Highlights:
Cash Position:
The cash balance as at the date of this report is ~$660,000.
• Cash balance at 30 June 2015 was ~$275,000 (including $79,000
received under the Share Purchase Plan). An Appendix 5B report is
attached.
The company raised a total of $585,250 via a Share Purchase Plan which
opened during the quarter and closed on 17 July 2015.
Operational Highlights for the quarter:
BML has four focused business objectives:
1. PL 110/94 MAIBELE NORTH:
TO EXPAND KNOWN RESOURCE FOR POTENTIAL MINING.
• Grow and reclassify the current JORC resource status from
inferred to indicated by infill drilling and met drilling
• Extend the known resource by step out drilling of new SQUID
TDEM and DHEM conductor targets
Action: 12,500m drill program commenced during the quarter.
(See Figure 3 below.)
Botswana Metals Limited
Suite 3, 16 Cotham Road, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
2. PL54/98 TAKANE:
TO EXPLORE THE UNTAPPED POTENTIAL FOR SEVERAL NEW
DISCOVERIES
Action:
23 VTEM anomalies prioritised down to 4 for immediate work
SQUID EM technology field program completed over 4
targets areas during the quarter.
SQUID and VTEM being interpreted for drill targets to be
presented to the JV.
The BML board believes this area has the potential to be declared
a new mineralised province located along the well-known Limpopo
Belt as it extends into Botswana on its eastern border from
Zimbabwe (see Figure 9.)
3. PL59/2008: 100% OWNED BY BML
TO EXPLORE FOR THE EASTERN EXTENSION TO MAIBELE NORTH
ORE BODY.
• Anomalies identified are within 4km and along strike to the
Maibele North orebody (see Figure 10.)
• The objective is to drill a number of holes into the best
targets before the end of 2015.
Action: exploration commenced in July 2015 with the SQUID
technology commissioned and now onsite.
4. BML EXPLORATION PROFOLIO:
TO GROW THE CURRENT PORTFOLIO FOCUSING ON THE EASTERN
BOARDER OF BOTSWANA ALONG THE LIMPOPO BELT.
• 1000sq km under licence of which
• 184sq km under JV with BCL Limited.
Botswana Metals Limited
Suite 3, 16 Cotham Road, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
Action:
• 3000sq km of new PL applications were lodged in 2015 and are
pending processing by the DOM.
• During the quarter, work commenced on BML’s 100% owned
PL59/2008.
BML is committed to its total exploration portfolio of which 184km is
under JV with BCL Limited.
In 2015 BML made applications for several new prospecting licences that
if granted will significantly increase the total exploration area secured by
BML under its management.
The board strategy is to secure the most prospective ground along the
Limpopo belt where BML has accumulated in-depth geological and
geophysical knowledge during nearly 10 years of exploration. (see Figure
2.)
Progress achieved in the quarter to 30th June 2015:
PL 110/94: Maibele North JV with BCL Limited
The JV committed to a further 12,500m of drilling at Maibele North which
commenced in June 2015. Refer Figures 3 to 7
• To date 16 holes have been completed.
• All step out holes (7) to date were designed to test SQUID TDEM
and/or DHEM conductors and 6 have so far intersected
significant sulphides.
Step out holes intersected significant sulphides
o 200m beneath the known ore body
o 250 m to the east of the known ore body
o 400m to the north-east of the known ore body
Botswana Metals Limited
Suite 3, 16 Cotham Road, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
The drilling program is also confirming
o Numerous thick sulphide intersections within the existing
orebody
o Highly encouraging sulphide intersections at SQUID EM
conductor targets along strike and adjacent to existing orebody
o SQUID EM surveys have identified a number of strong
conductors up to 1km along strike from orebody
PL 54/98: Takane JV with BCL Limited
o During the quarter the known 23 VTEM anomalies at PL 54/98
Takane were prioritised down to 4 targets for immediate follow
up (see Figure 9).
o SQUID TDEM and ground magnetic surveys were employed and
completed over these 4 priority targets in the June 2015 quarter.
o A review and interpretation to determine the next steps forward
is in progress between the JV partners.
PL59/2008: Shashe South
o BML contracted the services of a South African company,
Spectral Geophysics who has performed all the SQUID EM for
the JV ground, to conduct SQUID EM surveying on BMLs 100%
PL59/2008.
o The SQUID program commenced late in July 2015 and will focus
on three areas as shown at Figure 8 and 10 in this report.
Corporate:
Cash Position and Capital Raising
Cash at bank was $275,000 at 30 June 2015.
Share Purchase Plan
During the quarter the Company offered a Share Purchase Plan to Eligible
Shareholders. The Plan closed following the end of the quarter and the
Botswana Metals Limited
Suite 3, 16 Cotham Road, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
Company raised a total of $585,250 (before costs) through the issue of
new shares at an issue price of 0.75 cent ($0.0075) per new share.
The Company now has 648,355,435 shares on issue.
Exploration Activities for the June 2015 quarter:
Location Map and Schedule of Prospecting Licences held by BML.
Figure 1: Location of Botswana Metals Limited Exploration portfolio in Botswana
Exploration areas held in Botswana
The Company holds the following prospecting licences in Botswana:
Tenement
Magogaphate
PL 110/94
Mokoswane
PL 111/94
Renewal /
Expiry Date
Percentage
Holding
Title Holder
31/03/16
100
African Metals (Pty) Ltd
31/03/16
100
African Metals (Pty) Ltd
Botswana Metals Limited
Suite 3, 16 Cotham Road, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
Comment
J/V with BCL Ltd
effective 01/04/14
J/V with BCL Ltd
effective 01/04/14
ABN 96 122 995 073
Takane
PL 54/98
31/03/16
100
African Metals (Pty) Ltd
J/V with BCL Ltd
effective 01/04/14
Shashe South
PL 059/2008
30/09/2016
100
African Metals (Pty) Ltd
Renewal granted
until 30/09/16
Central
PL 070/2008
30/09/2016
100
African Metals (Pty) Ltd
Central Sampa
PL 111/2011
30/06/2014
100
African Metals (Pty) Ltd
Renewal granted
until 30/09/16
Renewal
application lodged
31/03/14
African Metals (Pty) Ltd is a wholly owned subsidiary of the Company.
Minerals Holdings (Botswana) Pty Ltd holds a 5% net profit share interest in PL 110/94,
PL 111/94 & PL 54/98.
PL 110/94, PL 111/94 and PL 54/98 were extended for a further two years to 31 April
2016.
On 1 April 2014 a Farm-In Joint Venture agreement with BCL Limited became
effective where BCL Limited can earn an initial 40% interest in 3 PLs based on making
certain expenditure commitments. If BCL Limited funds to the end of a Bankable
Feasibility Study then BCL can earn a 70% equity interest in the 3 JV PL’s being 110/94,
111/94 and 54/98.
Several new PL applications were lodged with the Department of Mines in the March
2015 quarter which are still being processed. These are shown in light green in figure
2 below.
Other than the details above, the Company did not acquire or dispose of any other
tenements or beneficial interests in farm-in agreements during the quarter.
Botswana Metals Limited
Suite 3, 16 Cotham Road, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
Figure 2: BML exploration tenement portfolio in Botswana. Prospecting Licences subject to the Joint
Venture with BCL are shaded light blue.
JOINT VENTURE EXPLORATION ACTIVITIES FOR THE QUARTER
PL110/94 - Maibele North
During the June 2015 Quarter, the Joint Venture partners, BCL Limited, committed to
an extensive program of Infill, Metallurgical and Extension drilling at the Maibele
North deposit. Totalling ~12,500m the program is divided evenly between in-resource
drill holes and extension holes targeting the number of significant conductor targets
along strike and adjacent to the main orebody.
Botswana Metals Limited
Suite 3, 16 Cotham Road, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
Figure 3: shows the Maibele North orebody and in red the 12 additional step out holes that will be
drilled in addition to the 5 step out holes shown in blue
The focus of the program is to both upgrade and grow the JORC-compliant Inferred
resource that was announced to the market during the March quarter. The estimate
was performed by independent consultants, MSA South Africa, from an extensive drill
program undertaken in 2014 in conjunction with BML’s Joint Venture partners BCL
Limited.
At a 0.3% Ni cut-off the resource stands at:
Cut-off Tonnes Ni
Cu
Pt
Pd
(%Ni)
(Mt)
(%)
(%)
(g/t)
(g/t)
0.30
2.38
0.72 0.21 0.08
0.36
Rh
(g/t)
0.04
Ru
(g/t)
0.05
Au
(g/t)
0.10
Ground work completed during the quarter and to the date of this report included
4076.84m of drilling in 16 completed and 3 pre-collared holes as well as fixed loop
SQUID Time Domain Electromagnetic Surveys (TDEM) designed to assess the strike
and depth potential of the mineralisation to the northeast. A number of significant
conductors have been identified from this program and are the subject of the
extensive resource extension campaign currently underway.
Botswana Metals Limited
Suite 3, 16 Cotham Road, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
Initial Drilling Results
A total of 16 holes have been completed to date. Nine metallurgical holes and 7
extension holes had been completed with significant sulphide intersections observed
in many of the holes. A further 3 holes had commenced with RC pre-collars by the
date of this report. Samples are currently being prepared for laboratory assay and
results will be released when available.
Figure 4: shows infill and step out holes drilled to the end of the June quarter. SQUID targets so far
drilled have all encountered mineralisation with at least three more planned with the furthest up to
1km to the east of Maibele North resource.
Highlights of the Metallurgical and Infill program include:
•
MARD0101: Mineralisation was intersected between 119.28 and 123.91m
(4.63m down hole) including 0.56m thick zone of massive sulphides. This
met/infill drill hole planned to target the thick mineralisation zone behind
MADD058.
Botswana Metals Limited
Suite 3, 16 Cotham Road, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
MARD0103: Several zones of disseminated, semi-massive and massive
sulphide mineralisation were intersected between 112.47m to 121.67m (9.2m
down-hole) and 125.36m to 147.27m (21.91m down-hole).
• MARD0104: intercepted 4.2m of sulphide mineralisation from 111.53m,
including 0.97m of massive sulphide
• MARD0105: intercepted 20.68m of sulphide mineralisation from 171.32m,
including 0.24m of massive sulphide
•
Highlights of Step-out Holes targeting DHEM and SQUID EM Conductors
MARC0099
o 5m sulphide intersection from 245m
MARD0106 (targeting DHEM conductor adjacent to the orebody)
o 25m of mineralised sulphides over 2 zones:
9m from 289m and
16m from 359m.
MARD0112 (EOH 244.13m)
o Mineralised intersection: 175.05 to 194.24 (19.19m)
o Significant zones:
185m to 187.59m (2.59m) disseminated + sulphide stringers
187.59m to 187.95m (0.36m) Moderate to strong sulphide
stringers.
187.95m to 189m (1.05m) disseminated sulphides
MARD0113 EOH: 215.10m
o Mineralised intersection: 178m to 187.85m (9.85 m)
o Significant zones:
179.10m to 181.86m (2.76m) Moderate to strong disseminated
sulphides
181.86m to 185.42m (3.56m) disseminated sulphides + stringers
185.42m to 187.71m (2.29m) Mod to strong disseminated
sulphides + sulphide stringers
MARD0115 (EOH 250.15m)
o Mineralised intersection:
Botswana Metals Limited
Suite 3, 16 Cotham Road, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
187.45m to 188.71m disseminated sulphide and stringers
MARD0116 (EOH 248.15m)
o Mineralised intersection:
206.59m to 207.19m (0.60m) - Massive Sulphides
SQUID technology: all SQUID Conductors drilled to date have returned significant
sulphide intersections returning a 100% success rate. Due to down hole deviations, all
of the holes targeting SQUID conductors have pierced the conductor plates on their
peripheries and great anticipation for even better intersections exists for future holes
that pierce the centre of these targets.
Figure 5: Long Section, looking to the Northwest showing the Ni accumulation (yellow shading), historic
drill pierce points and the pierce points from the recently completed holes (Red spots). Blue rectangles
indicate conductor plate models
Botswana Metals Limited
Suite 3, 16 Cotham Road, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
Figure 6: Cross section, looking northeast, through step-out hole MARD0099. Note the significant drop
in the drill trace and the result miss of the modelled EM conductor (blue line). The sulphide
mineralisation (red) in the drill hole lies directly beneath the modelled conductor.
Botswana Metals Limited
Suite 3, 16 Cotham Road, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
Figure 7: Cross section, looking northeast, through step-out hole MARD0106. Note the drop in the drill
trace and the result miss of the modelled EM conductor (blue line). The first sulphide zone (red) in the
drill hole lies directly beneath the modelled conductor and the second, at the bottom of the hole, lies in
the extended down-dip position of the Maibele North orebody.
2015 Time Domain Electromagnetic (SQUID) Survey
Spectral Geophysics from Gaborone, Botswana, completed a SQUID system for Time
Domain Electromagnetics at Maibele North over the northeast, along strike from the
existing mineralisation and the southeast end of Maibele North during the quarter.
The SQUID TDEM has helped resolve the deeply plunging conductors on both ends of
the orebody that were poorly identified by previous geophysical methods. The survey
has successfully identified at least 4 prospective conductors along strike to the
northeast that are the focus of the current drilling program.
SQUID EM TECHNOLOGY:
A SQUID (superconducting quantum interference device) is a very sensitive
magnetometer used to measure extremely subtle magnetic fields, based on
superconducting loops containing Josephson junctions. The SQUID technology has
Botswana Metals Limited
Suite 3, 16 Cotham Road, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
many uses and is often employed in the medical industry in such application as
Magnetic Resonance Imaging (MRI). In minerals exploration, the SQUID EM technique
can be used to accurately detect very deep conductors potentially associated with
sulphide accumulations.
The SQUID system is stronger and more sensitive than the previous equipment used
and has provide a deeper assessment of conductive targets. The new system allows
for shorter data acquisition times hence more efficient TDEM programs. The SQUID
system has in the past used successfully used in many exploration campaigns in the
world.
Regional Potential of Maibele North Trend
Examination of regional geological and geophysical images shows linear features that
correlate strongly with the zone of mineralisation and extend a considerable distance
to the east towards the Maibele North Extension prospect and further still towards
the Mashambe Prospect (see Figure 6). Both prospects are marked by prominent
VTEM anomalism and the presence of ultramafic lithology and geochemical
anomalies. PL 59/2008 “Maibele Extension and Mashambe lie some 5km and 6km
respectively east of the Maibele “new zone” and exhibit similar surface geological
indicators to those at Maibele North that mark the presence of significant Ni + Cu +
PGEs mineralisation. PL59/2008 is 100% owned by BML and not currently subject to
the JV with BCL.
The same linear trend can be traced 5km to the west of Maibele North and Airstrip
Copper to VTEM Anomaly 10380a, where a single historic drill hole into a conductor
plate returned 0.3%Ni in sulphides down hole.
Evidence is mounting that Maibele North – Airstrip Copper lie on a regional geological
horizon of at least 16km in length prospective for Ni-Cu sulphide mineralisation and
containing a number of prominent conductive anomalies associated with ultramafic
lithology. BML believes this trend is grossly under explored.
Botswana Metals Limited
Suite 3, 16 Cotham Road, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
Figure 8: Regional perspective view from above, looking northeast, of the linear horizon along which the
Maibele North-Aistrip mineralised trend lies. Background image is VTEM db/dt Tau and shows numerous
prominent conductive anomalies along the horizon. Sulphide Ni mineralisation has been intersected at
Airstrip, Maibele North + Maiblele new zone and conductor 10830a.
Hole
Easting
Northing
Number
MARC0099
633090
7595876
MARD0107
633820
7595876
MARD0106
632303
7595149
MARD0100
632236
7595388
MARD0101
632357
7595479
MARD0102
632458
7595454
MARD0104
632493
7595541
MARD0105
632690
7595598
MARD0103
632286
7595434
MARD0110
632523
7595490
MARD0108 632381.00 7595345.00
MARD0109 632366.9 7595404.6
MADD0111 632340.3 7595375.5
MARD0113 633127.50 7595915.70
MARD0112 633081.00 7595890.60
MARD0114
633174
7595946
MARD0115
633036
7595862
MARD0116
632942
7595734
MARD0117
632256
7595347
RL
Total
Dip
Azi
Comment
849
851
840
841
841
843
842
846
845
844
843
843
843
843
843
852
848
848
842
255.00
550.4
376.18
183.05
140.1
175.05
125.10
203.10
156.75
180.06
227.1
212.05
19.23
215.1
244.13
185.02
250.15
248.15
152.2
-60
-75
-60
-55
-55
-55
-55
-55
-55
-55
-55
-55
-55
-60
-60
-60
-60
-60
-60
335
335
330
330
330
330
330
330
330
330
330
330
330
330
330
330
330
330
330
Extension - SQUID TDEM
Extension - SQUID TDEM
Extension - SQUID TDEM
INFILL/MET Hole
INFILL/MET Hole
INFILL/MET Hole
INFILL/MET Hole
INFILL/MET Hole
INFILL/MET Hole
INFILL Hole
INFILL Hole
INFILL Hole
Geotech Hole
Extension - SQUID TDEM
Extension - SQUID TDEM
Extension - SQUID TDEM
Extension - SQUID TDEM
Extension
GEOTECH
Botswana Metals Limited
Suite 3, 16 Cotham Road, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
MARD0118
632340
7595375
842
53.32
-55
330
GEOTECH
Table 1: Details of holes drilled to 30 June 2015 from the 12,500m Maibele North program. Green cells
denote holes still in progress.
Other JV areas of interest:
Regional Exploration - PL54/98 Exploration
During the June quarter, a detailed ground geophysical survey program aimed at
providing drill targets at the 4 priority Ni-sulphide prospects at Takane (PL 54/98) was
completed. The program included 21 line km of ground SQUID EM and 100 line km of
ground magnetic surveying.
Data processing and a report detailing the new SQUID targets as well as priority VTEM
targets recommended for drilling are ongoing with the results expected in the
September quarter.
The JV partners are highly encouraged by the initial reconnaissance sampling and
mapping at the projects and believe good potential exists for further discovery of
significant base and precious metal deposits.
Takane is one of three licences covered by the joint venture and represents ~80 sq km
of the total ~185 sq km included in the JV agreement. The JV tenements form part of
BML’s extensive exploration portfolio in Botswana which covers over 1000 sq km of
highly prospective terrain.
The BML portfolio runs East – West along the Limpopo Mobile Belt that extends into
eastern Botswana from Zimbabwe where it hosts several significant mineral
discoveries.
The Takane area is approximately 10 km from the Maibele North Prospect.
Botswana Metals Limited
Suite 3, 16 Cotham Road, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
Figure 9: Location of the 4 priority target areas on the regional VTEM image. The outline of the SQUID
survey areas are shown (black rectangle) along with ultramafic intrusions and modelled VTEM
conductors (faint pink rectangles)
Exploration Activities outside the JV PLs during the Quarter
Activities outside the Prospecting Licences not covered by the JV with BCL focused on
planning of field work programs for the Maibele North Extension PL59/2008 (100%
BML). Work on the other PLs kept to a minimum during the quarter as the Company
focused on continued exploration on the Joint Venture prospects as outlined above.
The Company has retained the services of Mr Steve Groves (MAIG, MSEG) as its
competent person to review exploration activities of the Company.
PL 59/2008 Maibele North Extension (100% BML)
The 2014 renewal of this 100% owned licence has allowed BML to plan its exploration
strategy outside of the BCL Limited Joint Venture ground for 2015. An exploration field
work program has been designed and will be funded by the proceeds of the recent
Share Purchase Plan. The first stage of work will employ the SQUID TDEM system to
identify further conductive anomalies at the priority targets on the licence with a view
to drilling later in 2015. These prospects lie along strike from the Maibele North
orebody (in JV with BCL Limited) that is currently the subject of a 12,500m resource
Botswana Metals Limited
Suite 3, 16 Cotham Road, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
infill and extension drill program. The SQUID EM technique has been very successfully
used to identify additional conductor targets at Maibele North and will be used over
prospects with similar geological and geophysical settings on PL59/2008 to fast track
the projects to drill ready status.
Figure 10: VTEM image showing the position of the PL59 prospects along strike from Maibele North.
Prospect Details
PL59/2008 is considered particularly attractive because it contains a number of
prospects that lie along strike from Maibele North on a geological horizon that is
interpreted to be a preferential host to Ni - Cu mineralisation in the district. The PL
contains two priority prospects, Maibele North Extension and Mashambe, which show
good indicators of potential Ni + Cu mineralisation similar to that displayed at Maibele
North and have been discovered through soil geochemical surveys, geological
mapping and airborne VTEM surveys. Strong conductors that are coincident with
elevated Ni + Cu soil geochemistry and ultramafic rocktypes are present at both
prospects.
The prospects lie along an interpreted geological horizon that contains a number of Ni
+ Cu occurrences including the Maibele North Resource, with Maibele Extension some
4 km east of Maibele North and Mashambe a further 6km east of Maibele North
Extension.
A third target, Mashambe Northeast, lies some 5km along strike from Mashambe and,
although it displays similar geological and geophysical features, is a second priority
due to less exploration having been undertaken there to date.
Botswana Metals Limited
Suite 3, 16 Cotham Road, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
Maibele North Extension
• ~4km from Maibele North
• Ultramafic Rocktypes present
• Two modelled VTEM Conductors – 11420a, 11470a
• Favourable Cu and Ni soil geochemical anomalies
Mashambe
• 10km from Maibele North, 6km from Maibele North Extension
• Ultramafic Rocktypes present
• Associated modelled VTEM Conductor – 11870b
• Favourable Cu and Ni soil geochemical anomalies
Mashambe North East
• 15km from Maibele North, 4km from Mashambe
• Ultramafic Rocktypes present
• Associated modelled VTEM Conductor 12100a
• Favourable Cu and Ni soil geochemical anomalies
It should also be noted that highly elevated Zinc soil geochemical anomalies exist at
Mashambe and rock chips of up to 0.79g/t Au have been collected at Mashambe
Northeast. These, along with any other features of interest will be followed up in the
course of the exploration program.
Program Details
The exploration program on PL59 is designed to quickly identify drill targets indicative
of Ni-sulphide mineralisation for first-pass RC drill testing. The initial phase of
exploration will include detailed SQUID TDEM surveys over previously identified VTEM
anomalies at both Maibele North and Mashambe. The SQUID system employs cutting
edge, ultra-sensitive electro-magnetic sensors to detect conductors far deeper than
conventional EM technology and has been recently used to great effect at the nearby
Maibele North deposit. All SQUID conductors drilled at Maibele North to date have
shown significant levels of sulphide mineralisation and have confirmed the
effectiveness of the SQUID technique in this terrain.
Spectral Geophysics from Gaborone, Botswana, have been commissioned to
undertake the surveys in the coming weeks and were the contractors who successfully
identified conductors at nearby Maibele North.
Botswana Metals Limited
Suite 3, 16 Cotham Road, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
PL 111/2011
The Company applied to renew PL 111/2011 on 31 March 2014. No correspondence
was received in the December 2014 quarter on the status of this application.
In the March 2015 quarter, the company applied for several new application for a
Prospecting Licences with the Department of Mines in Botswana which are pending
processing. These are highlighted in light green in the Figure 2 above.
Patrick Volpe
Chairman
The information in this report that relates to Exploration Results is based on, and fairly
represents, information and supporting documentation compiled by BML staff on site
and provided to Mr Steve Groves who is a Member of The Australasian Institute of
Mining and Metallurgy. Mr Groves is a consulting geologist to BML and has previously
been employed as the Exploration Manager at BML. Mr Groves has sufficient
experience which is relevant to the style of mineralisation and type of deposit under
consideration and to the activity which he is undertaking to qualify as a Competent
Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of
Exploration Results, Mineral Resources and Ore Reserves’. Mr Groves consents to the
inclusion in this report of the matters based on his information in the form and context
in which it appears.
About BCL Limited
BCL Limited is a mining and smelting company owned by the Botswana Government.
The company commenced operations in 1959 and is now one of the largest private
sector employers in Botswana.
BCL Limited produces two types of finished matte containing nickel, copper and
cobalt, and platinum group and precious metals to a smaller extent. The Selebi Phikwe
ore deposits are owned and operated by BCL Limited.
The Selebi copper and nickel ore body was discovered in 1963, and higher grade ore
was discovered at Phikwe in 1966. Mining of nickel-copper ore commenced in 1973
and since 1980, BCL’s smelter has operated at an annual production rate of
approximately 50,000 tonnes of nickel-copper matte.
BCL Investments (Pty) Limited is a wholly owned subsidiary of BCL Limited.
About the BCL Limited Farm-In Joint Venture on PL 110/94, PL 111/94 and PL 54/98
BCL Investments (Pty) Limited (“BCL”), under the joint venture agreement, can spend
an initial AUD$4 million on a drilling program to earn 40% of the projects over these
Botswana Metals Limited
Suite 3, 16 Cotham Road, Kew, Victoria 3101
P: +61 3 9855 1885; F: +61 3 9855 2885
Email info@botswanametals.com.au
www.botswanametals.com.au
ABN 96 122 995 073
areas. BCL has the option to continue to fund the projects to the completion of a
Bankable Feasibility Study (“BFS”) to earn a 70% interest.
At that point BCL will have the off-take rights at commercial prices, to any ore mined.
It is planned to truck ore to the BCL smelter operations at Selebi Phikwe for processing,
which is situated 55 km to the southwest of our projects. BCL also has a first right of
refusal to participate in exploration on the Company’s other prospecting licences in
Botswana.
The Company will retain a 30% interest after the BFS is completed, at which time the
management of the projects will be transferred to BCL.
BCL Investments (Pty) Limited - Farm-in Joint Venture Agreement
BCL executed the revised Farm-In Joint Venture Agreement on 22 January 2014 with
the only condition precedent being that the DOM grants extensions to PL 110/94, PL
111/94 and PL 54/98 (“the three PLs”). The DOM subsequently granted the extensions
to the three PLs.
The Company has made base metal discoveries within the three PLs: Maibele North
(nickel, copper and platinum group elements), Airstrip Copper (copper and silver) and
Dibete (copper and silver). A total of 23 VTEM base and precious metal anomalies
hav
Share your feedback
Discover