased to announce significant
drilling intercepts in two new zones never previously drilled which now have
the potential to significantly redefine the size and extend the known Maibele
North mineralisation.
Figure 1: Shows infill and step out holes drilled and proposed to be drilled. SQUID targets so
far drilled have all encountered mineralisation with at least three more planned with one hole
up to 1km to the east of Maibele North resource.
Botswana Metals Limited
Mailing Address Suite 3, 16 Cotham Road, Kew, Victoria 3101
Registered Office Suite 506, Level 5, 1 Princess Street, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
Overview:
•
•
Three step out holes all intersected sulphide mineralisation
Current resource has potential to grow through:
Step out Hole MAR0106: some 200m below the known Maibele North
ore body intersected 25m of mineralised sulphides over 2 zones: 9m from
289m and 16m from 359m.
Step out Hole: MARD0094 some 250m to the east of the Maibele North
resource intersected 6.82m of sulphides from 450m (drilled in 2014).
Step out Hole MRD0099: some 400m to the east of the Maibele North
resource intersected 5m of sulphides from 245m
• SQUID technology: (superconducting quantum interference device)
all three step out holes drilled TDEM targets identified using SQUID
technology have intersected sulphides returning a 100% success rate.
Additional SQUID TDEM targets up to 1km to the east of the main Maibele
North resource ore body are to be drilled.
Although hole MARD0099 and MARD0106 deviated in direction and missed the
target conductors, they both still intersected significant disseminated sulphide
mineralisation that demonstrates the extent of the mineralising system at Maibele
North.
INFILL /MET DRILLING:
Infill and Met drilling into the main resource ore body continues with excellent
intercepts.
More significant sulphide mineralisation encountered in holes are:
•
•
•
MARD0105: intersected 21m of sulphide mineralisation from 171m depth.
This hole is located towards the eastern end of the modelled Maibele North
mineralised zone.
MARD0103:intersected a cumulative 31m down-hole zone of sulphide
mineralisation including: 9.2 m from 112.5m and a thicker section of 21m
from 125m.
MARD0101: intersected 4.6m of sulphide mineralisation from 119m.
The drill cores are being cut for laboratory analysis.
Botswana Metals Limited
Mailing Address Suite 3, 16 Cotham Road, Kew, Victoria 3101
Registered Office Suite 506, Level 5, 1 Princess Street, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
These latest results confirm that the Maibele North ore body is open to the east, west
and at depth with the known step out hole intercepts opening up the potential to
significantly increase the size of the Maibele North current JORC 2012 inferred
resource of 2.38mt.
The drill program has completed ~ 2500m of drilling from a planned ~8000m with 3
rigs now on site
Details
The Board of Botswana Metals Limited (BML) is pleased to announce the
continuing and encouraging progress of the 8000m drilling program currently
underway at the Company’s Maibele North project in Botswana.
The aggressive 8000m drill program commenced in June 2015 and is designed to:
o
o
o
infill the known resource to lift the JORC category from inferred to indicated;
provide more met work samples for testing and optimising the ore
performance with the BCL plant; and
Step out drilling to potentially increase the known resource significantly.
Figure 2: Long Section, looking to the Northwest showing the Ni accumulation (yellow
shading), historic drill pierce points and the pierce points from the recently completed holes.
Blue rectangles represent EM conductors projected onto the plane.
Botswana Metals Limited
Mailing Address Suite 3, 16 Cotham Road, Kew, Victoria 3101
Registered Office Suite 506, Level 5, 1 Princess Street, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
Step-out Holes
A series of 5 step-out holes have been planned for the campaign with one step out
hole MAR0094 completed in late 2014. These holes are designed to test a number of
along strike and adjacent EM conductors for the presence of additional sulphide
mineralisation. Conductor targets have been identified using Down Hole EM as well
as ground SQUID EM technology. The SQUID system employs cutting edge, ultrasensitive electro-magnetic sensors to detect conductors far deeper than conventional
EM technology. Any sulphide mineralisation encountered in this drilling has the
potential to increase the extent of mineralisation at Maibele North. To date, three
step-out holes, MARD0094, MARD0099 and MARD0106 have been completed.
MARD0099: Drilled approximately 400m along strike to the east of the main Maibele
North orebody to test a large SQUID EM conductor. The hole deviated vertically a
considerable amount and passed beneath the intended target conductor. Despite
this, the hole intersected a 5m (down-hole) zone of disseminated and veinlet-style
sulphide mineralisation containing pyrrhotite and chalcopyrite from 245m. This zone
lies on the interpreted extension of the bottom edge of the modelled conductor and
provides great encouragement that the original target conductor could represent a
significant sulphide accumulation.
Botswana Metals Limited
Mailing Address Suite 3, 16 Cotham Road, Kew, Victoria 3101
Registered Office Suite 506, Level 5, 1 Princess Street, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
Figure 3: Cross section, looking northeast, through step-out hole MARD0099. Note the
significant drop in the drill trace and the result miss of the modelled EM conductor (blue line).
The sulphide mineralisation (red) in the drill hole lies directly beneath the modelled conductor.
MARD0106: drilled to test a DHEM conductor in the hangingwall of the Maibele North
orebody detected from surveys at the end of the 2014 drilling campaign. This hole
also deviated and passed beneath the intended modelled conductor. The hole did
however intersect two separate zones of disseminated sulphide mineralisation; 9m
from 289m and 16m from 359.2m. The first zone lies at the bottom edge of the
modelled hangingwall conductor and provides great encouragement for the presence
of significant sulphide accumulations adjacent to the Maibele North orebody. The
second zone lies some 200m in the down-dip direction of the Maibele North orebody
and potentially represents a much deeper portion of the Maibele North mineralisation.
Figure 4: Cross section, looking northeast, through step-out hole MARD0106. Note the drop
in the drill trace and the result miss of the modelled EM conductor (blue line). The first
sulphide zone (red) in the drill hole lies directly beneath the modelled conductor and the
second, at the bottom of the hole, lies in the extended down-dip position of the Maibele North
orebody.
Botswana Metals Limited
Mailing Address Suite 3, 16 Cotham Road, Kew, Victoria 3101
Registered Office Suite 506, Level 5, 1 Princess Street, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
Metallurgical / Infill Holes
MARD0104: was drilled to collect metallurgical sample material within the existing
extents of the Maibele North orebody and intersected 4.2m (down hole) of sulphide
mineralisation from 111.53m, including 0.97m of massive sulphide material.
MARD0105: was drilled to collect metallurgical sample material towards the eastern
extents of the Maibele North orebody and intersected 20.68m (down-hole) of
sulphide mineralisation from 171.32m, including 0.24m of massive sulphide material.
This zone appears to be thicker than that intersected in older holes in the vicinity and
provides great encouragement for the quality of mineralisation along strike to the
east.
Botswana Metals Limited
Mailing Address Suite 3, 16 Cotham Road, Kew, Victoria 3101
Registered Office Suite 506, Level 5, 1 Princess Street, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
Figure 5: Cross section, looking northeast, through met hole MARD0105. The thick sulphide
mineralisation (red) in the drill hole lies within the modelled extent of the Maibele North
orebody.
Comment
The Board of Botswana Metals is extremely excited by the continuing good results
from the current drilling campaign. The Metallurgical holes completed so far
demonstrate the quality of the Maibele North orebody and will be important in the
ongoing assessment of the mining potential at Maibele North.
Botswana Metals Limited
Mailing Address Suite 3, 16 Cotham Road, Kew, Victoria 3101
Registered Office Suite 506, Level 5, 1 Princess Street, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
The three step-out holes both demonstrate that the sulphide mineralised system
extends well beyond the modelled extents of the current orebody. Although both
holes did not intersect their intended targets, the presence of significant amounts of
sulphide mineralisation peripheral to the target zones indicates that the modelled
conductors identified by the SQUID and DHEM surveys have a high probability of
representing significant sulphide accumulations. A number of large conductors
have been modelled along strike and adjacent to Maibele North and remain to
be tested. The demonstrated effectiveness of the EM technology employed by
BML/BCL to detect sulphides provides great encouragement that further
mineralisation will be discovered at Maibele North.
SQUID EM TECHNOLOGY:
A SQUID (superconducting quantum interference device) is a very sensitive
magnetometer used to measure extremely subtle magnetic fields, based on
superconducting loops containing Josephson junctions. The SQUID technology has
many uses and is often employed in the medical industry in such application as
Magnetic Resonance Imaging (MRI). In minerals exploration, the SQUID EM
technique can be used to accurately detect very deep conductors potentially
associated with sulphide accumulations.
The market will be kept informed on progress of the drilling
For more information:
Pat Volpe
Chairman
Tel: +61 3 9855 1885
Fax: +61 3 9855 2885
Email: patv@botswanametals.com.au
Web: www.botswanametals.com.au
The information in this report that relates to Exploration Results is based on, and fairly
represents, information and supporting documentation compiled by BML staff on site and
provided to Mr Steve Groves who is a Member of The Australasian Institute of Mining and
Metallurgy. Mr Groves is a consulting geologist to BML and has previously been employed as
the Exploration Manager at BML. Mr Groves has sufficient experience which is relevant to the
style of mineralisation and type of deposit under consideration and to the activity which he is
undertaking to qualify as a Competent Person as defined in the 2012 Edition of the
‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore
Reserves’. Mr Groves consents to the inclusion in this report of the matters based on his
information in the form and context in which it appears.
Botswana Metals Limited
Mailing Address Suite 3, 16 Cotham Road, Kew, Victoria 3101
Registered Office Suite 506, Level 5, 1 Princess Street, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
Section 1 Sampling Techniques and Data
(Criteria in this section apply to all succeeding sections.)
CRITERIA
JORC Code Explanation
Commentary
Sampling
techniques
- Nature and quality of sampling
(eg cut channels, random chips,
or specific specialised industry
standard measurement tools
appropriate to the minerals under
investigation, such as down hole
gamma sondes, or handheld
XRF instruments, etc). These
examples should not be taken as
limiting the broad meaning of
sampling.
- Include reference to measures
taken to ensure sample
representivity and the
appropriate calibration of any
measurement tools or systems
used.
- Aspects of the determination of
mineralisation that are Material to
the Public Report.
- In cases where ‘industry
standard’ work has been done
this would be relatively simple
(eg ‘reverse circulation drilling
was used to obtain 1 m samples
from which 3 kg was pulverised
to produce a 30 g charge for fire
assay’). In other cases more
explanation may be required,
such as where there is coarse
gold that has inherent sampling
problems. Unusual commodities
or mineralisation types (eg
submarine nodules) may
warrant disclosure of detailed
information.
•
•
•
Drill core is neatly arranged
in 1 m core trays for HQ core
(mainly oxidised horizon) and
1.5 m core trays for NQ core
(mainly competent rock).
Core is marked at every
metre along an orientation
line and later marked at 0.05
m for handheld XRF analysis.
Spot analysis at every 0.05 m
interval is analysed at the
BML site office in Tshokwe
using
a
portable XRF
analyser (INNOV-X Delta
Premium). Standards and
blanks are used to monitor
the
calibration
of
the
instrument.
The spot values are then
averaged at 0.5 m intervals,
to give an estimated grade at
0.5 m intervals. This estimate
is only used as a guide to
determine where core should
be sampled and analysed by
the laboratory
Botswana Metals Limited
Mailing Address Suite 3, 16 Cotham Road, Kew, Victoria 3101
Registered Office Suite 506, Level 5, 1 Princess Street, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
CRITERIA
JORC Code Explanation
Commentary
Drilling
techniques
- Drill type (eg core, reverse
circulation ,open-hole hammer,
rotary air blast, auger, Bangka,
sonic, etc) and details (eg core
diameter, triple or standard tube,
depth of diamond tails, face
sampling bit or other type,
whether core is oriented and if
so, by what method, etc).
•
•
Drill sample
recovery
- Method of recording and
assessing core and chip
sample recoveries and
results assessed.
- Measures taken to maximise
sample recovery and ensure
representative nature of the
samples.
- Whether a relationship exists
between sample recovery
and grade and whether
sample bias may have
occurred due to preferential
loss/gain of fine/coarse
material.
•
•
•
The drillhole is pre-collared
with HQ in the weathered
rock. HQ pre-collars range
from 15 m to 30 m using a
standard tube. NQ diamond
core drilling is used to
complete the hole.
Weathered rock is too friable
to orientate using the spear
method. Only the competent
rock is orientated (from
approximately 30 m to the
end of hole).
Drillholes are mostly
orientated between 320° and
350°, inclined between 50°
and 65°.
The core length is measured
after every run. Results are
compared to the actual run
length to calculate core
recoveries. Core is handled
with care to avoid breakage
and crumbling. Core is
washed and placed onto
holding core trays.
HQ is used on friable ground,
rotation speeds and water
pressure are monitored to
avoid destroying the core. A
soft rubber mallet is used to
drive out core from the barrel.
Overall core recovery in the
mineralised zones is >98%.
Botswana Metals Limited
Mailing Address Suite 3, 16 Cotham Road, Kew, Victoria 3101
Registered Office Suite 506, Level 5, 1 Princess Street, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
CRITERIA
JORC Code Explanation
Commentary
Logging
- Whether core and chip samples
have been geologically and
geotechnically logged to a level
of detail to support appropriate
Mineral Resource estimation,
mining studies and
metallurgical studies.
- Whether logging is
qualitative or quantitative in
nature. Core (or costean,
channel, etc) photography.
- The total length and
percentage of the relevant
intersections logged.
•
- If core, whether cut or sawn
and whether quarter, half or
all core taken.
- If non-core, whether riffled, tube
sampled, rotary split, etc and
whether sampled wet or dry.
- For all sample types, the
nature, quality and
appropriateness of the sample
preparation technique.
- Quality control procedures
adopted for all sub-sampling
stages to maximise
representivity of samples.
- Measures taken to ensure that
the sampling is representative
of the in situ material collected,
including for instance results for
field duplicate/second-half
sampling.
- Whether sample sizes are
appropriate to the grain size
of the material being
sampled.
•
Subsampling
techniques
and sample
preparation
•
•
Core is washed and stored in
diamond core trays in both 1
m and 1.5 m intervals,
depending on whether the
material recovered is
oxidised or fresh. Diamond
core is visually inspected,
recording lithology,
weathering, alteration,
mineralisation, veining and
structure. The core is also
geotechnically logged for
RQD.
Core photography is
performed on every hole with
photos having two full core
trays with clear interval
details on a white
background. Wet and dry
core is photographed.
All relevant drilling is
diamond core drilling in the
mineralised and surrounding
zones. Core is cut
longitudinally along an
orientation line with half core
used for metallurgical test
work. The remaining half
core is cut into quarters for
lab assaying and storage.
A sub-sampling approach is
applied for SG whereby 1015 cm samples are taken
from specific rock types
Botswana Metals Limited
Mailing Address Suite 3, 16 Cotham Road, Kew, Victoria 3101
Registered Office Suite 506, Level 5, 1 Princess Street, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
CRITERIA
JORC Code Explanation
Commentary
Quality of
assay data
and
laboratory
tests
- The nature, quality and
appropriateness of the
assaying and laboratory
procedures used and whether
the technique is considered
partial or total.
- For geophysical tools,
spectrometers, handheld
XRF instruments, etc, the
parameters used in
determining the analysis
including instrument make
and model, reading times,
calibrations factors applied
and their derivation, etc.
- Nature of quality control
procedures adopted (eg
standards, blanks, duplicates,
external laboratory checks)
and whether acceptable levels
of accuracy (ie lack of bias)
and precision have been
established.
- The verification of significant
intersections by either
independent or alternative
company personnel.
- The use of twinned holes.
- Documentation of primary
data, data entry procedures,
data verification, data storage
•
Verification
of sampling
and
assaying
•
•
•
•
An Olympus Innov-X Delta
Premium
portable
XRF
analyser was used to guide
core sampling.
Blanks,
duplicates
and
standards are inserted at a
rate of approximately 13%,
although the blank material is
appears to have elevated
values of Ni and Cu. The
duplicates are prepared and
inserted by the laboratory
and are not inserted blindly
by the onsite geologist. The
performance of the CRM
analyses is acceptable.
No verification work of
significant intersections has
been completed
The Competent Person
confirmed the collar positions
and sampling intervals
onsite.
No twin holes have been
Botswana Metals Limited
Mailing Address Suite 3, 16 Cotham Road, Kew, Victoria 3101
Registered Office Suite 506, Level 5, 1 Princess Street, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
CRITERIA
JORC Code Explanation
Commentary
(physical
and
electronic)
protocols.
- Discuss any adjustment to assay
data.
Location
of data
points
Data spacing
and
distribution
•
- Accuracy and quality of
surveys used to locate drill
holes (collar and down-hole
surveys), trenches, mine
workings and other locations
used in Mineral Resource
estimation.
- Specification of the grid system
used.
- Quality and adequacy of
topographic control.
-
- Data spacing for reporting of
Exploration Results.
- Whether the data spacing and
distribution is sufficient to
establish the degree of
geological and grade continuity
appropriate for the Mineral
Resource and Ore Reserve
estimation procedure(s) and
classifications applied.
- Whether sample
compositing has been
applied.
•
•
•
•
•
•
•
drilled
No statistical adjustments to
data have been applied
All of the drillhole collars
have been surveyed using a
DGPS.
A number of drillhole collars
have been observed by MSA
in the field.
Down-the-hole surveys were
conducted for all holes.
The grid system for the
project is UTM WGS84.
The topography model was
derived from the drillhole
collar elevations and
modelled in Leapfrog.
The drillholes were spaced at
an average of 50 m apart on
strike and from 25 m to 50 m
on dip (along the drilling
fence).
The drillhole spacing is
sufficient to assume
geological and grade
continuity for this type of
mineralisation but insufficient
for grade continuity to be
confirmed.
Samples have been
composited according to
mineralisation zone.
Botswana Metals Limited
Mailing Address Suite 3, 16 Cotham Road, Kew, Victoria 3101
Registered Office Suite 506, Level 5, 1 Princess Street, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
Orientation
of data in
relation to
geological
structure
- Whether the orientation of
sampling achieves unbiased
sampling of possible
structures and the extent to
which this is known,
considering the deposit type.
- If the relationship between the
drilling orientation and the
orientation of key mineralised
structures is considered to have
introduced a sampling bias, this
should be assessed and
reported if material.
•
Sample
security
- The measures taken to ensure
sample
security.
- The results of any audits or
reviews of
sampling techniques and data.
Appropriate chain-of-custody
procedures were followed to
ensure sample security.
• The data were examined by
the independent consultant Mr
Steve Groves of Perth in
Australia and considered
appropriate.
Audits or
reviews
Drillholes are mostly
orientated between 320° and
350°, with dips ranging from
50° to 65° to perpendicularly
intersect mineralisation.
•
Section 2 Reporting of Exploration Results
(Criteria in this section apply to all succeeding sections.)
CRITERIA
JORC Code Explanation
Commentary
Mineral
tenement
and land
tenure status
• Type, reference name/number,
location and ownership
including agreements or
material issues with third
parties such as joint ventures,
partnerships, overriding
royalties, native title interests,
historical sites, wilderness or
national park and
environmental settings.
• The security of the tenure
held at the time of reporting
along with any known
impediments to obtaining a
licence to operate in the area.
• The results reported in this
announcement are located in
PL110/94 which is a granted
Exploration Licence held by
African Metals Limited, a 100%
owned subsidiary of Botswana
Metals Limited.
• PL110/94 is subject to a Joint
Venture agreement with BCL
Limited.
• PL110/94 was recently
extended for a further two years
and is in good standing.
Botswana Metals Limited
Mailing Address Suite 3, 16 Cotham Road, Kew, Victoria 3101
Registered Office Suite 506, Level 5, 1 Princess Street, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
CRITERIA
JORC Code Explanation
Commentary
Exploration
done by other
parties
• Acknowledgment and appraisal
of
exploration by other parties.
• Interpretations and conclusions
in this announcement refer in
part to results generated by
historic exploration work
conducted by Roan Selection
Trust, Falconbridge, Cardia
Mining and Botswana Metals.
• Botswana Metals considers all
previous exploration work to
have been undertaken to an
appropriate professional
standard.
Geology
• Deposit type, geological
setting and style of
mineralisation.
• The Maibele North Prospect is
hosted
within
the
Magogaphate Shear Zone - a
major geological structural
feature, generally considered
to mark the boundary between
the Archaean aged (>2.5
billion year old) Zimbabwean
Craton and the Limpopo Belt
or Limpopo Mobile Zone
(LMZ). . The nickel-copper
deposits of Selebi Phikwe lie
within the northern part of the
Central Zone of the Limpopo
Mobile Belt, whilst the nickel
copper deposits of Phoenix,
Selkirk and Tekwane lie in the
Zimbabwean
Craton.
The
Central Zone of the LMZ
comprises variably deformed
banded gneisses and granitic
gneisses,
infolded
amphibolites and ultramafic
intrusions that that have the
potential
to
host
Ni-Cu
sulphide mineralization. Ni-CuPGE mineralization at Maibele
North and Airstrip copper is
spatially associated with an
ultramafic intrusion.
Botswana Metals Limited
Mailing Address Suite 3, 16 Cotham Road, Kew, Victoria 3101
Registered Office Suite 506, Level 5, 1 Princess Street, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
CRITERIA
JORC Code Explanation
Commentary
Drill hole
Information
• A summary of all information
material to the understanding
of the exploration results
including a tabulation of the
following information for all
material drill holes:
o easting and northing of
the drill hole collar
o elevation or RL (Reduced
Level – elevation above
sea level in metres) of the
drill hole collar
o dip and azimuth of the hole
o down hole length and
interception depth
o hole length.
• If the exclusion of this
information is justified on the
basis that the information is not
Material and this exclusion
does not detract from the
understanding of the report, the
Competent Person should
clearly explain why this is the
case.
• In reporting Exploration
Results, weighting averaging
techniques, maximum and/or
minimum grade truncations
(eg cutting of high grades) and
cut-off grades are usually
Material and should be stated.
• Where aggregate intercepts
incorporate short lengths of
high grade results and longer
lengths of low grade results,
the procedure used for such
aggregation should be stated
and some typical examples of
such aggregations should be
shown in detail.
• The assumptions used for
any reporting of metal
equivalent values should be
•
Data
aggregation
methods
Refer to Appendix 1.
With regards to the MRE:
• Mineralised intersections are
composited to 2 m lengths per
Zone.
• No discernible relationship
exists regarding sample length
and grade.
With Regards to reported drill
intersections
• Where uneven sampling
intervals have contributed to
an averaged result, the result
has been calculated by a
weighted average technique
that incorporates the interval
width of each contributing
sample.
• A grade cut off of 0.3% and
internal dilution of <2m has
Botswana Metals Limited
Mailing Address Suite 3, 16 Cotham Road, Kew, Victoria 3101
Registered Office Suite 506, Level 5, 1 Princess Street, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
CRITERIA
JORC Code Explanation
clearly stated.
Relationship
between
mineralisatio
n widths and
intercept
lengths
• These relationships are
particularly important in the
reporting of Exploration
Results.
• If the geometry of the
mineralisation with respect to
the drill hole angle is known,
its nature should be reported.
• If it is not known and only the
down hole lengths are
Commentary
been used in the calculation of
significant intercepts.
• No grade truncations have
been applied to the data.
• The Maibele North ore is
interpreted to be genetically and
mineralogically similar to the ore
treated at the nearby Selebi
Phikwe smelter where current
recovery grades in the flotation
plant average 84% for Ni and
95% for Cu. Where Ni Eqv
calculations have been
undertaken on historic assay
results it has been assumed
that similar high recoveries will
be achievable. The current drill
program has been designed to
assess the metallurgical
properties of the Maibele North
mineralisation and the indicative
recoveries will be published in
due course.
• Given that that the Maibele
North project is currently the
subject of a Joint Venture with
the nearby Mine and Smelter
operator, BCL, BML assumes
that no impediments in
recovering and selling the
metals contained in the deposit
would exist provided an viable
economic resource can be
defined.
• The precise geometry of
the mineralization with
respect to the drill hole
angle is not known and
thus, all drill hole results
are reported as down hole
length.
• The drill holes in the current
program are inclined
reconnaissance holes based on
Botswana Metals Limited
Mailing Address Suite 3, 16 Cotham Road, Kew, Victoria 3101
Registered Office Suite 506, Level 5, 1 Princess Street, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
CRITERIA
JORC Code Explanation
Commentary
reported, there should be a
clear statement to this effect
(eg ‘down hole length, true
width not known’).
the average dip of exposed
units. The orientation of the
mineralization is unknown and
true width is unknown.
• Geotechnical logging is under
way to address the geometry
Share your feedback