Quarterly Activities/Appendix 5B Cash Flow Report
Released
Released
Announcement PDF
25 October, 2024
Quarterly Activities and Cashflow Report
for the period ending 30 September 2024
Boab Metals Limited (ASX: BML) (“Boab” or “Company”) is pleased to provide the following activities
and cashflow report for the quarter ending 30 September, 2024. During the quarter, the Company
continued progressing its 75% owned Sorby Hills Lead-Silver-Zinc Project (“Sorby Hills” or “the
Project”), located in the Kimberley Region of Western Australia.
HIGHLIGHTS
•
Option Agreement to acquire 100% of Sorby Hills Project executed with Joint Venture
partner Henan Yuguang Gold & Lead Co. Ltd (“Yuguang”).
o
12 month option period during which Boab will carry Yuguang’s 25% joint venture
expenses and in turn, will have full control over the approval of joint venture budgets
and work programs.
o
Should the option be exercised, Boab will pay Yuguang:
▪
Tranche 1: A$12.5M upon exercise of the option and the concurrent
acquisition of Yuguang’s 25% Joint Venture interest;
▪
Tranche 2: A$5.5M payable no later than 12 months from the
commencement of concentrate production at Sorby Hills; and
▪
Tranche 3: A$5.0M payable no later than 18 months from the
commencement of concentrate production at Sorby Hills.
o
The ability to exercise the option is subject to Boab reaching a Final Investment
Decision (“FID”) on the Sorby Hills Project within the next 12 months.
o
Importantly, the option agreement requires no immediate payment to Yuguang
and allows for Tranche 1 payment to be met with funds raised at FID.
•
Phase VIII drilling program completed with assay results confirming continuity of
mineralisation and supporting future exploration of the Keep Seismic Target.
•
Offtake negotiations continue to progress well.
•
Boab assessing opportunities to further de-risk project execution and development
timelines.
•
The Company had a cash balance of approximately A$4.4M as at 30 September, 2024.
Boab Managing Director and CEO, Simon Noon, stated :
“The execution of the option agreement with Yuguang during the quarter represents a pivotal
development for Boab and the Sorby Hills Project. With the Project in an advanced state following
completion of the FEED study in the previous quarter, the option agreement provides Boab with a
clear runway to present Sorby Hills to project financiers and offtakers on the basis that it will be
100% owned by Boab Metals. We now look forward to advancing these workstreams to a
conclusion and reaching a Final Investment Decision on the Project”.
_____________________________________________________________________________________________________________________________ ____________________
Quarterly Report September 2024
Page 1
Background on the Sorby Hills Project
On 6 June 2024, Boab released the results of a Front-End Engineering & Design Study (“FEED
Study”) on the Project showing strong pre-tax economics including C1 operating costs of
US$0.36/lb payable Pb (incl. a net Silver credit of US$0.37/lb payable Pb), NPV 8 of A$411M, IRR of
37%, A$778M free cash flow, and an average annualised EBITDA of A$126M. Pre-production capital
costs are estimated to be A$264M.
The Sorby Hills Resource comprises a Mineral Resource of 47.3Mt containing 1.5Mt Pb at 3.1% and
53Moz Sliver at 35g/t (Table 1). The current Sorby Hills mine plan comprises 18.3Mt at 3.4% Pb and
39g/t Ag of which ~83% is classified as an Ore Reserve (Table 2).
Option to Acquire 100% of the Sorby Hills Project
During the quarter, Boab entered into an option agreement to acquire from joint venture partner
Henan Yuguang Gold & Lead Co. Ltd’s (“Yuguang”) their 25% interest in the Sorby Hills Project (ASX
release 23 September, 2024). Yuguang has been a committed joint venture partner over the past
6 years of Boab’s involvement in the Sorby Hills Project. During this period, the joint venture has
effectively grown the Mineral Resource and completed high-quality Feasibility studies on the
Project. The option agreement is reflective of this productive and cooperative relationship and
provides a new pathway to advance Sorby Hills toward a Final Investment Decision.
Key Terms of the Agreement
•
12-month option for Boab to acquire Yuguang’s 25% interest in Sorby Hills, increasing
Boab’s current 75% interest in the Project to 100%.
•
During the option period, Boab will carry Yuguang’s joint venture expenses and in turn, will
have full control over joint venture budgets and work programs.
•
Should the option be exercised, Boab will pay Yuguang:
•
o
Tranche 1: A$12.5M upon exercise of the option and the concurrent acquisition of
Yuguang’s 25% Joint Venture interest;
o
Tranche 2: A$5.5M payable no later than 12 months from the commencement of
concentrate production at Sorby Hills; and
o
Tranche 3: A$5.0M payable no later than 18 months from the commencement of
concentrate production at Sorby Hills.
The ability to exercise the option is subject to Boab reaching a Final Investment Decision
on the Sorby Hills Project within the next 12 months.
Importantly, the option agreement requires no immediate payment to Yuguang and allows for
Tranche 1 payment to be met with funds raised at FID.
Based on the results of the FEED Study, a further 218kt of lead-silver concentrate, 137kt of payable
lead, 4.3Moz of payable silver and A$103M NPV8 will be attributable to Boab upon exercise of the
option and acquisition of Yuguang’s 25% interest.
_____________________________________________________________________________________________________________________________ ____________________
Quarterly Report September 2024
Page 2
Completion of the Phase VIII Drilling Program
In early August, Boab announced the commencement of a Phase VIII drilling program to follow
up on its exploration success from the 2023 campaign at the Keep Seismic Target. The Phase VIII
drilling program comprised of 4-hole deep sonic/diamond step out drill holes for a total of 1,352m
and was completed ahead of schedule and within budget.
The new drill holes were collared as 100m step-outs from Phase VII hole SHSD_185 to enable
correlation and interpretation of the original results. SHSD_185 was aimed at testing the potential
for a mineralised feeder fault system, which can be seen on the seismic data and the potential for
stratiform mineralisation at the base of the Knox Formation/Sorby Dolomite interface.
In summary, the program delivered several important results:
•
A significant mineralisation intercept demonstrating the validity of the targeting rationale;
•
Intersected further intervals of massive stratiform sphalerite mineralisation; and
•
Demonstrated the role of structure in the distribution and deformation of mineralisation.
Assay results released subsequent to the quarter end (ASX release 22 October 2024), confirmed
the continuity of mineralisation and support future exploration of the Keep Seismic Target Boab
is of the view that the Keep Zinc-Lead Prospect area is now established as a compelling subsurface target with scope for future discovery.
Project Execution Update
As part of Boab’s project execution derisking initiative, the Company has commenced detailed due
diligence on the potential acquisition of the DeGrussa process plant from Sandfire Resources
Limited (ASX:SFR) (“Sandfire”) for use at Sorby Hills. The DeGrussa process plant, located 900km
northeast of Perth, formed part of the world-class DeGrussa Copper mine that was built and
operated by Sandfire between 2011 and May 2023. Since the cessation of operations in early FY24,
the DeGrussa process plant has been kept on active care and maintenance by Sandfire.
Preliminary due diligence undertaken by Boab during the quarter has indicated the DeGrussa
process plant, which comprises a conventional crushing, milling, flotation, dewatering and
filtration circuit is ideally suited for the requirements of Sorby Hills. Over the coming quarter, Boab
will work closely with preferred EPC Contractor GR Engineering Service (“GRES”) (ASX release 21
November 2022) to undertake a thorough review of the DeGrussa process plant and assess the
technical and economic benefit of its incorporation into the Sorby Hills Project.
Boab Managing Director and CEO Simon Noon stated: “Throughout the quarter, the Company has
been proactively assessing multiple opportunities to materially reduce the upfront capital
expenditure for Sorby Hills. The identification of available second-hand process plants has been
one such initiative and the DeGrussa plant represents the most technically suitable option for
Sorby Hills. We look forward to completing our due diligence on the DeGrussa opportunity over
the coming quarter and quantifying its potentially significant impact on Project economics.”
_____________________________________________________________________________________________________________________________ ____________________
Quarterly Report September 2024
Page 3
During the quarter, the Company continued to work with relevant government departments to
progress approvals including EPA 45c amendment, works approvals and EPBC referral.
Financial and Corporate Overview
The consolidated cash balance of the Company as at 30 September 2024 was A$4.35M. During the
period, the Company paid $137k to related parties. These payments were made to Directors of
Boab Metals Limited in relation to salaries and directors’ fees, on normal commercial terms.
On 26 September, 2024 the Company released its Annual Report and has subsequently advised
the market that its Annual General Meeting will be held on 26 November, 2024.
The Board of Directors have authorised this announcement for release to the market.
FOR FURTHER INFORMATION, PLEASE CONTACT:
Simon Noon
Managing Director & CEO
Phone: +61 (0)8 6268 0449
Email: info@boabmetals.com
Table 1: Sorby Hills Mineral Resource Estimate – Pb Domains only.
Grade
Contained Metal
Tonnes
(Mt)
Pb
Zn
Ag
Pb
Zn
Ag
%
%
g/t
kt
kt
koz
Measured
12.6
3.5%
0.4%
43
444
45
17,521
Indicated
11.0
3.4%
0.4%
34
377
46
12,114
Inferred
23.6
2.7%
0.5%
31
645
117
23,406
Total Resource
47.3
3.1%
0.4%
35
1,465
207
53,042
Resource Classification
Note: Tonnes and Grade are rounded. Reported at a 1.0% Pb Cut-Off. Discrepancies in calculated Contained Metal is due to rounding .
Table 2: Sorby Hills Ore Reserve Statement.
Grade
Contained Metal
Ore Reserve
Category
Ore
(Mt)
Pb (%)
Ag (g/t)
Pb (kt)
Ag (Moz)
Proved
10.4
3.5%
42
358
14.1
Probable
4.9
3.5%
32
172
5.0
Total Ore Reserve
15.2
3.5%
39
531
19.1
Note: Tonnes and Grade are rounded. Reported at a 1.0% Pb cut-off. The above data has been rounded to the nearest 10,000 tonnes ore, 0.1%
lead grade and 1,000 lead tonnes, 1g/t silver grade and 100,000 silver ounces. Discrepancies in calculated Contained Metal is due to rounding.
Ore Reserves have been calculated using metal prices of A$3,313.91/t Pb and A$37.89/oz Ag and royalties of 4.3% of gross revenue including
allowable deductions.
_____________________________________________________________________________________________________________________________ ____________________
Quarterly Report September 2024
Page 4
About Boab Metals Limited
Boab Metals Limited (“Boab”, ASX: BML) is a Western Australian-based exploration and
development company with interests in Australia and South America. In Australia, the Company is
currently focused on developing the Sorby Hills Lead-Silver-Zinc Joint Venture Project in WA. Sorby
Hills is located 50km from the regional centre of Kununurra in the East Kimberley and has access
to existing sealed roads to transport concentrate from site to the facilities at Wyndham Port, a
distance of 150km. Established infrastructure and existing permitting allows for fast-track
development and production.
Boab owns a 75% interest in the Joint Venture with the remaining 25% interest held by Henan
Yuguang Gold & Lead Co. Ltd. Boab holds an option to acquire Yuguang’s interest in the Project.
Compliance Statements
The Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves
(the ‘JORC Code’) sets out minimum standards, recommendations and guidelines for Public
Reporting in Australasia of Exploration Results, Mineral Resources and Ore Reserves.
Information included in this activities report relating to Exploration Results has been extracted
from the announcement titled KEEP confirmed as a Target for Further Exploration dated 22
October 2024 , available to view at www.boabmetals.com.au. The Company confirms that the form
and context in which the Competent Person’s findings are presented have not been materially
modified from the original announcement.
Information included in this activities report relating to Mineral Resources has been extracted from
the Mineral Resource Estimate dated 17 December 2021, available to view at
www.boabmetals.com.au. The Company confirms that it is not aware of any new information or
data that materially affects the information included in the Mineral Resource Estimate and that all
material assumptions and technical parameters underpinning the estimates, continue to apply
and have not materially changed. The Company confirms that the form and context in which the
Competent Person’s findings are presented have not been materially modified from the Mineral
Resource Estimate.
Information included in this activities report relating to Ore Reserves, Production Targets and
Financial Forecasts has been extracted from the Sorby Hills Definitive Feasibility Study dated 19
January 2023 and Sorby Hills FEED Study Results dated 6 June 2024, both available to view at
www.boabmetals.com.au. The Company confirms that it is not aware of any new information or
data that materially affects the information included in the Ore Reserve Statement and that all
material assumptions and technical parameters underpinning the estimates, production targets
and financial forecasts continue to apply and have not materially changed. The Company confirms
that the form and context in which the Competent Person’s findings are presented have not been
materially modified from the Ore Reserves Statement.
_____________________________________________________________________________________________________________________________ ____________________
Quarterly Report September 2024
Page 5
Metal Equivalent Calculation Method
The contained metal equivalence formula is based on the Sorby Hills Feed Study including:
•
•
•
•
•
•
Lead Price US$2,253.19/t;
Lead recovery of 91.0% (weighted average of oxide and fresh Pb recoveries);
Lead Payability rate of 95%;
Silver Price US$27.4/oz;
Silver recovery of 81.8% (weighted average of oxide and fresh Ag recoveries); and
Silver Payability rate of 95%.
It is Boab’s opinion that all elements included in the metal equivalent calculation have a
reasonable potential to be recovered and sold.
The formula used to calculate lead equivalent grade is:
MetalEq (%) = Gpri + (Gpri × [∑i Ri Si Vi Gi ]/(Rpri SpriVpriGpri))
where R is the respective metallurgical metal recovery rate, S is the respective smelter return rate,
V is metal price/tonne or ounce, and G is the metal commodity grade for the suite of potentially
recoverable commodities (i) relative to the primary metal (pri).
Metal equivalents are highly dependent on the metal prices used to derive the formula. Boab
notes that the metal equivalence method used above is a simplified approach. The metal prices
are based on the DFS values adopted and do not reflect the metal prices that a smelter would pay
for concentrate nor are any smelter penalties or charges included in the calculation. Owing to
limited metallurgical data, zinc grades are not included at this stage in the lead equivalent grade
calculation.
FEED Study Macroeconomic Assumptions
Assumption
Unit
FY2025
FY2026
FY2027
FY2028
FY2029+
Lead Price
US$/t
2,259
2,268
2,269
2,254
2,251
Silver Price
US$/oz
24.8
25.8
26.4
27.3
27.5
Exchange Rate
A$:US$
0.70
0.70
0.70
0.69
0.68
_____________________________________________________________________________________________________________________________ ____________________
Quarterly Report September 2024
Page 6
APPENDIX 1
INTERESTS IN TENEMENTS
Farm-In Agreements/
Projects/Tenements
Location
Held at Start of
Quarter
Held at End of
Quarter
Sorby Hills Project
M80/196
M80/197
M80/285
M80/286
M80/287
75%
75%
75%
75%
75%
75%
75%
75%
75%
75%
100%
100%
100%
51%
51%
100%
51%
51%
51%
51%
51%
51%
51%
51%
100%
100%
NT, Australia
100%
100%
100%
100%
Colombia
100%
100%
WA, Australia
E80/5317
Borroloola West
Project
EL31354
EL26938
EL26939
EL28658
EL30305
NT, Australia
MLN624
Manbarrum Project
EL24395
MA24518
MA26581
Urrao Project
2791
_____________________________________________________________________________________________________________________________ ____________________
Quarterly Report September 2024
Page 7
Rule 5.5
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
BOAB METALS LIMITED
Quarter ended (“current quarter”)
ABN
43 107 159 713
Consolidated statement of cash flows
1.
Cash flows from operating activities
1.1
Receipts from customers
1.2
Payments for
30 SEPTEMBER 2024
Current quarter
$A’000
Year to date
(3 months)
$A’000
-
-
(1,036)
(1,036)
(b) development
-
-
(c) production
-
-
(d) staff costs
(157)
(157)
(e) administration and corporate costs
(199)
(199)
-
-
51
51
(a) exploration & evaluation (if expensed)
1.3
Dividends received (see note 3)
1.4
Interest received
1.5
Interest and other costs of finance paid
-
-
1.6
Income taxes paid
-
-
1.7
Government grants and tax incentives
-
-
1.8
Other:Recharge of staff costs and other
administration costs to the Sorby JV
30
30
Net cash from / (used in) operating
activities
(1,311)
(1,311)
1.9
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 1
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Consolidated statement of cash flows
2.
Cash flows from investing activities
2.1
Payments to acquire or for:
Current quarter
$A’000
Year to date
(3 months)
$A’000
(a) entities
-
-
(b) tenements
-
-
(11)
(11)
(d) exploration & evaluation
-
-
(e) investments
-
-
(36)
(36)
(a) entities
-
-
(b) tenements
-
-
(c) property, plant and equipment
-
-
(d) investments
-
-
(e) other non-current assets
-
-
2.3
Cash flows from loans to other entities
-
-
2.4
Dividends received (see note 3)
-
-
2.5
Other (provide details if material)
-
-
2.6
Net cash from / (used in) investing
activities
(47)
(47)
3.
Cash flows from financing activities
3.1
Proceeds from issues of equity securities
(excluding convertible debt securities)
-
-
(c) property, plant and equipment
(f)
2.2
other non-current assets
Proceeds from the disposal of:
3.2
Proceeds from issue of convertible debt
securities
-
-
3.3
Proceeds from exercise of options
-
-
3.4
Transaction costs related to issues of equity
securities or convertible debt securities
-
-
3.5
Proceeds from borrowings
-
-
3.6
Repayment of borrowings
-
-
3.7
Transaction costs related to loans and
borrowings
-
-
3.8
Dividends paid
-
-
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 2
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Consolidated statement of cash flows
Current quarter
$A’000
Year to date
(3 months)
$A’000
3.9
Other (provide details if material)
-
-
3.10
Net cash from / (used in) financing
activities
-
-
4.
Net increase / (decrease) in cash and
cash equivalents for the period
4.1
Cash and cash equivalents at beginning of
period
5,708
5,708
4.2
Net cash from / (used in) operating
activities (item 1.9 above)
(1,311)
(1,311)
4.3
Net cash from / (used in) investing activities
(item 2.6 above)
(47)
(47)
4.4
Net cash from / (used in) financing activities
(item 3.10 above)
-
-
4.5
Effect of movement in exchange rates on
cash held
-
-
4.6
Cash and cash equivalents at end of
period
4,350
4,350
5.
Reconciliation of cash and cash
equivalents
Current quarter
$A’000
Previous quarter
$A’000
at the end of the quarter (as shown in the
consolidated statement of cash flows) to
the related items in the accounts
5.1
Bank balances
297
556
5.2
Call deposits
4,000
5,100
5.3
Bank overdrafts
-
-
5.4
Other (provide details)
53
52
5.5
Cash and cash equivalents at end of
4,350
quarter (should equal item 4.6 above)
Payments to related parties of the entity and their associates
5,708
6.
6.1
6.2
Aggregate amount of payments to related parties and their
associates included in item 1
Current quarter
$A'000
(137)*
Aggregate amount of payments to related parties and their
associates included in item 2
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of,
and an explanation for, such payments.
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 3
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
7.
Financing facilities
Note: the term “facility’ includes all forms of
financing arrangements available to the entity.
Add notes as necessary for an understanding of the
sources of finance available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
7.1
Loan facilities
-
-
7.2
Credit standby arrangements
-
-
7.3
Other (please specify)
-
-
7.4
Total financing facilities
-
-
7.5
Unused financing facilities available at quarter end
7.6
Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing
facilities have been entered into or are proposed to be entered into after quarter end,
include a note providing details of those facilities as well.
8.
Estimated cash available for future operating activities
-
$A’000
8.1
Net cash from / (used in) operating activities (item 1.9)
8.2
(Payments for exploration & evaluation classified as investing
activities) (item 2.1(d))
8.3
Total relevant outgoings (item 8.1 + item 8.2)
(1,311)
8.4
Cash and cash equivalents at quarter end (item 4.6)
4,350
8.5
Unused finance facilities available at quarter end (item 7.5)
8.6
Total available funding (item 8.4 + item 8.5)
4,350
8.7
Estimated quarters of funding available (item 8.6 divided by
item 8.3)
3.31
8.8
If item 8.7 is less than 2 quarters, please provide answers to the following questions:
8.8.1
(1,311)
-
-
Does the entity expect that it will continue to have the current level of net operating
cash flows for the time being and, if not, why not?
Answer: Not Applicable.
8.8.2
Has the entity taken any steps, or does it propose to take any steps, to raise further
cash to fund its operations and, if so, what are those steps and how likely does it
believe that they will be successful?
Answer: Not Applicable.
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 4
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
8.8.3
Does the entity expect to be able to continue its operations and to meet its business
objectives and, if so, on what basis?
Answer: Not Applicable.
Note: where item 8.7 is less than 2 quarters, all of questions 8.8.1, 8.8.2 and 8.8.3 above must be answered.
Compliance statement
1
This statement has been prepared in accordance with accounting standards and policies which comply with
Listing Rule 19.11A.
2
This statement gives a true and fair view of the matters disclosed.
Date:
25 October, 2024
Authorised for release by the Board of Directors of Boab Metals Limited
Notes
1.
This quarterly cash flow report and the accompanying activity report provide a basis for informing the market about the entity’s activities
for the past quarter, how they have been financed and the effect this has had on its cash position. An entity that wishes to disclose
additional information over and above the minimum required under the Listing Rules is encouraged to do so.
2.
If this quarterly cash flow report has been prepared in accordance with Australian Accounting Standards, the definitions in, and
provisions of, AASB 6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash Flows apply to this
report. If this quarterly cash flow report has been prepared in accordance with other accounting standards agreed by ASX purs uant to
Listing Rule 19.11A, the corresponding equivalent standards apply to this report.
3.
Dividends received may be classified either as cash flows from operating activities or cash flows from investing activities, depending on
the accounting policy of the entity.
4.
If this report has been authorised for release to the market by your board of directors, you can insert here: “By the board”. If it has been
authorised for release to the market by a committee of your board of directors, you can insert here: “By the [name of board committee –
eg Audit and Risk Committee]”. If it has been authorised for release to the market by a disclosure committee, you can insert here: “By
the Disclosure Committee”.
5.
If this report has been authorised for release to the market by your board of directors and you wish to hold yourself out as complying
with recommendation 4.2 of the ASX Corporate Governance Council’s Corporate Governance Principles and Recommendations, the
board should have received a declaration from its CEO and CFO that, in their opinion, the financial records of the entity have been
properly maintained, that this report complies with the appropriate accounting standards and gives a true and fair view of the cash flows
of the entity, and that their opinion has been formed on the basis of a sound system of risk management and internal control which is
operating effectively.
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 5
Share your feedback
Discover