Quarterly Activities/Appendix 5B Cash Flow Report
Released
Released
Announcement PDF
21 January, 2025
Quarterly Activities and Cashflow Report
for the period ending 31 December 2024
Boab Metals Limited (ASX: BML) (“Boab” or “Company”) is pleased to provide the following
activities and cashflow report for the quarter ending 31 December, 2024. During the quarter, the
Company continued progressing its flagship Sorby Hills Lead-Silver-Zinc Project (“Sorby Hills” or
“the Project”), located in the Kimberley Region of Western Australia.
HIGHLIGHTS
•
Binding US$30 million Prepayment Terms Sheet and associated Offtake Agreement
executed between Boab’s 100% subsidiary Sorby Hills Pty Ltd and global commodities
trader Trafigura.
Prepayment Terms Sheet – Key Terms
o
US$30 million Prepayment Facility from Trafigura to be applied towards the
construction and development of the Project.
o
Interest Rate of SOFR + 5% per annum.
o
5-year Term from first drawdown with an 18-month interest-only period.
Offtake Agreement – Key Terms
o
75% of lead-silver concentrate from Sorby Hills for a minimum of 531,000 tonnes.
o
If Boab obtains alternative financing to the Prepayment, the Offtake volume will revert
to 50% (or greater, at Boab’s discretion) for a minimum 354,000 tonnes.
o
If Financial Close is not achieved on the Prepayment, the Offtake volume will revert to
25% (or greater, at Boab’s discretion) for a minimum 177,000 tonnes.
•
WA Government consented to key amendments for Sorby Hills required under Part IV
of Western Australia’s Environmental Protection
•
Boab continues to progress opportunities to further reduce capital and operating costs.
•
Targeted Final Investment Decision in 2H 2025.
•
The Company had a cash balance of approximately A$3.5M as at 31 December, 2024.
Boab Managing Director and CEO, Simon Noon, stated:
“The December quarter of 2024 saw significant project execution milestones achieved. The binding
Prepayment and Offtake agreement with Trafigura is highly favourable for Boab and is the result of a
thorough offtake process that demonstrated the attractiveness of the Sorby Hills concentrate. The EPA
amendments provide Boab with scope to implement the Sorby Hills Project in line with the Project’s
FEED study, including an increase to the open pit depth and mining production rate. We look forward
to building upon these milestones and the momentum that we have generated over the past six
months to advance Sorby Hills to a Final Investment Decision in 2025.”
_________________________________________________________________________________________________________________________________________________
Quarterly Report December 2024
Page 1
Background Information
Sorby Hills is located 50km from the regional centre of Kununurra in the East Kimberley of Western
Australia and has access to existing sealed roads to transport the concentrate 150km from the site
to the facilities at Wyndham Port. The Project comprises a Mineral Resource of 47.3Mt containing
1.5Mt Pb at 3.1% and 53Moz silver at 35g/t (Table 1). The current Sorby Hills mine plan comprises
18.3Mt at 3.4% Pb and 39g/t Ag of which ~83% is classified as an Ore Reserve (Table 2).
On 6 June 2024, Boab released the results of a Front-End Engineering & Design Study (“FEED
Study”) on the Project showing strong pre-tax economics including C1 operating costs of
US$0.36/lb payable Pb (incl. a net silver credit of US$0.37/lb payable Pb), NPV8 of A$411M, IRR of
37%, A$778M free cash flow, and an average annualised EBITDA of A$126M. Pre-production capital
costs were estimated to be A$264M.
With operating costs covered by revenue generated by a historically non-volatile lead price, the
Project free cash flow is exposed to movements in the price of silver.
The Company currently owns 75% of the Project and has executed an agreement to acquire the
remaining 25% of the Project upon a Final Investment Decision (ASX release 23 September 2024).
Binding Offtake and Prepayment Agreement
During the quarter, Boab (via its 100% own subsidiary Sorby Hills Pty Ltd (“SHPL”) executed a
binding Offtake Agreement and associated US$30 million Prepayment with global commodities
trader, Trafigura (ASX release 10 December 2024).
The Prepayment terms include a 5-year term, an interest rate margin of SOFR1 + 5%, and an 18month interest-free period after which repayments will be paid via equal monthly instalments.
Financial Close and drawdown of the Prepayment are subject to, amongst other things, the
execution of full-form documentation, the finalisation of outstanding due diligence, and the
Project being fully-funded.
Base offtake terms are for 75% of the Sorby Hills Lead-Silver concentrate up to a minimum of
531,000 tonnes (~7 years based on the FEED Study production schedule) with market standard
metal payabilities, metal pricing based on spot pricing and a lead treatment charge linked to the
quoted annual benchmark. Should Boab utilise alternative financing to the Prepayment or not
reach financial close on the Prepayment, Boab shall have the discretion to reduce the offtake
volumes to 50% and 25% respectively. In each case, lead treatment charges will revert to an average
of the prevailing annual benchmark and the spot lead treatment charge.
The agreements are the result of a highly competitive process including other global traders and
smelters that demonstrated the attractiveness of the Sorby Hills concentrate product and
represent a key milestone towards a final investment decision on Sorby Hills and a cornerstone of
Boab’s financing solution for the Project.
1
Secured Overnight Financing Rate
_________________________________________________________________________________________________________________________________________________
Quarterly Report December 2024
Page 2
EPA Amendments
During the quarter, the Western Australian Government provided consent to key amendments to
the Sorby Hills Project existing approval under the Environmental Protection Act (“EPA”)(ASX
release 23 December 2024).
The consent was the result of a detailed information exchange with the Western Australia
Environmental Protection Agency department to demonstrate that the Project in its current
expanded form is in accordance with requirements of the EPA. The amendments provide Boab
with scope to implement the Sorby Hills Project in line with the Project’s FEED study, including an
increase to the open pit depth and mining production rate. The amendments also provide the
opportunity for Boab to further reduce capital expenditure through an optimisation of the
proposed water management strategy and rationalisation of associated infrastructure.
All EPA amendments required under Part IV of the Act to commence the implementation of the
Sorby Hills Project have been received and the Company will now proceed toward finalising
outstanding regulatory approvals, including the completion and updating of documentation
required under the federal Environmental Protection and Biodiversity Conservation Act (“EPBC”)
as a result of the increase in the Project’s scope since the Project was originally assessed in 2013.
EPA approval to mine the Beta Pit, which is scheduled to occur at the end of the current Project
mining plan, will be sought subsequent to the commencement of operations.
Cost Reduction Initiatives
As the Company advances toward a Final Investment Decision, it continues to assess opportunities
to reduce costs. Such opportunities include ongoing due diligence of the potential acquisition of
Sandfire’s DeGrussa process plant as a means to reduce capital costs, and the feasibility of utilising
100% grid power sourced from the Ord hydroelectric plant as a means of reducing operating costs.
KEEP confirmed as a Target for Further Exploration
In early August 2024, Boab announced the commencement of a Phase VIII drilling program to
follow up on its exploration success from the 2023 campaign at the KEEP Target. The Phase VIII
drilling program comprised of 4-hole deep sonic/diamond step-out drill holes for a total of 1,352m
and was completed ahead of schedule and within budget.
Assay results from the Phase VIII drilling program released during the quarter (ASX release
22 October 2024) confirmed the continuity of mineralisation and support future exploration of the
KEEP Target. Boab is of the view that the KEEP Zinc-Lead Prospect area is now established as a
compelling sub-surface target with scope for future discovery.
Key intercepts of base metal mineralisation from the drilling of the Keep Target include:
•
SHSD_184: 9.55m @ 5.10% PbEq (2.59%Pb & 2.26% Zn) and 17.6 g/t Ag from 242.6m
•
SHSD_189: 2.00m @ 7.73% PbEq (1.23% Pb & 5.86% Zn) and 36.7 g/t Ag from 303.0m
_________________________________________________________________________________________________________________________________________________
Quarterly Report December 2024
Page 3
•
SHSD_189: 13.0m @ 1.23% PbEq (0.73% Pb & 0.45% Zn) and 2.76 g/t Ag from 314m
•
SHSD_188: 7.6m @ 1.00% PbEq (0.83% Pb & 0.14% Zn) and 7.31 g/t Ag from 66.4m
Financial and Corporate Overview
The consolidated cash balance of the Company as at 31 December 2024 was A$3.54M. During the
period, the Company paid $151k to related parties. These payments were made to Directors of Boab
Metals Limited in relation to salaries and directors’ fees, on normal commercial terms.
On 26 November 2024, the Company held its Annual General Meeting and advised Shareholders
that all resolutions put to the meeting were passed on a poll by an overwhelming majority.
The Board of Directors have authorised this announcement for release to the market.
FOR FURTHER INFORMATION, PLEASE CONTACT:
Simon Noon
Managing Director & CEO
Phone: +61 (0)8 6268 0449
Email: info@boabmetals.com
Table 1: Sorby Hills Mineral Resource Estimate – Pb Domains only.
Grade
Contained Metal
Tonnes
(Mt)
Pb
Zn
Ag
Pb
Zn
Ag
%
%
g/t
kt
kt
koz
Measured
12.6
3.5%
0.4%
43
444
45
17,521
Indicated
11.0
3.4%
0.4%
34
377
46
12,114
Inferred
23.6
2.7%
0.5%
31
645
117
23,406
Total Resource
47.3
3.1%
0.4%
35
1,465
207
53,042
Resource
Classification
Note: Tonnes and Grade are rounded. Reported at a 1.0% Pb Cut-Off. Discrepancies in calculated Contained Metal is due to rounding .
Table 2: Sorby Hills Ore Reserve Statement.
Grade
Contained Metal
Ore Reserve
Category
Ore
(Mt)
Pb (%)
Ag (g/t)
Pb (kt)
Ag (Moz)
Proved
10.4
3.5%
42
358
14.1
Probable
4.9
3.5%
32
172
5.0
Total Ore Reserve
15.2
3.5%
39
531
19.1
Note: Tonnes and Grade are rounded. Reported at a 1.0% Pb cut-off. The above data has been rounded to the nearest 10,000 tonnes ore, 0.1%
lead grade and 1,000 lead tonnes, 1g/t silver grade and 100,000 silver ounces. Discrepancies in calculated Contained Metal is due to rounding.
Ore Reserves have been calculated using metal prices of A$3,313.91/t Pb and A$37.89/oz Ag and royalties of 4.3% of gross revenue including
allowable deductions.
_________________________________________________________________________________________________________________________________________________
Quarterly Report December 2024
Page 4
About Boab Metals Limited
Boab Metals Limited (“Boab”, ASX: BML) is a Western Australian-based exploration and
development company with interests in Australia and South America. In Australia, the Company is
currently focused on developing the Sorby Hills Lead-Silver-Zinc Joint Venture Project in WA. Sorby
Hills is located 50km from the regional centre of Kununurra in the East Kimberley and has access
to existing sealed roads to transport concentrate from site to the facilities at Wyndham Port, a
distance of 150km. Established infrastructure and existing permitting allows for fast-track
development and production.
Boab owns a 75% interest in the Joint Venture with the remaining 25% interest held by Henan
Yuguang Gold & Lead Co. Ltd. Boab holds an option to acquire Yuguang’s interest in the Project.
Compliance Statements
The Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves
(the ‘JORC Code’) sets out minimum standards, recommendations and guidelines for Public
Reporting in Australasia of Exploration Results, Mineral Resources and Ore Reserves.
Information included in this activities report relating to Exploration Results has been extracted
from the announcement titled KEEP confirmed as a Target for Further Exploration dated 22
October 2024 , available to view at www.boabmetals.com.au. The Company confirms that the form
and context in which the Competent Person’s findings are presented have not been materially
modified from the original announcement.
Information included in this activities report relating to Mineral Resources has been extracted from
the Mineral Resource Estimate dated 17 December 2021, available to view at
www.boabmetals.com.au. The Company confirms that it is not aware of any new information or
data that materially affects the information included in the Mineral Resource Estimate and that all
material assumptions and technical parameters underpinning the estimates, continue to apply
and have not materially changed. The Company confirms that the form and context in which the
Competent Person’s findings are presented have not been materially modified from the Mineral
Resource Estimate.
Information included in this activities report relating to Ore Reserves, Production Targets and
Financial Forecasts has been extracted from the Sorby Hills Definitive Feasibility Study dated 19
January 2023 and Sorby Hills FEED Study Results dated 6 June 2024, both available to view at
www.boabmetals.com.au. The Company confirms that it is not aware of any new information or
data that materially affects the information included in the Ore Reserve Statement and that all
material assumptions and technical parameters underpinning the estimates, production targets
and financial forecasts continue to apply and have not materially changed. The Company confirms
that the form and context in which the Competent Person’s findings are presented have not been
materially modified from the Ore Reserves Statement.
_________________________________________________________________________________________________________________________________________________
Quarterly Report December 2024
Page 5
Metal Equivalent Calculation Method
The contained metal equivalence formula is based on the Sorby Hills Feed Study including:
•
•
•
•
•
•
•
•
•
Lead Price US$2,253.19/t;
Lead recovery of 91.0% (weighted average of oxide and fresh Pb recoveries);
Lead Payability rate of 95%;
Silver Price US$27.4/oz;
Silver recovery of 81.8% (weighted average of oxide and fresh Ag recoveries); and
Silver Payability rate of 95%.
Zinc Price US$2,500/t
Zinc Recovery of 91%
Zinc Payability of 95%
It is Boab’s opinion that all elements included in the metal equivalent calculation have a
reasonable potential to be recovered and sold.
The formula used to calculate lead equivalent grade is:
MetalEq (%) = Gpri + (Gpri × [∑i Ri Si Vi Gi ]/(Rpri SpriVpriGpri))
where R is the respective metallurgical metal recovery rate, S is the respective smelter return rate,
V is metal price/tonne or ounce, and G is the metal commodity grade for the suite of potentially
recoverable commodities (i) relative to the primary metal (pri).
Metal equivalents are highly dependent on the metal prices used to derive the formula. Boab
notes that the metal equivalence method used above is a simplified approach. The metal prices
are based on the DFS values adopted and do not reflect the metal prices that a smelter would pay
for concentrate nor are any smelter penalties or charges included in the calculation. Owing to
limited metallurgical data, zinc grades are not included at this stage in the lead equivalent grade
calculation.
FEED Study Macroeconomic Assumptions
Assumption
Unit
FY2025
FY2026
FY2027
FY2028
FY2029+
Lead Price
US$/t
2,259
2,268
2,269
2,254
2,251
Silver Price
US$/oz
24.8
25.8
26.4
27.3
27.5
Exchange Rate
A$:US$
0.70
0.70
0.70
0.69
0.68
_________________________________________________________________________________________________________________________________________________
Quarterly Report December 2024
Page 6
APPENDIX 1
INTERESTS IN TENEMENTS
Farm-In
Agreements/
Projects/Tenements
Location
Held at Start of
Quarter
Held at End of
Quarter
Sorby Hills Project
M80/196
75%
75%
M80/197
75%
75%
75%
75%
75%
75%
M80/287
75%
75%
E80/5317
100%
100%
100%
100%
51%
51%
51%
51%
51%
51%
51%
51%
51%
51%
100%
100%
100%
100%
100%
100%
100%
100%
M80/285
M80/286
WA, Australia
Borroloola West
Project
EL31354
EL26938
EL26939
NT, Australia
EL28658
EL30305
MLN624
Manbarrum Project
EL24395
MA24518
NT, Australia
MA26581
Urrao Project
2791
Colombia
_________________________________________________________________________________________________________________________________________________
Quarterly Report December 2024
Page 7
Rule 5.5
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
BOAB METALS LIMITED
Quarter ended (“current quarter”)
ABN
43 107 159 713
Consolidated statement of cash flows
1.
Cash flows from operating activities
1.1
Receipts from customers
1.2
Payments for
31 December 2024
Current quarter
$A’000
Year to date
(6 months)
$A’000
-
-
(393)
(1,429)
(b) development
-
-
(c) production
-
-
(d) staff costs
(147)
(304)
(e) administration and corporate costs
(342)
(541)
-
-
56
107
(a) exploration & evaluation (if expensed)
1.3
Dividends received (see note 3)
1.4
Interest received
1.5
Interest and other costs of finance paid
-
-
1.6
Income taxes paid
-
-
1.7
Government grants and tax incentives
-
-
1.8
Other:Recharge of staff costs and other
administration costs to the Sorby JV
20
50
Net cash from / (used in) operating
activities
(806)
(2,117)
1.9
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 1
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Consolidated statement of cash flows
2.
Cash flows from investing activities
2.1
Payments to acquire or for:
Current quarter
$A’000
Year to date
(6 months)
$A’000
(a) entities
-
-
(b) tenements
-
-
(c) property, plant and equipment
-
(11)
(d) exploration & evaluation
-
-
(e) investments
-
-
(f)
-
(36)
(a) entities
-
-
(b) tenements
-
-
(c) property, plant and equipment
-
-
(d) investments
-
-
(e) other non-current assets
-
-
2.3
Cash flows from loans to other entities
-
-
2.4
Dividends received (see note 3)
-
-
2.5
Other (provide details if material)
-
-
2.6
Net cash from / (used in) investing
activities
-
(47)
3.
Cash flows from financing activities
3.1
Proceeds from issues of equity securities
(excluding convertible debt securities)
-
-
2.2
other non-current assets
Proceeds from the disposal of:
3.2
Proceeds from issue of convertible debt
securities
-
-
3.3
Proceeds from exercise of options
-
-
3.4
Transaction costs related to issues of equity
securities or convertible debt securities
-
-
3.5
Proceeds from borrowings
-
-
3.6
Repayment of borrowings
-
-
3.7
Transaction costs related to loans and
borrowings
-
-
3.8
Dividends paid
-
-
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 2
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Consolidated statement of cash flows
Current quarter
$A’000
Year to date
(6 months)
$A’000
3.9
Other (provide details if material)
-
-
3.10
Net cash from / (used in) financing
activities
-
-
4.
Net increase / (decrease) in cash and
cash equivalents for the period
4.1
Cash and cash equivalents at beginning of
period
4,350
5,708
4.2
Net cash from / (used in) operating
activities (item 1.9 above)
(806)
(2,117)
4.3
Net cash from / (used in) investing activities
(item 2.6 above)
-
(47)
4.4
Net cash from / (used in) financing activities
(item 3.10 above)
-
-
4.5
Effect of movement in exchange rates on
cash held
-
-
4.6
Cash and cash equivalents at end of
period
3,544
3,544
5.
Reconciliation of cash and cash
equivalents
Current quarter
$A’000
Previous quarter
$A’000
at the end of the quarter (as shown in the
consolidated statement of cash flows) to
the related items in the accounts
5.1
Bank balances
291
297
5.2
Call deposits
3,200
4,000
5.3
Bank overdrafts
-
-
5.4
Other (provide details)
53
53
5.5
Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
3,544
4,350
6.
Payments to related parties of the entity and their associates
6.1
Aggregate amount of payments to related parties and their
associates included in item 1
6.2
Current quarter
$A'000
(151)*
Aggregate amount of payments to related parties and their
associates included in item 2
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of,
and an explanation for, such payments.
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 3
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
7.
Financing facilities
Note: the term “facility’ includes all forms of
financing arrangements available to the entity.
Add notes as necessary for an understanding of the
sources of finance available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
7.1
Loan facilities
-
-
7.2
Credit standby arrangements
-
-
7.3
Other (please specify)
-
-
7.4
Total financing facilities
-
-
7.5
Unused financing facilities available at quarter end
7.6
Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing
facilities have been entered into or are proposed to be entered into after quarter end,
include a note providing details of those facilities as well.
8.
Estimated cash available for future operating activities
-
$A’000
8.1
Net cash from / (used in) operating activities (item 1.9)
8.2
(Payments for exploration & evaluation classified as investing
activities) (item 2.1(d))
8.3
Total relevant outgoings (item 8.1 + item 8.2)
(806)
8.4
Cash and cash equivalents at quarter end (item 4.6)
3,544
8.5
Unused finance facilities available at quarter end (item 7.5)
8.6
Total available funding (item 8.4 + item 8.5)
3,544
8.7
Estimated quarters of funding available (item 8.6 divided by
item 8.3)
4.39
8.8
If item 8.7 is less than 2 quarters, please provide answers to the following questions:
8.8.1
(806)
-
-
Does the entity expect that it will continue to have the current level of net operating
cash flows for the time being and, if not, why not?
Answer: Not Applicable.
8.8.2
Has the entity taken any steps, or does it propose to take any steps, to raise further
cash to fund its operations and, if so, what are those steps and how likely does it
believe that they will be successful?
Answer: Not Applicable.
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 4
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
8.8.3
Does the entity expect to be able to continue its operations and to meet its business
objectives and, if so, on what basis?
Answer: Not Applicable.
Note: where item 8.7 is less than 2 quarters, all of questions 8.8.1, 8.8.2 and 8.8.3 above must be answered.
Compliance statement
1
This statement has been prepared in accordance with accounting standards and policies which comply with
Listing Rule 19.11A.
2
This statement gives a true and fair view of the matters disclosed.
Authorised for release by the Board of Directors of Boab Metals Limited
Notes
1.
This quarterly cash flow report and the accompanying activity report provide a basis for informing the market about the entity’s activities
for the past quarter, how they have been financed and the effect this has had on its cash position. An entity that wishes to disclose
additional information over and above the minimum required under the Listing Rules is encouraged to do so.
2.
If this quarterly cash flow report has been prepared in accordance with Australian Accounting Standards, the definitions in, and
provisions of, AASB 6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash Flows apply to this
report. If this quarterly cash flow report has been prepared in accordance with other accounting standards agreed by ASX pursuant to
Listing Rule 19.11A, the corresponding equivalent standards apply to this report.
3.
Dividends received may be classified either as cash flows from operating activities or cash flows from investing activities, depending on
the accounting policy of the entity.
4.
If this report has been authorised for release to the market by your board of directors, you can insert here: “By the board”. If it has been
authorised for release to the market by a committee of your board of directors, you can insert here: “By the [name of board committee –
eg Audit and Risk Committee]”. If it has been authorised for release to the market by a disclosure committee, you can insert here: “By
the Disclosure Committee”.
5.
If this report has been authorised for release to the market by your board of directors and you wish to hold yourself out as complying
with recommendation 4.2 of the ASX Corporate Governance Council’s Corporate Governance Principles and Recommendations, the
board should have received a declaration from its CEO and CFO that, in their opinion, the financial records of the entity have been
properly maintained, that this report complies with the appropriate accounting standards and gives a true and fair view of the cash flows
of the entity, and that their opinion has been formed on the basis of a sound system of risk management and internal control which is
operating effectively.
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 5
Share your feedback
Discover