Corporate Presentation
Released
Released
Announcement PDF
A near-term producer in Australia with a margin
highly leveraged to the Silver Price
Corporate Presentation
International Mining and Resources Conference (IMARC)
October 2024
ASX: BML
boabmetals.com
Delivering metals for a sustainable future
2
Disclaimer
Forward-Looking Statements
Compliance Statement
Certain statements in the presentation are or may be “forward-looking statements” and
represent the Company’s intentions, projections, expectations or beliefs concerning,
among other things, future operating and exploration results or the Company’s future
performance. These forward-looking statements speak, and the presentation generally
speaks, only at the date hereof. The projections, estimates and beliefs contained in such
forward-looking statements necessarily involve known and unknown risks and
uncertainties, and are necessarily based on assumptions, which may cause the
Company’s actual performance and results in future periods to differ materially from
any express or implied estimates or projections.
The Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore
Reserves (the ‘JORC Code’) sets out minimum standards, recommendations and
guidelines for Public Reporting in Australasia of Exploration Results, Mineral Resources
and Ore Reserves.
General Disclaimer
The information in this presentation remains subject to change without notice. This
presentation may contain information (including information derived from publicly
available sources) that has not been independently verified by the Company.
Not an Offer
This presentation is for information purposes only. The presentation does not comprise
a prospectus, product disclosure statement or other offering document under
Australian law. The presentation does not constitute or form part of any invitation, offer
for sale or subscription or any solicitation for any offer to buy or subscribe for any shares
in Boab Metals Limited.
No Liability
Boab Metals Limited has prepared this document based on information available at the
time of preparation. No representation or warranty, express or implied is made as to the
fairness, accuracy or completeness of the information, opinions and conclusions
contained in this presentation. To the maximum extent permitted by law, Boab Metals
Limited, its related bodies corporate and the officers, directors, employees, advisers and
agents of those entities do not accept any responsibility or liability for any loss arising
from the use of the presentation or its contents or otherwise arising in connection with
it.
Information included in this presentation relating to Exploration Results has been
extracted from the ASX Announcements titled “Keep confirmed as a Target for Further
Exploration” dated 22 October 2024, “Amended Drilling Announcement” dated 4
September 2023”, “Assays Confirm Further Positive Outcome for Sorby” dated 23
January 2023, “High-Grade Lead-Silver Confirmed at Beta Deposit” dated 1 February
2022 available to view at www.boabmetals.com.au. The Company confirms that it is not
aware of any new information or data that materially affects the information included in
these announcements. The Company confirms that the form and context in which the
Competent Person’s findings are presented have not been materially modified from the
form in which they were first presented.
Information included in this presentation relating to Mineral Resources has been
extracted from the Mineral Resource Estimate dated 17 December 2021, available to
view at www.boabmetals.com.au. The Company confirms that it is not aware of any new
information or data that materially affects the information included in the Mineral
Resource Estimate and that all material assumptions and technical parameters
underpinning the estimates, continue to apply and have not materially changed. The
Company confirms that the form and context in which the Competent Person’s findings
are presented have not been materially modified from the Mineral Resource Estimate.
Information included in this presentation relating to Ore Reserves, Production Targets
and Financial Forecasts has been extracted from the Sorby Hills Definitive Feasibility
Study and FEED Study dated 19 January 2023 and 6 June 2024 respectively, available to
view at www.boabmetals.com.au. The Company confirms that it is not aware of any new
information or data that materially affects the information included in the Ore Reserve
Statement and that all material assumptions and technical parameters underpinning
the estimates, production targets and financial forecasts continue to apply and have not
materially changed. The Company confirms that the form and context in which the
Competent Person’s findings are presented have not been materially modified from the
Ore Reserves Statement.
3
Boab Metals
Corporate Summary
Share Price
A$0.15 /share
Debt
Nil
Shares on Issue
234 million shares
Cash
A$4.4 million1
Market Cap
A$35 million
30 September 2024
Performance Rights
7,600,000
Volume (M Sahres)
Capital Structure (24 October 2024)
5.0
0.25
4.0
0.20
3.0
0.15
2.0
0.10
1.0
0.05
0.0
0.00
Volume
Top 4 Shareholders
#
Holder Name
1
Villiers Queensland PL
7.85%
2
Citicorp Nominees Pty Limited
4.25%
3
Zero Nominees Pty Ltd
4.11%
4
Acuity Capital Investment
3.33%
24 October 2024
1. $4.8m At the market (ATM) Facility available for use at the company’s absolute discretion
Share Price (A$/sh)
Share Price History
Price
• ASX-listed base and
precious metals
developer and explorer.
• Board & Management
team with a proven track
record in development.
• Advancing toward Final
Investment Decision on
Sorby Hills.
• Top 20 shareholders hold
36% of issued capital.
4
Sorby Hills Project
A near term producer of Lead & Silver
Investment Highlights
•
Located 50km northeast of Kununurra, Western Australia and
150km by existing sealed roads to the Wyndham Port.
•
High quality 47.3Mt Mineral Resource1
•
1.5Mt contained Lead at 3.1%
•
0.2Mt contained Zinc at 0.4%
•
53Moz contained Silver at 35 g/t
•
Production target of 18.3Mt underpinned by 83% Reserves
•
Significant near mine and greenfields exploration upside
•
Conventional open pit mining and flotation process plant
producing a high-grade Lead-Silver concentrate
•
Feasibility Studies Complete
•
Process Plant Front End Engineering & Design complete
•
Offtake nearing completion
•
Engagement with Financiers ongoing
•
Project advancing toward a Final Investment Decision
Figure: Location of the Sorby Hills Project
1.
Boab Metals Limited ASX: BML
See Slide 5 for Resource breakdown
5
Sorby Hills Project
High Quality Resource Estimate
Deposit
Tonnes
(Mt)
Grade
Contained Metal
Pb
%
Zn
%
Ag
g/t
PbEq1
%
Pb
kt
Zn
kt
Ag
koz
A
0.6
5.3%
0.1%
23
6.1%
31
6
427
B
2.7
3.6%
0.3%
20
4.3%
97
8
1,720
Omega
17.2
3.3%
0.4%
34
4.5%
566
71
18,948
Norton
21.1
2.8%
0.4%
34
4.0%
590
96
24,090
Alpha
1.5
3.1%
0.9%
64
5.3%
45
13
2,975
Beta
4.2
3.6%
0.4%
43
5.1%
151
17
5,856
Measured
12.6
3.5%
0.4%
43
5.0%
444
45
17,521
Indicated
11.0
3.4%
0.4%
34
4.6%
377
46
12,114
Inferred
23.6
2.7%
0.5%
31
3.8%
645
117
23,406
Total
47.3
3.1%
0.4%
35
4.3%
1,465
207
53,042
See ASX announcement 17 December 2021
Figure: Location of the Sorby Hills Resources
1. See Appendix for Lead & Silver Equivalent calculation method
A different perspective - 47.3Mt @ 123g/t Silver Equivalent
Boab Metals Limited ASX: BML
6
Sorby Hills Project
FEED Study completed June 2024
FEED Study Highlights
A$264m preproduction Capex
underpinned 75%
by tendered
pricing
C1 cash cost
US$0.36/lb payable Pb
Incl. net Silver credit of
US$0.37/lb payable Pb
Average Annual Production
103kt Lead-Silver concentrate
64kt Lead and 2.0Moz Silver
NPV8 A$411m
IRR 37%
Strong pre-tax
economics
1.
2.
2.25Mtpa
8.5 Year
Mine Life
A$1.1bn Operating Cash Flow
A$126m p.a. Average EBITDA
See Appendix for Revenue Assumptions
See Appendix for Annual Physical and Cash flow summary together with Capital and Operating Cost breakdowns
Boab Metals Limited ASX: BML
Lead
546 thousand payable tonnes
A$1,803 Million Revenue
Silver
17.2 million payable ounces
A$693 Million Revenue
7
Sorby Hills Project
Project Sensitivities
Macroeconomics
1,000
As at 24 October 2024
900
800
• Lead: US$2,017/t
• Silver: US$34/oz
• FX: 0.66 AUD:USD
• Spot Lead TC: US$30/t
Project NPV8
700
600
500
400
NPV8 = A$523m
300
200
100
-30% -25% -20% -15% -10%
Lead
Silver
-5%
FX
0%
5%
Lead TC
10%
15%
Opex
20% 25% 30%
Capex
FEED Study Macroeconomic Assumptions
Pb: US$2,252/t, Ag: US$27.4/oz, FX: 0.68, Lead TC: US$125/t
Boab Metals Limited ASX: BML
Source
London Metal Exchange
ABC Bullion
www.xe.com
Fastmarkets
8
Sorby Hills Project
Development Ready
Primary Crusher
▪
GRES has recently completed
FEED Workstreams.
▪
FEED output has resulted in:
Flotation
Circuit
Filter Press
SAG Mill
Ball Mill
Tailings
Thickener
Concentrate Container Loading
Figure: 3D Model of the Sorby Hills Process Plant produce by GRES during FEED.
Boab Metals Limited ASX: BML
▪
detailed plant design and;
optimised site layout; and
▪
updated EPC pricing
consistent with EPC
pricing adopted in the DFS.
▪
Options to reduce costs have
been identified by GRES.
▪
Preliminary due diligence
indicates the DeGrussa process
plant currently for sale is ideally
suited to Sorby Hills.
9
Sorby Hills Project
Boab option to acquire 100% Interest
Terms of the Agreement (See ASX Announcement 23 September 2024)
•
12-month option for Boab to acquire Yuguang’s 25% interest in Sorby Hills,
increasing Boab’s current 75% interest in Sorby Hills to 100%.
•
During the option period, Boab will carry Yuguang’s joint venture expenses and in
turn, will have full control over joint venture budgets and work programs.
•
Should the option be exercised, Boab will pay Yuguang:
•
+218kt Concentrate
+137kt Payable Lead
+4.3Moz Payable Silver
+A$103M NPV
o
Tranche 1: A$12.5M upon exercise of the option and the concurrent
acquisition of Yuguang’s 25% Joint Venture interest;
o
Tranche 2: A$5.5M payable within 12 months from the commencement of
concentrate production at Sorby Hills; and
Attributable to Boab based on
the Sorby Hills FEED Study
o
Tranche 3: A$5.0M payable within 18 months from the commencement of
concentrate production at Sorby Hills.
ASX Release 6 June 2024
The ability to exercise the option is subject to Boab reaching a Final Investment
Decision (FID) on the Sorby Hills Project by September 2025.
Importantly, the option agreement:
•
requires no immediate payment to Yuguang and allows for the Tranche 1
payment to be met with funds raised at FID; and
•
provides a new basis on which to engage potential Offtakers and Financiers
Boab Metals Limited ASX: BML
10
Sorby Hills Project
53Moz - A significant Silver Resource
200
200
180
180
160
160
140
140
120
120
100
100
80
80
60
60
40
40
20
20
0
0
Reserve Ounces Contained
Boab Metals Limited ASX: BML
Non Reserve Ounces Contained
Resource Grade
Feasibility Study Complete
PFS Complete
Scoping Study Complete
See Appendix 1 for underlying peer data
No Study
Resource Grade (g/t Ag)
Contained Silver in Resource (Moz)
Comparison of contained Silver in undeveloped Australian Silver deposits as at 23 October 2024
11
Sorby Hills Project
Confirmed Low-Cost producer
Independently confirmed as a 1st Quartile Project
on the Global Lead cost curve
2027 Lead Cost Curve (ex-works basis)
2nd Quartile
3rd Quartile
4th Quartile
US$/t Lead
1st Quartile
▪ Low risk open cut mining
and high process plant
throughput drives low
operating cost relative to
global peers.
Sorby Hills
Project
CRU, Independent Market Consultant Report for Boab Metals’ Sorby Hills Pb-Ag Project (Sept 2023).
Boab Metals
Limited ASX:BML
Boab Metals Limited
ASX: BML
11
12
Sorby Hills Project
Delivering Silver Exposure to Investors
The Sorby Hills Project and Boab Metals offer
rare ASX exposure to Silver Price movements
▪ Since the acquisition of the
Sorby Hills Project in June
2018, Boab’s share price has
exhibited a strong
correlation with movements
in the price of Silver.
Rolling 30-day average daily % changes in USD Silver price & BML share price since June 2018
2.00%
USD Silver 30-day
Avg Daily % Change
30-day Avg daily % Change
6.00%
4.00%
2.00%
0.00%
-6.00%
-4.00%
1.50%
1.00%
0.50%
0.00%
-2.00%
0.00%
-0.50%
-2.00%
-1.00%
-4.00%
-1.50%
-6.00%
Jun-18
Dec-18
Jun-19
Dec-19
Jun-20
Dec-20
Jun-21
BML
Boab Metals Limited ASX: BML
Dec-21
Jun-22
Silver
Dec-22
Jun-23
Dec-23
Jun-24
-2.00%
2.00%
4.00%
6.00%
BML 30-day Avg
Daily % Change
▪ In particular, significant
positive movements in
Silver price correspond to
significant positive
movements in the Boab
share price
13
Sorby Hills Project
Exposure to Silver Price
Operating Costs covered by a historically non-volatile
Lead Price leaves the Operating margin fully leveraged
to Silver price movements.
2.0
Viewed differently, the Sorby
Hills Project may be considered
a low-cost silver producer
US$/oz
US$/lb
Increasing Silver Price
50
Sorby Hills AISC ex
Lead “Credits”
US$51/oz Ag
1.0
38% Margin
Sorby Hills AISC
ex-Silver Credits
US$0.81/lb Pb
0
Project Costs
Sorby Hills Net
Silver Credits*
US$0.37/lb Pb
AISC = negative US$14/oz Ag
Sorby Hills
Net Lead “Credits”
US$65/oz Ag
0
10-Year average
Lead Price
US$0.93/lb Pb
AISC = negative US$14/oz Ag
-50
Project Revenue
Sorby Hills Project Costs are more than
covered by the 10-year average1 Lead Price
*Based on FEED Study Price of US$27/oz Ag
Sorby Hills – A low-cost Silver Producer?
AISC = All in Sustaining Cost or “Breakeven” cost
1 As at 5 August 2024
Boab Metals
Limited ASX:BML
Boab Metals Limited
ASX: BML
13
14
Silver
The most conductive metal on earth
Strong demand for use in solar cells and the
electronic components of electric vehicles
•
Silver‘s traditional role as a
storer of wealth is
complemented by its
increasing industrial demand.
•
The use of Silver in solar cells
has increased nearly 150%
(8.3% CAGR) to 127Moz over the
past 10 years1.
•
Sorby Hills and Boab Metals
offers rare ASX exposure to
Silver metal demand.
1. www.silverinstitute.org/silver-supply-demand/
Boab Metals Limited ASX: BML
15
Sorby Hills Project
Supplying the proven Battery Metal
Lead demand growth underpinned by mature and
emerging vehicle technologies
1. www.batteryinnovation.org/resources/lead-battery-market-data/
Global Refined
Lead Demand (Mt)
Global Sales of light duty
vehicles (million units)
Forecast Light Vehicles Sales versus Lead Demand1
ICE Petrol
ICE Diesel
Hybrid EVs
Battery EVs
Other EVs
Lead Demand
Source: Bloomberg 29 November 2023
Boab Metals Limited ASX: BML
“…. low voltage 12V leadbased batteries will
continue to be used for
starter and auxiliary
functions in most internal
combustion engine
vehicles (ICE) and new
electric vehicles1 …..”
1. CRU, Independent Market
Consultant Report for Boab Metals’
Sorby Hills Pb-Ag Project (Sept 2023)
16
Sorby Hills Project
Significant Intercepts post MRE 2021
Phase V – 15 holes not yet included in Mineral Resource Estimate
▪ SHRC_123 (Beta): 27m @ 3.47% Pb & 37g/t Ag from 34m:
▪ Incl. 3m @ 7.04% Pb & 95g/t Ag from 35m; 5m @ 5.60% Pb & 44g/t Ag
from 45m; and 6m @ 4.50% Pb & 49g/t Ag from 55m.
▪ SHRC_124 (Beta): 17m @ 3.51% Pb & 46g/t Ag from 49m:
▪ Incl. 8m @ 6.93% Pb & 90g/t Ag from 57m.
▪ SHRC_129 (Wildcat): 6m @ 5.37% Pb & 21g/t Ag from 12m down hole.
Phase VI – 28 holes not yet included in mineral Resource Estimate
▪ SHRC_157 (Beta): 7m @ 19.17% PbEq, (16.23% Pb & 82g/t Ag) from 72m
▪ Incl. 3m @ 41.38% PbEq, (35.26% Pb & 174g/t Ag) from 72m.
▪ SHRC_136 (Beta): 20m @ 7.39% PbEq, (5.58% Pb & 52g/t Ag) from 65m
▪ Incl. 8m @ 13.86% PbEq, (10.49% Pb & 96g/t Ag) from 77m.
▪ SHRC_151 (Beta): 5m @ 5.13% PbEq, (3.70% Pb & 41g/t Ag) from 45m.
▪ SHRC_149 (Norton): 2m @ 16.64% PbEq, (10.92% Pb & 163g/t Ag) from 103m
▪ SHRC_147 (Norton): 11m @ 5.74% PbEq, (3.84% Pb & 54g/t Ag) from 86m.
▪ SHRC_143 (Norton): 13m @ 4.06% PbEq, (2.82% Pb & 35g/t Ag) from 95m.
Phase VII – 21 holes not yet included in Mineral Resource Estimate
▪ SHSD_171 (Norton): 11m @ 17.63% PbEq (10.98% Pb & 189 g/t Ag) from 82m
Figure: Location of the Sorby Hills Resources
▪ SHSD_174 (Norton): 11.6m @ 20.23% PbEq (8.78%Pb & 325 g/t Ag) from 74m
▪ SHSD_164 (Norton): : 6m @ 9.92% PbEq (3.92% Pb & 170g/t Ag) from 101m
Boab Metals Limited ASX: BML
Figure: Location of drill holes not yet included in the Sorby Hills Mineral Resource
17
Sorby Hills Project
Manbarrum Zn-Pb-Ag Project
Strategic Growth Opportunities
Vision to establish a long-life presence in the east
Kimberley Region
Figure:
Location of the
Manbarrum
Project, Eight
Mile Creek
Project and
Keep n-Pb
Target relative
to Sorby Hills.
▪
located 25km east of the Sorby Hills Project.
▪
175km2 of prospective tenements (including two
granted mining leases) covering geology related
to that found at Sorby Hills.
▪
Mineral Resources declared at two prospects
which are zinc and silver dominated.
▪
Conceptual open pit mining studies completed
by CSA Global in 2018.
Keep Zinc Lead Target
▪
New Zinc-Lead mineralisation recently discovered
via greenfield exploration within the existing Sorby
Hills mining leases
▪
Ore grade intercepts include:
▪
SHSD_185: 9.55 m @ 5.10% PbEq (2.59% Pb &
2.26% Zn) and 17.6 g/t Ag from 242.55 m
▪
SHSD_189: 2.00 m @ 7.73% PbEq (1.23% Pb &
5.86% Zn) and 36.7 g/t Ag from 303.0 m
Keep Zn-Pb Target
Eight Mile Creek
(Pb-Ag-Zn)
Eight Mile Creek Project
Boab Metals Limited ASX: BML
▪
30km of along-strike geology, highly prospective
for deposits similar to Sorby Hills.
▪
The exploration success based on seismic data at
the Keep Zinc-Lead Target has opened the door
for more bold exploration at Eight Mile Creek.
18
Boab Metals
Investment Opportunity
Near Term News Flow and Ongoing Activities
11% - FEED vs DFS NPV
Based on the same macroeconomic assumptions
Past 12 Months
111% - Boab Share Price1
25% - Median ASX Materials2
1% - Lead Price1
49% - Silver Price1
1. Bloomberg: 25 October 2023 – 24 October 2024
2. www.marketindex.com.au 24 October 2024
Boab Metals Limited ASX: BML
▪
▪
Execute Offtake Agreement(s).
▪
Boab working closely GR Engineering Services (“GRES”) to
assess the potential economic benefit of incorporating the
DeGrussa process plant into the Sorby Hills Project
▪
Progress approvals EPA 45c amendment, Works Approvals
EPBC referral.
▪
Engagement with potential financers to Secure credit
approved offer(s).
▪
Reach a Final Investment Decision.
Assessing opportunities to further de-risk project
execution and development timelines
19
Thank You
Simon Noon – Managing Director & CEO
info@BoabMetals.com
www.BoabMetals.com
www.linkedin.com/company/boab-metals
Boab Metals Limited ASX:BML
19
20
Boab Metals
Establishing Deep Roots within the Local Community
Boab is extremely proud to be the Naming Rights
Sponsor of the Ord Valley Muster for
2023 and beyond.
•
Sense of community plays a key role in economic
and social well-being of stakeholders across the
east Kimberley Region.
•
The Ord Valley Muster has been a highlight of
the Kimberley community calendar for 20 years.
Boab is an enthusiastic supporter and active
contributor to the Teach Learn Grow program.
•
Boab Metals has been partnering with Teach
Learn Grow (TLG) since 2021 in the delivery of
their Rural Program which supports one-on-one
tutoring and mentorship to students in East
Kimberley schools.
Boab Metals Limited ASX: BML
Boab Metals Limited ASX:BML
Images: Ord Valley Muster 2023 and Simon Noon - Managing Director/CEO with team at Teach Learn
Grow, East Kimberley
20
21
Board and
Technical Team
Gary Comb
Board and Management
with a proven track
record in exploration and
development
Technical Team
Boab Metals
Limited ASX:BML
Boab Metals Limited
ASX: BML
Simon Noon
Richard Monti
Andrew Parker
Chairman
Managing Director
and CEO
Non-Exec. Director
Non-Exec. Director
Engineer with over 30
years’ experience in the
Australian mining
industry, with a strong
track record in
successfully
commissioning and
operating base metal
mines.
Experienced mining
executive with a strong
background in
management, capital
raising and operating
JV’s with mid to top tier
miners in a variety of
commodities.
Geologist with over 30
years’ experience in
technical, commercial,
marketing and finance
within the exploration
and mining industry.
Lawyer with significant
experience in the
exploration and mining
industry. Wealth of
expertise in corporate
advisory, strategic
consultancy and raising
capital.
Bill Darcey – Project Manager
Simon Dorling - Exploration Manager
Mining professional with over 40 years of experience and a proven Geologist with more than 26 years’ experience in exploration,
track record of successfully managing, optimising, and developing development and the mining of base metals, precious metals,
mining operations. Bill was previously Operations Manager at the Mt energy minerals and industrial minerals.
Garnet copper-lead-zinc operation, where he oversaw the successful
start-up and management of an 800,000 TPA zinc-lead operation in
China. Bill holds degrees in both mining engineering and metallurgy.
21
22
Appendix
Appendix
Boab Metals Limited ASX:BML
22
23
Sorby Hills Project
Low Risk Open Pit Ore Reserve
FEED Study Production Target
Pit
Total
(Mt)
Waste
(Mt)
ROM
(Mt)
Pb
(%)
Ag
(g/t)
PbEq
(%)
Strip
Ratio
Pit A
4.1
3.7
0.5
3.7
16.4
4.3%
8.1
Pit B
14.8
12.6
2.3
3.2
17.4
3.8%
5.5
Omega South
21.1
18.3
2.8
2.9
29.5
3.9%
6.5
Omega Main
57.7
50.3
7.4
3.6
38.7
5.0%
6.8
Norton
21.4
19.5
1.9
4.0
78.5
6.8%
10.0
Beta
35.6
32.2
3.4
3.3
41.5
4.8%
9.5
Total Production
154.8
136.5
18.3
3.4
38.8
4.8%
7.5
Ore Reserve
Category
Ore
(Mt)
Proved
Grade
Contained Metal
Pb (%)
Ag (g/t)
Pb (kt)
Ag (Moz)
10.4
3.5%
42
358
14.1
Probable
4.9
3.5%
32
172
5.0
Total Ore Reserve
15.2
3.5%
39
531
19.1
See ASX announcement 19 January 2023
Production Target
underpinned 83% by
Measured and Indicated
Resources.
17%
1. See Appendix for Lead Equivalent calculation method
Ore Reserve Statement
Boab Metals Limited ASX: BML
Figure: DFS pit shells with respect to the Resource block model
26%
57%
Including 95% Measured
and Indicated Resources
over the first 7 years of
production.
Measured
Indicated
Inferred
24
Sorby Hills Feed Study
Life of Mine Physicals
2025
2026
2027
2028
2029
2030
2031
2032
2033
2034
2035
2036
18.3
-
0.4
2.1
2.3
2.4
2.5
2.3
2.0
1.1
3.0
0.3
-
Mt
134.6
-
3.8
11.7
14.3
25.7
25.4
21.0
17.3
13.0
4.2
0.2
-
% Measured
%
56.7%
-
67.3%
91.7%
64.7%
72.0%
89.7%
71.8%
47.7%
16.6%
-
-
-
% Indicated
%
26.5%
-
32.7%
8.3%
35.3%
27.2%
8.9%
26.7%
49.7%
30.6%
31.1%
-
-
% Inferred
%
16.8%
-
-
-
-
0.9%
1.4%
1.5%
2.7%
52.8%
68.9%
100.0%
-
Lead Grade
%
3.4%
-
3.8%
4.1%
3.2%
3.8%
3.3%
3.1%
3.1%
3.6%
3.4%
2.9%
-
Silver Grade
g/t
39
-
24
39
28
60
50
22
27
42
41
50
-
Processed Tonnes
Mt
18.3
-
-
1.39
2.25
2.26
2.25
2.25
2.25
2.26
2.25
1.11
-
Lead Grade
%
3.4%
-
-
5.5%
3.4%
4.0%
3.5%
3.1%
3.0%
2.5%
3.5%
3.0%
-
Silver Grade
g/t
39
-
-
47
30
59
54
24
27
30
41
41
-
Lead Recovery
%
91.6%
-
-
90.9%
94.1%
90.0%
88.0%
92.7%
94.7%
93.8%
90.3%
90.3%
-
Silver Recovery
%
81.7%
-
-
87.2%
86.2%
82.2%
81.4%
86.9%
86.9%
85.7%
70.4%
70.3%
-
Concentrate Produced
kt
873
-
-
109
110
126
112
99
98
80
97
42
-
Lead Grade
%
65.8%
-
-
64.2%
65.6%
63.5%
62.4%
65.9%
66.0%
65.7%
72.2%
72.3%
-
Silver Grade
g/t
664
-
-
529
532
860
878
479
535
730
677
770
-
Payable Lead
kt
546
-
-
61
69
79
65
63
63
50
68
30
-
Payable Silver
Moz
17.2
-
-
1.5
1.7
3.2
3.0
1.4
1.5
1.8
2.0
1.0
-
PHYSICALS SUMMARY
Unit
Total
ROM Mined
Mt
Waste Mined
Boab Metals
Limited ASX:BML
Boab Metals Limited
ASX: BML
24
25
Sorby Hills Feed Study
Life of Mine Cashflows
FINACIAL SUMMARY
Unit
Lead Revenue
A$M
Silver Revenue
2025
2026
2027
2028
2029
2030
2031
2032
2033
2034
2035
2036
1,803
-
-
198
225
260
215
207
208
165
226
98
1,803
A$M
693
-
-
59
69
131
121
57
62
71
82
40
693
Total Revenue
A$M
2,496
-
-
257
295
392
337
264
269
236
308
138
-
TR/RCs
A$M
(191)
-
-
(21)
(23)
(30)
(26)
(21)
(21)
(18)
(22)
(10)
-
Royalties
A$M
(95)
-
-
(10)
(11)
(14)
(12)
(10)
(10)
(9)
(12)
(5)
-
Net Revenue
A$M
(117)
-
-
(14)
(15)
(17)
(15)
(13)
(13)
(11)
(13)
(6)
-
Logistics
A$M
(547)
-
-
(51)
(62)
(94)
(93)
(81)
(71)
(54)
(36)
(4)
-
Mining
A$M
(388)
-
-
(38)
(47)
(47)
(47)
(47)
(47)
(47)
(47)
(24)
-
Processing
A$M
(88)
-
-
(10)
(10)
(10)
(10)
(10)
(10)
(10)
(10)
(5)
-
G&A
A$M
1,069
-
-
114
126
180
134
81
96
88
167
84
-
Operating Cash Flow
A$M
(117)
-
-
(14)
(15)
(17)
(15)
(13)
(13)
(11)
(13)
(6)
-
Pre-production Capex
A$M
(264)
(131)
(133)
-
-
-
-
-
-
-
-
-
-
Sustaining Capex
A$M
(26)
-
-
(12)
(1)
(3)
(1)
(0)
-
-
-
(5)
(4)
Project Cash Flows
A$M
778
(131)
(133)
101
125
177
133
81
96
88
167
78
(4)
NPV8
A$M
411
IRR
%
37
A$M
126
Average EBITDA
Boab Metals
Limited ASX:BML
Boab Metals Limited
ASX: BML
Total
25
26
Sorby Hills FEED Study
Capital Cost Breakdown
Total upfront capital cost of A$264M
including A$22.7M contingency
~66% of capital costs underpinned by
tendered pricing, including an updated
Process Plant EPC pricing following the
completion of Front-End Engineering &
Design by GRES.
A$32M Owner Costs including
operational readiness items such as
critical spares and owner’s team
Pre-Production
(A$M)
Sustaining
(A$M)
Total
(A$M)
EPC Contract
134.9
-
134.9
Site Ests/ Bulk Earthworks
31.9
4.9
36.9
Water Management
8.1
11.7
19.8
Accommodation Village
11.5
-
11.5
Other Infrastructure
8.5
0.6
9.1
Owners Costs
32.0
-
32.0
Contingency
22.7
-
22.7
Pre-Production Opex
15.0
-
15.0
-
9.3
9.3
264.5
26.5
290.9
Item
Closure Costs
Total Capital Costs
Opportunities being explored to
further reduce upfront capital costs
and project implementation risk.
Boab Metals
Limited ASX:BML
Boab Metals Limited
ASX: BML
26
27
Sorby Hills FEED Study
Operating Cost Breakdown
Competitive C1 cash cost of US$0.36/lb
payable Pb (including Silver Credits).
~80% of Mining Costs underpinned by
tendered pricing.
Opportunity to reduce Process costs
through the optimisation of back-up
power requirements.
Unit Costs
Total
(A$M)
A$/t ore
US$/lb payable Pb
Logistics
117
6.4
0.07
Mining
547
30.0
0.31
Processing
388
21.3
0.22
G&A
88
4.8
0.05
Lead Treatment
160
8.8
0.09
C1 Costs (ex-Credits)
1,300
71.2
0.74
Net Silver Credits
(661)
(36.2)
(0.37)
C1 Costs
639
35.0
0.36
Royalties
95
5.2
0.05
Sustaining Capital
26
1.4
0.01
AISC
760
41.6
0.43
Item
Unit Operating Costs based on 18.3Mt of Ore, 546kt of Payable
Lead, average exchange rate of AUD:USD 0.68 and average
Silver price of US$27.4/oz.
Boab Metals
Limited ASX:BML
Boab Metals Limited
ASX: BML
27
28
Sorby Hills Project
Resource Classification by Deposit
Deposit
Classification
Tonnes
(Mt)
Inferred
Sub Total
Measured
Indicated
Sub Total
Measured
Indicated
Inferred
Sub Total
Measured
Indicated
Inferred
Sub Total
Indicated
Inferred
Sub Total
Indicated
Inferred
Sub Total
Measured
Indicated
Inferred
Total
0.6
0.6
1.4
1.3
2.7
8.5
5.8
2.9
17.2
2.8
2.1
16.2
21.1
0.7
0.8
1.5
1.0
3.2
4.2
12.6
11.0
23.6
47.3
A
B
Omega
Norton
Alpha
Beta
Total Resource
Boab Metals Limited ASX: BML
Grade
Pb
%
5.3%
5.3%
3.8%
3.4%
3.6%
3.3%
3.5%
2.7%
3.3%
4.1%
3.2%
2.5%
2.8%
2.6%
3.6%
3.1%
4.1%
3.4%
3.6%
3.5%
3.4%
2.7%
3.1%
Zn
%
1.0%
0.1%
0.3%
0.3%
0.3%
0.4%
0.4%
0.4%
0.4%
0.3%
0.5%
0.5%
0.4%
0.5%
1.2%
0.9%
0.2%
0.4%
0.4%
0.4%
0.4%
0.5%
0.4%
1. See Appendix for Lead & Silver Equivalent calculation method
Ag
g/t
23
23
19
21
20
37
34
26
34
75
38
27
34
41
86
64
42
43
43
43
34
31
35
PbEq1
%
6.1%
6.1%
4.5%
4.1%
4.3%
4.6%
4.7%
3.6%
4.5%
6.7%
4.5%
3.4%
4.0%
4.0%
6.6%
5.3%
5.6%
4.9%
5.1%
5.0%
4.6%
3.8%
4.3%
Pb
kt
31
31
52
44
97
279
205
76
566
112
68
402
590
18
27
45
42
109
151
444
377
645
1,465
Contained Metal
Zn
kt
6
6
4
4
8
32
25
13
71
9
11
75
96
4
9
13
2
14
17
45
46
117
207
Ag
koz
427
427
859
862
1,720
9,995
6,331
2,414
18,948
6,668
2,617
14,039
24,090
923
2,052
2,975
1,382
4,474
5,856
17,521
12,114
23,406
53,042
29
Sorby Hills Project
Peer Comparison
(as at 23 October 2024)
Project
Primary
Commodity
Ticker
Owner
Proved
Reserve
(Mt)
Probable
Reserve
(Mt)
Reserve
Grade
(g/t)
Measured
Resource
(Mt)
Indicated
Resource
(Mt)
Inferred
Resource
(Mt)
Resource
Grade
(g/t)
Bowdens
Silver
SVL
Silver Mines Limited
29
1
68
107
50
43
29
Company Presentation – 11 September 2024
Admiral Bay
Zinc
ARI
Arika Resources Limited
-
-
-
-
-
170
25
2023 Annual Report
Maronan
Silver
MMA
Maronan Metals Limited
-
-
-
-
2
30
107
Resource Report – 12 March 2024
Walford Creek
Copper
AML
Aeon Metals Limited
-
-
-
17
28
28
28
Resource Report – 15 March 2023
Peterlumbo
Silver
IVR
Investigator Resources Limited
-
-
-
-
17
7
73
2024 Annual Report
Sorby Hills
Lead
BML
Boab Metals Limited
10
5
39
13
11
24
35
Resource Report – 17 December 2021
Wonawinta
Silver
MKR
Manuka Resources Limited
-
-
-
1
12
25
41
Resource Report – 1 April 2021
Kempfield
Silver
ARD
Argent Minerals Limited
-
-
-
-
23
16
34
2024 Annual Report
Mt Mulgine
Tungsten
TGN
Tungsten Mining NL
-
140
6
-
183
76
5
Pre-Fe