Fully Underwritten A$5.0 Million Placement and
Entitlement Offer to Progress the
Sorby Hills Lead-Silver Project
Boab Metals Limited (ASX: BML) (Boab or the Company) is pleased to announce a fully
underwritten A$5.0 million capital raising to progress its 75% owned Sorby Hills Lead-Silver-Zinc
Project (Sorby Hills Project), located in the Kimberley Region of Western Australia. The Company
has also utilised it’s At-the-Market Subscription Agreement (ATM) with Acuity Capital (announced
on 22 December 2023) to raise an additional $185,000 (inclusive of costs).
HIGHLIGHTS
•
Fully underwritten A$5.0 million capital raising to progress the Sorby Hills Project
comprising:
o
A$1.7 million share placement to institutional investors; and
o
A$3.3 million Non-Renounceable Entitlement Offer to eligible shareholders.
•
Binding commitments have been received.
•
Boab’s Board have all committed to participating in the entitlement offer.
•
Funds will be used to finalise workstreams required to support project financing, advance
an exploration drilling campaign during the coming dry season, ramp up the Sorby Hills
project team and early site establishment works.
•
A further $0.18 million raised utilising ATM facility.
Boab Managing Director and CEO, Simon Noon, stated:
“We are confident of finalising our offtake arrangements and FEED Study over the coming
months. Whilst modest in size, the capital raising will allow us to effectively leverage the outcome
of these milestones into our project financing and project execution workstreams. The funds
raised will also support a drilling program, including Boab maiden drilling at our Manbarrum
Zinc-Silver-Lead Project located 25km east of Sorby Hills. The Boab Board strongly encourages
existing shareholders to take up their rights under the entitlement offer and participate in what
is shaping as an exciting period for the Company.”
Structure of the Offers
•
A fully underwritten placement to institutional investors (Placement); and
•
A fully underwritten pro-rata 1 for 5.6 non-renounceable entitlement offer (Entitlement
Offer) to eligible shareholders.
The Placement and the Entitlement Offer are together referred to as the ‘Offers’.
Placement
The Placement raised approximately $1.7 million (before costs) through the issue of
approximately 17 million fully paid ordinary shares (Shares) at an issue price of $0.10 per Share
(Placement Shares) to sophisticated, professional and institutional investors utilising its
placement capacity under Listing Rule 7.1. Allotment of the Placement Shares is expected to
occur on Friday, 10 May 2024.
The Company has engaged Morgans Corporate Limited and Unified Capital Partners Pty Ltd as
joint lead managers, bookrunners and underwriters to the Placement (JLMs).
Entitlement Offer
The Company is also undertaking pro rata non-renounceable entitlement offer of new Shares to
eligible shareholders at an issue price of $0.10 per Share (New Share) to raise approximately $3.3
million (before costs).
The issue price of A$0.10 per New Share represents a:
•
20% discount to the last traded Share price of $0.125 on 30 April 2024; and
•
18.2% discount to the 5-day VWAP of $0.123.
Shareholders with a registered address in Australia and New Zealand (Eligible Shareholders) are
entitled to acquire 1 New Share for every 5.6 existing Shares held as at 5:00pm (AWST) on
Wednesday, 8 May 2024 (Record Date). Eligible Shareholders that take up their entitlement in
full, may also apply for additional New Shares (Top-Up Shares) up to a maximum of 100% of their
entitlement.
The Entitlement Offer is fully underwritten by the JLMs pursuant to the terms of an Underwriting
Agreement (refer to the risk section of this announcement for a summary of the termination
events relating to the Underwriting Agreement).
The Directors have all committed to participating in the Entitlement Offer.
At-the-market (ATM) raise
The Company is pleased to announce that it has utilised its ATM subscription agreement with
Acuity Capital (see announcement on 22 December 2023) to raise $185,000 (inclusive of costs)
through the set-off of 1,230,000 Company collateral shares previously issued to Acuity Capital
under the ATM (Set-off Shares).
The Set-off Shares reduce the 9,000,000 Company collateral shares which Acuity Capital is
otherwise required to return to the Company upon termination of the ATM.
The Set-off Shares have a deemed price of $0.15 per share, being a premium of 6.3% to the
Company’s 15 trading day volume weighted average Share price (VWAP) of $0.1411 to 30 April 2024
(inclusive).
The funds raised will be utilised towards Advancing the Sorby Hills Project and general working
capital purposes.
ASX Announcement
Page 2
Key details of the Entitlement Offer
Aspect
Details
Ratio
1 New Share for every 5.6 Shares held on the Record Date
Offer price
$0.10 per New Share
Discount
Offer price of $0.10 per New Share represents a 20% discount
to the last closing price of $0.125 (as at 30 April 2024) and a
18.2% discount to the 5-day VWAP of $0.123.
Number of New Shares
Up to 32,761,209 New Shares
Renounceability
The Entitlement Offer is non-renounceable
Gross proceeds
Approximately $3.3 million (before costs)
Top-Up Offer
Eligible shareholders who subscribe for their Entitlement in full are eligible to apply for additional
New Shares (Additional New Shares) that are not subscribed for by other Eligible Shareholders
under the Entitlement Offer (Top-Up Offer). The Additional New Shares will be offered at the issue
price of $0.10, being the same issue price for New Shares under the Entitlement Offer.
The Additional New Shares will only be issued to the extent there is sufficient shortfall, and
applications will be subject to the allocation policy which is detailed in the Offer Booklet.
Additional New Shares will not be issued to an applicant if the issue would otherwise contravene
the Listing Rules or any applicable law.
Any New Shares not applied for under the Entitlement Offer or Top-Up Offer will be subscribed
for by the JLMs in accordance with the Underwriting Agreement.
Use of Funds
The Offers will raise a total of A$5.0 million.
Funds raised under the Offers will be applied in the following manner:
Item
Total
Advancing the Sorby Hills Project toward FID including completion of project
optimisation workstreams, technical, legal due diligence workstreams required
by potential project financiers and ramp up of the project execution team
A$1.9M
Early site works at Sorby Hills Project
A$0.5M
Drilling campaign at Sorby Hills Project and Manbarrum Project
A$1.1M
Working capital purposes
A$1.5M
Total
A$5.0M
ASX Announcement
Page 3
Indicative Timetable
Event
Announcement of Placement and Entitlement Offer,
Appendix 3B and Cleansing Statement
Date
Friday, 3 May 2024
Shares commence trading ex-entitlement basis
Tuesday, 7 May 2024
Record Date for eligibility under the Entitlement Offer
5:00pm (AWST) on
Wednesday, 8 May 2024
Allotment of New Shares under the Placement
Friday, 10 May 2024
Entitlement Offer opens
Offer Booklet and Entitlement and Acceptance forms
dispatched
Monday, 13 May 2024
Commencement of trading of New Shares issued under the
Placement
Monday, 13 May 2024
Despatch of holding statements for New Shares under the
Placement
Tuesday, 14 May 2024
Last day to extend Entitlement Offer closing date
Monday, 20 May 2024
Entitlement Offer closes
5:00pm (AWST) on Thursday,
23 May 2024
New Shares quoted on a deferred settlement basis
Friday, 24 May 2024
Results of Entitlement Offer announced to ASX
Tuesday, 28 May 2024
Allotment of New Shares under Entitlement Offer
Tuesday, 28 May 2024
Commencement of trading of New Shares under the
Entitlement Offer
Wednesday, 29 May 2024
Despatch of holding statements for the New Shares under the
Entitlement Offer
Monday, 3 June 2024
Note: The timetable above is indicative only and may change. The Company reserves the right to amend any
or all of these dates and times without notice, subject to the Corporations Act, the Listing Rules and other
applicable laws. In particular, the Company reserves the right to extend the Closing date and to accept late
Applications (either generally or in particular cases). Any extension of the Closing date will have a
consequential effect on the allotment date of New Shares. The commencement of quotation of the New
Shares is subject to confirmation from ASX. The Company also reserves the right not to proceed with the
Entitlement Offer in whole or in part at any time prior to allotment and issue of the New Shares. In that
event, the relevant application monies (without interest) will be returned in full to applicants.
ASX Announcement
Page 4
Key Risk Factors
Presented below are the key existing and emerging risks that could materially impact the
operating performance, financial results and financial position of the Company.
Additional risks and uncertainties that the Company is currently unaware of, or that it currently
considers to be immaterial, may also become important factors that adversely impact the
Company’s operating and financial performance and financial position.
You should be aware that an investment in the Company has a number of risks, some of which
are specific to the Company and some of which relate to listed securities generally, and many of
which are beyond the control of the Company.
Before investing in the Company shares, you should consider whether this investment is suitable
for you. Potential investors should consider publicly available information about the Company
(such as that available on the websites of the Company and ASX), carefully consider their personal
circumstances and consult their stockbroker, solicitor, accountant or other professional advisers
before making an investment decision.
(a)
Future capital requirements
The Company will require further financing in the future, in addition to amounts raised under the Offers.
Any additional equity financing may be dilutive to Shareholders, may be undertaken at lower prices
than the current market price or may involve restrictive covenants which limit the Company's
operations and business strategy. Debt financing, if available, may involve restrictions on financing and
operating activities.
As an exploration entity, the Company is making a loss, meaning it is reliant on raising funds from
investors or lenders in order to continue to fund its operations and to scale growth.
Although the Directors believe that additional capital can be obtained, no assurances can be made that
appropriate capital or funding, if and when needed, will be available on terms favourable to the
Company or at all. If the Company is unable to obtain additional financing as needed, the Company
may be required to reduce the scope of its activities, which could have a material adverse effect on the
Company's activities and could affect the Company's ability to continue as a going concern.
The Company may undertake additional offerings of Shares and of Securities convertible into Shares in
the future. The increase in the number of Shares issued and outstanding and the possibility of sales of
such Shares may have a depressive effect on the price of Shares. In addition, as a result of such
additional Shares, the voting power of the Company's existing Shareholders will be diluted.
(b)
Exploration, development and operating risks and costs
The prospects of the Company should be considered in light of the risks, opportunities, expenses and
difficulties frequently encountered by companies at a similar stage of production and development.
The Company's initiatives may not proceed to plan, with potential for delay in the timing of exploration
and development activities.
There can be no assurance that exploration and development will result in the discovery of further
mineral deposits. Even if an apparently viable deposit is identified, there is no guarantee that it can be
economically exploited.
The future exploration and development activities of the Company and the future development of
mining operations at the Company’s Projects (or any future projects that the Company may acquire an
interest in) may be affected by a range of factors, including:
•
geological, metallurgical and hydrological conditions;
•
limitations on activities due to seasonal weather patterns;
•
lack of availability or shortages of equipment, spare parts and consumables;
ASX Announcement
Page 5
•
access to appropriately skilled labour, competent operation and managerial employees,
contactors and consultants;
•
unanticipated operational and technical difficulties, mechanical failure of operating plant and
equipment, industrial and environmental accidents;
•
industrial action, disputes or disruptions;
•
industrial and environmental accidents;
•
increases in costs and cost overruns;
•
financial failure, or default by any future alliance or service provider to the Company which may
require the Company to face unplanned expenditure;
•
native title process;
•
changing government regulations; and
•
other factors beyond the control of the Company.
In addition, the construction of any proposed development may exceed the expected timeframe or
cost for a variety of reasons out of the Company's control. Any delays to project development could
adversely affect the Company's operations and financial results and may require the Company to raise
further funds to complete the project development and commence operations.
(c)
Resource estimation risks
The Company has reported a Mineral Resource in respect of the Sorby Hills Project. However, resource
estimates are expressions of judgement based on knowledge, experience and industry practice.
Estimates which were valid when initially calculated may alter significantly or become more uncertain
when new information or techniques become available due to, for example, additional drilling or
production tests over the life of the mine. Downward revision of Mineral Resource estimates may
adversely affect the Company’s operational and financial performance. There can be no guarantee that
the Mineral Resource will be successfully converted to an Ore Reserve. In addition, by their very nature,
resource estimates are imprecise and depend to some extent on interpretations which may prove to
be inaccurate.
(d)
Tenure, access and grant of licences / permits
The Company’s operations are subject to receiving and maintaining licences and permits from
appropriate governmental authorities. There is no assurance that delays will not occur in connection
with obtaining all necessary grants or renewals of licences / permits for the proposed operations,
additional licences / permits for any possible future changes to operations, or additional permits
associated with new legislation.
Prior to any development on any of its properties, subsidiaries of the Company must receive licences /
permits from appropriate governmental authorities. There is no certainty that the Company will hold
all licences / permits necessary to develop or continue operating at any particular property.
(e)
Land access risk
Land access is critical for exploration and exploitation to succeed. It requires both access to the mineral
rights and access to the surface rights.
Minerals rights may be negotiated and acquired. In all cases, the acquisition of prospective exploration
and mining licences is a competitive business in which proprietary knowledge or information is critical
and the ability to negotiate satisfactory commercial arrangements with other parties is often essential.
The Company may not be successful in acquiring or obtaining the necessary licences to conduct
exploration or evaluation activities outside of the mineral tenements that it owns.
Access to land for exploration and evaluation purposes can be obtained by:
•
private access and compensation agreement with the landowner;
ASX Announcement
Page 6
•
purchase of surface rights; or
•
through judicial rulings.
•
However, access rights to licences can be affected by many factors, including:
•
travel restrictions, quarantining procedures or other impediments to the free movement of
personnel;
•
surface title land ownership negotiations, which are required before ground disturbing
exploration activities can commence within the jurisdictions in which the Company operates;
•
permitting for exploration activities, which are required in order to undertake most exploration
and exploitation activities within the jurisdictions in which the Company operates; and
•
natural occurrences, including inclement weather, volcanic eruptions, lahars and earthquakes.
All of these issues have the potential to delay, curtail and preclude the Company's operations. While the
Company will have the potential to influence some of these access issues, and retains staff to manage
those instances where negotiations are required to gain access, it is not possible for the Company to
predict the extent to which the above-mentioned risks and uncertainties may adversely impact the
Company's operations.
(f)
Reliance on key personnel
The Company's future depends, in part, on its ability to attract and retain key personnel. It may not be
able to hire and retain those personnel at compensation levels consistent with its existing
compensation and salary structure. The Company's future also depends on the continued contributions
of its executive management team and other key management and technical personnel, the loss of
whose services would be difficult to replace. In addition, any inability of the Company to attract
appropriately qualified personnel could have a material adverse effect on the Company's business.
(g)
Insurance and uninsured risks
The Company faces various risks in conducting its business and may lack adequate insurance coverage
or may not have the relevant insurance coverage. Although insurance is maintained in line with
industry practice, no assurance can be given that such insurance will be available in the future on
commercially reasonable terms or that any cover will be adequate and available to cover any or all
claims.
(h)
Commodity price and exchange rate risks
Commodity prices fluctuate and are affected by many factors beyond the control of the Company. Such
factors include supply and demand fluctuations for gold, technological advancements, forward selling
activities and other macro-economic factors.
Furthermore, international prices of various commodities are denominated in United States dollars,
whereas the income and expenditure of the Company are and will be taken into account in Australian
currency, exposing the Company to the fluctuations and volatility of the rate of exchange between the
United States dollar and the Australian dollar as determined in international markets.
(i)
Risk of adverse publicity
The Company's activities will involve mineral exploration and mining and regulatory approval of its
activities may generate public controversy. Political and social pressures and adverse publicity could
lead to delays in approval of, and increased expenses for, the Company's activities. The nature of the
Company's business attracts a high level of public and media interest and, in the event of any resultant
adverse publicity, the Company's reputation may be harmed.
(j)
Third party risk
The operations of the Company will require involvement of a number of third parties, including
suppliers. With respect to these third parties, and despite applying best practice in terms of
precontracting due diligence, the Company is unable to completely avoid the risk of:
ASX Announcement
Page 7
•
financial failure or default by a participant in any joint venture to which the Company may
become a party; and
•
insolvency, default on performance or delivery by any operators, contractors or service
providers.
These contracts typically contain provisions providing for early termination of the contracts upon giving
varying notice periods and paying varying termination amounts. The early termination of any of these
contracts, for any reason, may mean that the Company will not realise the full value of the contract,
which is likely to adversely affect the growth prospects, operating results and financial performance of
the Company.
(k)
Occupational health and safety
Site safety and occupational health and safety outcomes are a critical element in the reputation of the
Company and its ability to retain and be awarded new contracts in the resources industry. While the
Company has a strong commitment to achieving a safe performance on site and a strong record in
achieving safety performance, a serious site safety incident could impact upon the reputation and
financial performance of the Company.
Additionally, laws and regulations, as well as the requirements of customers, may become more
complex and stringent or the subject of increasingly strict interpretation and enforcement. Failure to
comply with applicable regulations or requirements may result in significant liabilities, suspended
operations and increased costs. Industrial accidents may occur in relation to the performance of the
Company's services. Accidents, particularly where a fatality or serious injury occurs, or a series of
accidents, may have operational and financial implications for the Company, which may negatively
impact the financial performance and future potential of the Company.
(l)
Management of growth
There is a risk that management of the Company will not be able to implement the Company's growth
strategy. The capacity of management to properly implement and manage the strategic direction of
the Company may affect the Company's financial performance.
(m) Unforeseen expenses
The Company's cost estimates and financial forecasts include appropriate provisions for material risks
and uncertainties and are considered fit for purpose for the activities of the Company. If risks and
uncertainties prove to be greater than expected, or if unforeseen material risks and uncertainties arise,
the expenditure proposals of the Company are likely to be adversely affected.
(n)
Environmental and social risks
The operations and proposed activities of the Company are subject to Provincial and Federal laws and
regulations concerning the environment. The current or future operations of the Company, including
exploration and development activities and commencement of production on the Projects, require
permits from various governmental authorities. Such operations are governed by laws and regulations
that govern prospecting, mining, development, production, taxes, labour standards, occupational
health, waste disposal, toxic substances, land use, environmental protection, mine safety, and other
matters. Companies engaged in the development and operation of mines and related facilities
generally experience increased costs and delays in production as a result of needing to comply with
applicable laws, regulations and permits. There can be no assurance that all permits that the Company
requires for future, exploration, development, construction and operation of mining facilities and the
conduct of mining operations will be obtainable on reasonable terms or that such laws and regulations
would not have an adverse effect on the operations of the Company.
The cost and complexity of complying with the applicable environmental laws and regulations may
prevent the Company from being able to develop potentially economically viable mineral deposits.
Although the Company believes that it is in compliance in all material respects with all applicable
environmental laws and regulations, there are certain risks inherent to its activities, such as accidental
spills, leakages or other unforeseen circumstances, which could subject the Company to extensive
liability.
ASX Announcement
Page 8
Government authorities may, from time to time, review the environmental bonds that are placed on
permits. The Directors are not in a position to state whether a review is imminent or whether the
outcome of such a review would be detrimental to the funding needs of the Company.
(o)
Native title and Aboriginal Heritage
The Company's tenements may include areas over which legitimate common law native title or
indigenous rights of persons in Australia exist. If native title or indigenous rights do exist, the ability of
the Company to gain access may be adversely affected. The Company will closely monitor the potential
effect of native title or indigenous claims involving its tenements.
Access to land for exploration purposes can be adversely affected by land ownership, including private
(freehold) land, pastoral lease and native title land or claims under the Native Title Act 1993 (Cath) (NTA)
(or similar legislation in the jurisdiction where the Company operates). The effect of the NTA is that
existing and new tenements held by the Company may be affected by native title claims and
procedures.
There is a risk that a determination could be made that native title exists in relation to land the subject
of a tenement held or to be held by the Company which may affect the operation of the Company’s
business and development activities. If it is determined that native title does exist, or a native title claim
has been registered, the Company may need to comply with procedures under the NTA in order to
carry out its operations or to be granted any additional rights required. Such procedures may take
considerable time, involve the negotiation of significant agreements, may involve access rights, and
require the payment of compensation to those persons holding or claiming native title in the land the
subject of a tenement.
The involvement in the administration and determination of native title issues may have a material
adverse impact on the position of the Company in terms of cash flows, financial performance, business
development, and the Share price.
(p)
Grant of future authorisations to explore and mine
If the Company discovers an economically viable mineral deposit that it then intends to develop, it will,
among other things, require various approvals, licences and permits before it will be able to mine the
deposit. There is no guarantee that the Company will be able to obtain all required approvals, licenses
and permits. To the extent that required authorisations are not obtained or are delayed, the Company’s
operational and financial performance may be materially adversely affected.
(q)
Mine development
Possible future development of mining operations at the Sorby Hills Project is dependent on a number
of factors including, but not limited to, the acquisition and/or delineation of economically recoverable
mineralisation, favourable geological conditions, receiving the necessary approvals from all relevant
authorities and parties, seasonal weather patterns, unanticipated technical and operational difficulties
encountered in extraction and production activities, mechanical failure of operating plant and
equipment, shortages or increases in the price of consumables, spare parts and plant and equipment,
cost overruns, access to the required level of funding and contracting risk from third parties providing
essential services.
If the Company commences production on one of its Projects, its operations may be disrupted by a
variety of risks and hazards which are beyond the control of the Company. No assurance can be given
that the Company will achieve commercial viability through the development of its Projects.
The risks associated with the development of a mine will be considered in full should the Projects reach
that stage and will be managed with ongoing consideration of stakeholder interests.
(r)
Metallurgy
Metal and/or mineral recoveries are dependent upon the metallurgical process that is required to
liberate economic minerals and produce a saleable product and by nature contain elements of
significant risk such as:
•
identifying a metallurgical process through test work to produce a saleable metal and/or
concentrate;
ASX Announcement
Page 9
(s)
•
developing an economic process route to produce a metal and/or concentrate; and
•
changes in mineralogy in the ore deposit can result in inconsistent metal recovery, affecting
the economic viability of the project.
Unforeseen risk
There may be other risks which the Directors are unaware of at the time of issuing the Offer Booklet in
connection with the Entitlement Offer which may impact on the Company, its operations and/or the
valuation and performance of its Shares.
(t)
Infectious diseases
The price of the Company’s Securities may be adversely affected by the economic uncertainty caused
by infectious diseases (including COVID-19). Measures to limit the transmission of infectious diseases
implemented by governments around the world (such as travel bans and quarantining) may adversely
impact the Company’s operations and may interrupt the Company carrying out its contractual
obligations or cause disruptions to supply chains.
(u)
Underwriting risk
The Company has entered into an underwriting agreement with the JLMs under which the JLMs have
agreed to fully underwrite the Entitlement Offer, subject to the terms and conditions of the
Underwriting Agreement.
The Underwriting Agreement contains customary representations and warranties and indemnities in
favour of the Underwriter for an agreement of this nature. If the Underwriting Agreement is terminated
for any reason, the Company may not receive the full amount of the proceeds expected under the
Entitlement Offer, its financial position might change and it might need to take other steps to raise
capital, including by raising additional debt.
Capitalised terms in this summary have the meaning given to them in the Underwriting Agreement
unless otherwise defined in this Announcement.
The Underwriter may, by notice given to the Company, and without cost or lia
Share your feedback
Discover