Sorby Hills FEED Study Results
Released
Released
Announcement PDF
6 June 2024
Sorby Hills Project FEED Study
Boab Metals Limited (ASX: BML) (“Boab” or the “Company”) is pleased to announce the results
of its Front-End Engineering & Design (“FEED”) Study for its 75% owned Sorby Hills Lead-SilverZinc Project (“Sorby Hills” or “the Project”), located in the Kimberley Region of Western
Australia. The FEED Study augments and enhances the Sorby Hills Definitive Feasibility Study
(“DFS”) released by the Company in January 2023.
HIGHLIGHTS
Project updates (excluding any change in macroeconomic assumptions) have delivered an
increase of +A$73M Net Cash Flow and +A$41M NPV8 compared to the DFS.
Key Base Case Project Metrics include upfront Capital Expenditure of A$264M, average C1
Cost of US$ 0.36/lb payable Lead (including silver credits), pre-tax NPV8 of A$411M, pre-tax
IRR of 37%, and average annual EBITDA of A$126M.
Importantly, the net change to pre-production Capital Expenditure is limited and project pretax cash flows over the initial 5 years of production have improved by +A$150M providing a
stronger profile to support debt financing.
Assuming current spot pricing1 for Lead, Silver, Exchange Rate and current Benchmark Lead
Treatment and Silver Refining Charges results in an NPV8 of A$596M, pre-tax IRR of 47% and
average annual EBITDA of A$160M.
Key Project updates include:
•
Updated post FEED pricing for the Process Plant EPC Contract provided by
GR Engineering Service (“GRES”).
•
Updated mining schedule bringing forward mining of the high-grade Norton Deposit.
•
Updated metal recovery and concentrate grades for the Norton Deposit based on
new metallurgical testwork on core recovered during the Phase VII drilling program.
•
Updated pricing for the Mining and Earthworks Contracts provided on a bundled basis
and based on the optimised site layout and mining schedule.
•
Updated tailings strategy with above-ground tailings disposal being employed for the
Life of Mine as opposed to in-pit deposition previously adopted in the DFS.
Boab Managing Director and CEO, Simon Noon, stated:
“Following the DFS, we identified clear opportunities to optimise and de-risk the Project both
technically and economically. Over the past year, we have pursued these opportunities in
conjunction with completing Front End Engineering & Design on our Process Plant with GRES.
We are pleased to present the results of our work during this period in the form of this FEED
Study. We now look forward to accelerating our engagement with financiers and further
advancing Sorby Hills toward a Final Investment Decision.”
1
As at 28 May 2024 – See page 12
Cautionary Statements
The FEED Study discussed herein has been undertaken to explore the technical and
economic feasibility of developing an open pit mine and adjacent processing facility to
economically and sustainably exploit the Sorby Hills Lead-Silver-Zinc Mineral Resource
located in the Kimberley Region of Western Australia.
The Sorby Hills Project is subject to a Joint Venture Agreement between Boab and Yuguang.
Boab holds a 75% interest in the Joint Venture via its 100% owned subsidiary Sorby Hills Pty
Ltd. The Production Target and financial forecasts presented in the FEED Study are shown
on a 100% Project basis and assume that outstanding environmental approvals are granted.
The Production Target underpinning financial forecasts included in the FEED Study
comprises 57% Measured Resources, 26% Indicated Resources and 17% Inferred Resources.
The estimated Ore Reserves and Mineral Resource underpinning the Base Case Production
Target have been prepared by a Competent Person in accordance with the requirements in
the JORC Code.
There is a low level of geological confidence associated with Inferred Resources and there is
no certainty that further exploration work will result in the conversion of Inferred Resources
to Indicated Resources or return the same grade and tonnage distribution. The stated
Production Target is based on the Company’s current expectations of the future results or
event and should not be solely relied upon by investors when making investing decisions.
Further evaluation work and appropriate studies are required to establish sufficient
confidence that this target will be met.
The economic outcomes associated with the FEED Study are based on certain assumptions
made for commodity prices, concentrate treatment and recovery charges, exchange rates
and other economic variables, which are not within the Company’s control and subject to
change from time to time. Changes in such assumptions may have a material impact on
economic outcomes.
To achieve the range of outcomes indicated in the FEED Study, debt and equity funding will
be required. Investors should note that there is no certainty that the Joint Venture may be
able to raise the amount of funding when needed and/or reach a Final Investment Decision
by the date proposed in the FEED Study. It is also possible that such funding may only be
available on terms that may be dilutive to, or otherwise affect the value of Boab’s existing
shares. It is also possible that Boab could pursue other ‘value realisation’ strategies such as a
sale or partial sale of the Company’s share of the Project.
This announcement contains forward‐looking statements. Boab has concluded it has a
reasonable basis for providing the forward‐looking statements included in this
announcement and believes it has a reasonable basis to expect it will be able to fund the
development of the project. However, several factors could cause actual results, or
expectations to differ materially from the results expressed or implied in the forward-looking
statements. Given the uncertainties involved, investors should not make any investment
decisions based solely on the results of the FEED Study.
ASX Announcement
Page 2
Project Summary
The Sorby Hills Lead-Silver-Zinc Project (“Sorby Hills”, the “Project”) is the largest undeveloped,
near-surface Lead-Silver-Zinc deposit in Australia. The Project comprises granted mining leases
covering six known Lead-Silver-Zinc deposits in the Kimberley Region of Western Australia,
50km northeast of Kununurra and 90km east of Wyndham Port (Figure 1).
Boab Metals Ltd (“Boab”, the “Company”) holds a 75% interest in the Project. Boab’s Joint
Venture partner in the Project is Henan Yuguang Gold & Lead Co. Ltd, China’s largest Lead
smelters and silver producer2.
In addition to the Sorby Hills Project, Boab holds a 100% interest in both the Manbarrum ZincLead-Silver Project, located 25km east of Sorby Hills and the Eight Mile Creek Project, located
immediately south of Sorby Hills. Both project areas comprise tenure overlying geology
genetically and stratigraphically related to that containing mineralisation at Sorby Hills.
Combined, the Sorby Hills Project, the Manbarrum Project and the Eight Mile Creek Project,
support Boab’s vision to establish a long-life presence in the east Kimberley Region.
Figure 1: Location of the Sorby Hills Project with respect to Boab’s other 100% owned LeadSilver-Zinc exploration assets in the region.
2
Yuguang gold and lead group limited liability company (yuguanggold-lead.com.cn)
ASX Announcement
Page 3
On 19 January 2023, Boab released a Definitive Feasibility Study (“DFS”) for the Project3. Over the
initial 8.5-year processing period contemplated by the DFS, 18.3Mt of ore was proposed to be
mined and processed through the Sorby Hills process plant to deliver an average 103ktpa of
concentrate containing 64ktpa of payable lead and 2Mozpa of payable silver to generate a pretax NPV8 of A$370M and IRR of 35%. The DFS economics were underpinned by Ore Reserves of
15.2Mt at 3.5% Pb and 39g/t Ag, and a large, well-defined Mineral Resource of 47.3Mt at 3.1% Pb,
35g/t Ag and 0.4% Zn4.
The Front-End Engineering and Design (“FEED”) Study presented herein augments and
enhances the DFS via various specific updates to the Project.
Key updates include:
•
Updated post FEED pricing for the Process Plant EPC Contract provided by
GR Engineering Service (“GRES”).
•
Updated metal recovery for the Norton Deposit based on new metallurgical testwork on
core recovered during the Phase VII drilling program.
•
Updated mining schedule bringing forward mining of the Norton Deposit and highgrade silver production.
•
Updated pricing for the Mining and Bulk Earthworks Contracts provided on a bundled
basis and based on the optimised site layout and mining schedule.
•
Updated tailings strategy with above-ground tailings disposal being employed for the
Life of Mine as opposed to in-pit deposition previously adopted.
No further updates to the Mineral Resource or Ore Reserve have been undertaken at this point.
A high-level comparison of the DFS and FEED Study base case results and the impact of
adopting current macroeconomics (“Spot Case”) is shown in Table 1.
Table 1: Comparison of FEED Study Result with the DFS
Item
Macroeconomics
Unit
Variance
“Spot Case”
Pb = US$2,253/t, Ag = US$27.4/oz; A$:US = $0.68,
Pb TC = US$125/t conc., Ag RC = US$1.25/oz paid
See Page 12
Mining Inventory
3
4
DFS
FEED
18.3 Mt at 3.4% Lead and 39g/t Silver
Recovered Lead
kt
571
575
1%
575
Recovered Silver
Moz
18.6
18.6
(0%)
18.6
Upfront Capital Cost
A$M
245
264
8%
264
C1 Cost (incl. credits)
US$/lb Pb
0.39
0.36
(8%)
0.25
Net Cash Flow
A$M
705
778
10%
1,067
LOM Average EBITDA
A$M
119
126
5%
160
Pre-Tax NPV8
A$M
370
411
11%
596
Pre-Tax IRR
%
35%
37%
3%
47%
ASX Release 19 January 2023
ASX Release 17 December 2021
ASX Announcement
Page 4
Table 2: Sorby Hills Mineral Resource Estimate – Pb Domains only
Grade
Contained Metal
Resource
Classification
Tonnes
(Mt)
Pb
Zn
Ag
Pb
Zn
Ag
%
%
g/t
kt
kt
koz
Measured
12.6
3.5%
0.4%
43
444
45
17,521
Indicated
11.0
3.4%
0.4%
34
377
46
12,114
Inferred
23.6
2.7%
0.5%
31
645
117
23,406
Total
47.3
3.1%
0.4%
35
1,465
207
53,042
Note: Tonnes and Grade are rounded. Reported at a 1.0% Pb Cut-Off. Discrepancies in calculated Contained Metal
is due to rounding.
Figure 2: Location of the Sorby Hills deposits, Resource classification and mining leases
with respect to local geology.
ASX Announcement
Page 5
Key Project Updates
Tailings Strategy
The DFS outlined a tailings strategy whereby above-ground tailings deposition was employed
for the initial stages of production after which the B-Deposit pit and Omega South Pit would be
utilised for in-pit tailings deposition as mining in the respective pits concluded.
Following further discussion with Tetra Tech Coffey (who undertook the design of the proposed
tailings storage facility (“TSF”) and additional testwork on tailings samples), the Company
decided to revert to a single above-ground TSF.
The TSF will be located approximately 1.3km south-east of the process plant and will be built in
eight stages (6 x 4m lifts and 1 x 2m lift) resulting in a final footprint of approximately 102 Ha. The
TSF will hold approximately 17.4Mt of tailings generated from the process plant.
Tetra Tech Coffey has completed a revised design of the TSF for the FEED Study.
Mining Schedule
An updated mining and processing schedule has been prepared for the FEED study by
independent mining consultant Entech Pty Ltd (Figure 3 and Figure 4). Like the DFS, the FEED
Study proposes the open-pit mining and processing of 18.3Mt of ore from five of the six Sorby
Hills deposits, namely: Omega, A, B, Beta, and Norton (Table 3).
Table 3: FEED Study Production Target
Source
Total
Waste
Ore
Strip Ratio
Lead
Silver
Unit
Mt
Mt
Mt
t:t
%
g/t
A Pit
4.1
3.7
0.5
8.1
3.7%
16.4
B Pit
14.8
12.6
2.3
5.5
3.2%
17.4
Norton
21.4
19.5
1.9
10.0
4.0%
78.5
Omega 1
11.3
8.9
2.4
3.7
4.1%
47.0
Omega 2
9.4
7.9
1.5
5.3
3.0%
35.0
Omega 3
26.6
24.2
2.3
10.3
3.4%
28.3
Omega 4
10.4
9.2
1.2
7.9
4.0%
47.5
Omega South
21.1
18.3
2.8
6.5
2.9%
29.5
Beta Pit
35.6
32.2
3.4
9.5
3.3%
41.5
Total
154.8
136.5
18.3
7.5
3.4%
38.8
The Production Target underpinning financial forecasts included in the FEED Study comprises
57% Measured Resources, 26% Indicated Resources and 17% Inferred Resources. The estimated
Ore Reserves and Mineral Resource underpinning the Base Case Production Target have been
prepared by a Competent Person in accordance with the requirements in the JORC Code.
ASX Announcement
Page 6
As a result of the updated tailings strategy, the requirement for the lower-grade Omega South
Pit to be mined earlier in the schedule to facilitate in-pit tailings deposition has been relaxed
allowing the higher-grade Norton Deposit to brought forward. This optimisation of the schedule
has resulted in the earlier production of metal, thus bringing forwarded revenue, particularly
that derived from silver (Figure 5).
Figure 3: FEED Study Mining Schedule showing total tonnes mined by source together with
the average mined lead and silver grade through time
Figure 4: FEED Study Processing Schedule showing total tonnes processed by Resource
Classification together with the average processed lead and silver grade through time
ASX Announcement
Page 7
Norton Metal Recoveries
Metallurgical testwork conducted during the DFS5 returned metal recoveries for the Norton
deposit that were unexpectedly lower than those achieved on samples from the other Sorby
Hills deposits. While historic testwork had suggested higher recoveries were achievable at
Norton, there was insufficient core available to undertake further testwork at the time therefore
the reduced recoveries were adopted for the DFS. The reduced recoveries resulted in
approximately 500kt of ore (17.7kt Lead and 1.3Moz Silver) dropping out of the Norton mining
inventory compared with the Sorby Hills Pre-Feasibility Study6.
During 2023, the Company undertook a Phase VII diamond drilling campaign of which 13 holes
were dedicated to the collection of metallurgical core samples from the Norton deposit. An
additional 16 batch tests were undertaken7. The inclusion of these results together with the 5
used for the DFS has improved the average metal recoveries at the Norton deposit from 78% to
83% for lead and confirmed the silver recovery at 78% (Table 4).
Table 4: Comparison of DFS and FEED Study Recoveries
Deposit / Study
Average Lead Recovery
Average Silver Recovery
Norton Deposit - DFS
78%
78%
Overall Average - DFS
91%
82%
Norton Deposit – FEED Study
83%
78%
Overall Average – FEED Study
92%
82%
Figure 5: Comparison of cumulative metal recovered highlighting the acceleration of silver
production and improved lead recoveries at Norton versus the DFS
ASX Release 19 December 2021
ASX Release 25 August 2020
7
ASX Release 22 May 2024
5
6
ASX Announcement
Page 8
Process Plant FEED and EPC Re-pricing
As for the DFS, the FEED Study is based on a conventional crush-mill-float processing circuit
(Figure 6) to produce lead-silver concentrate at approximately 103ktpa. Initially, the process
plant ore throughput rate will be 1.5Mtpa, however this will increase to 2.25Mtpa after 1 year of
production via the brining online of a ball mill that would be installed during the construction
phase and provide operational flexibility during year 1 if required.
Preliminary designs for the Sorby Hill process plant were developed for the DFS and used as the
basis for the EPC tender and associated pricing undertaken at the time. Following the DFS,
GRES was commissioned to undertake FEED on the process plant and associated non-process
infrastructure to progress design definition and maturity allowing for a more confident and
refined pricing of the EPC contract.
Site layout changes include the relocation of the crusher, crushed ore bin and SAG/Ball mill to
be situated within a cut-site established in the existing ridgeline. Furthermore, optimisation and
rationalisation of the process plant, buildings and structures was undertaken.
Pricing for the process plant EPC contract in the DFS was A$130.6M based on tenders received
at the time. Following the conclusion of FEED, the EPC contract has been repriced at A$134.9M
representing a 3% increase over the DFS pricing.
Figure 6: 3D Model of the Sorby Hills Process Plant produced by GRES during FEED
ASX Announcement
Page 9
Mining and Bulk Earthworks Contract
The mining and bulk earthworks pricing for the DFS were based on separate tenders
undertaken at the height of post COVID inflation. Subsequent to the DFS, and following the
optimisation of the site layout, mining schedule and tailings strategy, the Company took the
opportunity to retest the market with respect to these packages an on a bundled basis. The
Company received bundled tenders from multiple groups and has used this information for
updating direct mining costs and bulk earthworks for the purpose of the FEED Study.
Results of the updated mining tender compared to the DFS are shown in Table 5.
Table 5: Comparison of total Mining Costs between the DFS and FEED Study
Item
Unit
DFS
FEED Study
Variance
Life of Mine (incl. Pre-Strip)
A$M
591
561
(5%)
Unit Cost per BCM mined
A$/BCM
10.26
9.40
(8%)
Unit Cost per payable Lead
US$/lb Pb
0.34
0.31
(9%)
The bulk earthworks package includes updates in the location of Mine Water Settling Pond
(“MWSP”) and Evaporation Pond (“EVP”) and the inclusion of an Evaporation Basin (“EVB”) to
provide further flexibility for the Project’s water management strategy. The EVP design has been
updated by Tetra Tech Coffey to accommodate a forecast increased in water recovery from the
TSF and a new Restricted Area Catchment (“RAC”) incorporating specified area of the process
plant and non-process infrastructure.
Results of the updated bulk earthworks tender compared to the DFS are shown in Table 6.
Table 6: Comparison of Life of Mine bulk earthwork cost between the DFS and FEED Study
Item
Unit
DFS
FEED Study
Variance
Prelims & Site Establishment
A$M
17.9
10.9
(7.0)
Tailings Dam
A$M
8.7
11.7
3.0
Evaporation Pond
A$M
5.6
6.1
0.5
Mine Water Settling Pond
A$M
2.3
1.0
(1.3)
Water Storage Facility
A$M
4.1
2.8
(1.3)
Evaporation Basin
A$M
-
2.8
2.8
Haul Road
A$M
11.3
1.6
(9.7)
Total Bulk Earthworks
A$M
50.0
36.9
(13.1)
The significantly reduced expenditure on the Haul Road resulted from a decision to include the
construction and bulk earthworks component of the package under the mining contractor’s
scope of works. The mining contractor would be responsible for providing and maintaining an
appropriate and suitable Haul Road for the duration of the contract.
ASX Announcement
Page 10
Other Updates
Concentrate Transport
An in-principal agreement between the Company and the departmental representatives of the
Shire of Wyndham and East Kimberley (“SWEK”) provides for the ability to transport an
increased volume of concentrate product to port per load in exchange for a modest payment
contribution to SWEK for the upgrade of the road’s infrastructure. The proposal was presented
and approved at the 2023 end of year meeting of the SWEK council.
The approval for concessional loading allows Boab to transport approximately 20% more
product per road train. This increase in additional overall movement of material per load results
in an approximate A$5 per wmt saving over the cost for non-concessional loading vehicle
movements equating to an A$4.5M saving in haulage costs over the current Life of Mine.
ROM Loading
As a result of the updated mining tender, ROM ore handling cost has been reduced from A$1.69/t
ore to $1.50/t ore resulting in a Life of Mine cash flow improvement of +A$3.5M.
Water Management
Pit dewatering requirements and the overall site water balance was revised based on the
updated mining schedule and tailings strategy. While the revised mining schedule has
increased project water drawdown (~31%), the updated strategy of above-ground tailings allows
for completed open pits to be used for water management purposes thus reducing the volume
of water required to be treated through the water treatment plant and providing operational
flexibility in terms of water management strategy more generally. Consequently, a
reassessment of the water piping requirements has reduced associated capital costs by A$5.0M.
Camp Refurbishment
In September 2022, Boab paid A$1.3M to secure and relocate a second-hand camp comprising
178 rooms and laundry facilities. The DFS proposed this camp was to be refurbished to provide
accommodation facilities for construction workers after which a new facility built in Kununurra
in conjunction with SWEK would house the operational workforce.
For the FEED Study, the second-hand camp will be fully refurbished and upgraded to house the
operational workforce on site (+A$7.4M). Whilst the Company continues discussions with SWEK,
the provision by the Company for a full-scale on-site accommodation facility at Sorby Hills
decouples the project timeline from any potential risk relating to SWEK securing funding for
the proposed Kununurra facility.
Contingencies
Additional capital provisions have been made for owner’s spares (+A$3.0M). Upfront Capital
Contingency has increased from A$20.9M to A$22.7M.
Other than the changes described in this announcement, no further material updates to
operating or capital costs have been adopted in this FEED Study.
ASX Announcement
Page 11
Macroeconomic Assumptions
To highlight the impact of Project changes alone, the Company has adopted the same macroeconomic assumptions that were used for the DFS (Table 7).
Table 7: FEED Study macroeconomic assumptions
Assumption
Unit
FY2025
FY2026
FY2027
FY2028
FY2029+
Lead Price
US$/t
2,259
2,268
2,269
2,254
2,251
Silver Price
US$/oz
24.8
25.8
26.4
27.3
27.5
Exchange Rate
A$:US$
0.70
0.70
0.70
0.69
0.68
Lead Treatment Charge
US$/t conc.
125
125
125
125
125
Silver Refining Charge
US$/oz
1.25
1.25
1.25
1.25
1.25
Based on spot prices as at 28 May 2024: US$2,344/t Lead, US$32.1/oz Silver, A$:US$0.66,
Benchmark Lead Treatment Charge of US$98/t and Silver Refining Charge of US$0.95/oz
Project NPV8 = A$596M, Pre-Tax IRR = 47% and average annual EBITDA = A$160M.
Operating Cost Summary
The DFS forecast a C1 unit operating cost of US$0.39/lb payable lead including silver credits. An
independent review by CRU Global confirmed Sorby Hills as a 1st quartile lead producer on an
ex-works (i.e. excluding credits and selling costs)8. Through a combination of operational
optimisations including updated mining contract pricing and enhanced recoveries at Norton,
unit operating costs have decreased to US$0.36/lb payable lead (Table 8).
Table 8: Operating Cost Summary
Operating Costs
8
FEED Study
DFS
Variance
Unit
A$M
A$/t
US$/lb paid Pb
US$/lb paid Pb
%
Logistics
117
6.40
0.07
0.07
(4%)
Mining
547
29.96
0.31
0.34
(8%)
Processing
388
21.27
0.22
0.22
(1%)
G&A
88
4.80
0.05
0.05
(1%)
Lead Treatment
160
8.76
0.09
0.09
-
C1 Costs (ex. Credits)
1,300
71.19
0.74
0.77
(5%)
Net Silver Credits
(661)
(36.21)
(0.37)
(0.38)
(1%)
C1 Costs
639
34.98
0.36
0.39
(8%)
Royalties
95
5.20
0.05
0.05
-
Sustaining Capital
26
1.45
0.01
0.03
(52%)
AISC
760
41.63
0.43
0.48
(10%)
ASX Release 6 November 2023
ASX Announcement
Page 12
Capital Cost Summary
Table 9: Capital Cost Summary
FEED Study
Capital Costs
DFS
Variance
A$M
A$M
A$M
-
134.9
130.5
4.3
31.9
4.9
36.9
54.5
(17.6)
Water Management
8.1
11.7
19.8
24.8
(5.0)
Accommodation Village
11.5
-
11.5
4.1
7.4
Other Infrastructure
8.5
0.6
9.1
10.1
(1.0)
Owners Costs
32.0
-
32.0
31.0
0.9
Contingency
22.7
-
22.7
20.9
1.8
Pre-Production Opex
15.0
-
15.0
14.6
0.4
-
9.3
9.3
9.3
-
264.5
26.5
290.9
299.8
(8.8)
Pre-Production
Sustaining
Total
Unit Cost
A$M
A$M
EPC Contract
134.9
Site Est./Bulk Earthworks
Closure Costs
Total Capital Expenditure
Base Case Project Cashflows.
The Project generates A$778M of pre-tax free cash flow over the Life of Mine with pre-production
capital expenditure of A$264M, a maximum negative cash balance of A$282M and an average
annualised EBITDA of A$126M per annum during operations. The Project generates a pre-tax
NPV8 of A$411M and an IRR of 37%. A summary of the annual Project financials, and the physicals
underpinning them are shown in Table 10.
Concentrate Offtake
The Company has held positive discussions with Offtakers dating back prior to the DFS and
subsequently has shortlisted and advanced negotiations with preferred parties.
Negotiations have advanced to a stage where the Company anticipates awarding offtake in the
coming months.
Project Financing
It is proposed that the Project will be funded via a combination of debt and equity contributed
by the Sorby Hills Joint Venture partners in proportion to their interest in the Joint Venture.
Assessment of the debt-carrying capacity of the Project based on indicative commercial bank
project financing terms and the FEED study project cashflows demonstrate that the Project can
support up to 60% gearing at a Debt Service Coverage Ratios typical of those required to support
project financing. Following the release of the FEED Study, the Company will step up its
engagement with financiers, including the completion of typical project finance due diligence
workstreams including an update of the Independent Technical Review, to secure financing
binding terms sheet by Q4 2024.
ASX Announcement
Page 13
Table 10: Base Case Project Annual Physicals and Cashflow Summary
Calendar Year
Unit
Total
2025
2026
2027
2028
2029
2030
2031
2032
2033
2034
2035
2036
Waste Mined
Mt
136.5
-
3.8
11.7
14.3
25.7
25.4
21.0
17.3
13.0
4.2
0.2
-
-
Ore Mined
Mt
18.3
-
0.4
2.1
2.3
2.4
2.5
2.3
2.0
1.1
3.0
0.3
-
-
Lead Grade
%
3.4%
-
3.8%
4.1%
3.2%
3.8%
3.3%
3.1%
3.1%
3.6%
3.4%
2.9%
-
-
Silver Grade
g/t
39
-
24
39
28
60
50
22
27
42
41
50
-
-
% Measured
%
57%
-
67%
92%
65%
72%
90%
72%
48%
17%
-
-
-
-
% Indicated
%
26%
-
33%
8%
35%
27%
9%
27%
50%
31%
31%
-
-
-
% Inferred
%
17%
-
-
-
-
1%
1%
2%
3%
53%
69%
100%
-
-
Ore Processed
Mt
18.3
-
-
1.4
2.3
2.3
2.3
2.3
2.3
2.3
2.3
1.1
-
-
Lead Grade
%
3.4%
-
-
5.5%
3.4%
4.0%
3.5%
3.1%
3.0%
2.5%
3.5%
3.0%
-
-
Silver Grade
g/t
39
-
-
47
30
59
54
24
27
30
41
41
-
-
Lead Recovery
%
91.6%
-
-
90.9%
94.1%
90.0%
88.0%
92.7%
94.7%
93.8%
90.3%
90.3%
-
-
Silver Recovery
%
81.7%
-
-
87.2%
86.2%
82.2%
81.4%
86.9%
86.9%
85.7%
70.4%
70.3%
-
-
Concentrate Produced
kt
873
-
-
109
110
126
112
99
98
80
97
42
-
-
Lead Grade
%
65.8%
-
-
64.2%
65.6%
63.5%
62.4%
65.9%
66.0%
65.7%
72.2%
72.3%
-
-
Silver Grade
g/t
664
-
-
529
532
860
878
479
535
730
677
770
-
-
Lead Revenue
A$M
1,803
-
-
198
225
260
215
207
208
165
226
98
-
-
Silver Revenue
A$M
693
-
-
59
70
131
121
57
62
71
82
40
-
-
Total Revenue
A$M
2,496
-
-
257
295
392
337
264
269
237
308
138
-
-
Lead Treatment
A$M
(160)
-
-
(18)
(20)
(24)
(20)
(18)
(18)
(15)
(18)
(8)
-
-
Silver Refining
A$M
(32)
-
-
(3)
(3)
(6)
(6)
(3)
(3)
(3)
(4)
(2)
-
-
Royalties
A$M
(95)
-
-
(10)
(11)
(14)
(12)
(10)
(11)
(9)
(12)
(5)
-
-
Net Revenue
A$M
2,209
-
-
227
260
348
299
233
238
210
274
123
-
-
Logistics
A$M
(117)
-
-
(14)
(15)
(17)
(15)
(13)
(13)
(11)
(13)
(6)
-
-
Mining
A$M
(547)
-
-
(51)
(62)
(94)
(93)
(81)
(71)
(54)
(36)
(4)
-
-
Processing
A$M
(388)
-
-
(38)
(47)
(47)
(47)
(47)
(47)
(47)
(47)
(24)
-
-
G&A
A$M
(88)
-
-
(10)
(10)
(10)
(10)
(10)
(10)
(10)
(10)
(5)
-
-
Operating Cash Flow
A$M
1,069
-
-
114
126
180
134
81
96
88
168
84
-
-
Upfront Capex
A$M
(264)
(131)
(133)
-
-
-
-
-
-
-
-
-
-
-
Sustaining Capex
A$M
(26)
-
-
(12)
(1)
(3)
(1)
(0)
-
-
-
(5)
(4)
-
Net Cash Flow
A$M
778
(131)
(133)
101
125
177
133
81
96
88
168
78
(4)
-
Cumulative Cash Flow
A$M
(131)
(265)
(163)
(38)
139
271
352
449
536
704
782
778
778
NPV
A$M
411
%
37%
IRR
Average EBITDA
A$M
126
Operating Margin
%
43%
ASX Announcement
2037
Page 14
Project Execution Timeline
Table 11: Indicative Project Execution Timeline
Item
Indicative Date
FEED Study Completion
June 2024
EPBC Approval / EPA 45c Amendment
June – November 2024
Close out Offtake / Project Financing workstreams
June – November 2024
Final Investment Decision
Commencement of Site Establishment / Early Works
Commencement of Process Plant Construction
First Production
December 2024
January 2025
July 2025
January – March 2027
Opportunities
Key opportunities include:
•
Backup Power Review - The Company continues to explore initiatives to reduce the size
of the proposed backup diesel power station to further reduce the cost of power supply
and further increase to percentage of green, grid power from the hydroelectric plant
beyond the current ~90%.
•
Further analysis of Norton metal recoveries - The additional metallurgical testwork on
Norton has improved average lead recoveries from ore sourced at that deposit. Further
analysis will be aimed at gaining a clear understanding of the geological controls on
recoveries and therefore the ability to selectively mine the deposit.
•
Updated Resource Statement – Following further analysis of the Norton metallurgy,
Boab will seek to update the Mineral Resource Estimate to incorporate drilling
completed subsequent to the current estimate. Given that a significant portion of the
drilling was in-fill drilling, the Company does not anticipate a material change in the
Resource size or grade.
•
Updated Production Target and Ore Reserve - Following further analysis of the Norton
metallurgy and upda
Share your feedback