Annual General Meeting Presentation
Released
Released
Announcement PDF
Advancing the Sorby Hills
Lead-Silver Project Toward a Final Investment Decision
2023 AGM Presentation - 6 November 2023
Disclaimer
Forward-Looking Statements
Compliance Statement
Certain statements in the presentation are or may be “forward-looking statements” and represent
the Company’s intentions, projections, expectations or beliefs concerning, among other things,
future operating and exploration results or the Company’s future performance. These forwardlooking statements speak, and the presentation generally speaks, only at the date hereof. The
projections, estimates and beliefs contained in such forward-looking statements necessarily
involve known and unknown risks and uncertainties, and are necessarily based on assumptions,
which may cause the Company’s actual performance and results in future periods to differ
materially from any express or implied estimates or projections.
The Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves
(the ‘JORC Code’) sets out minimum standards, recommendations and guidelines for Public
Reporting in Australasia of Exploration Results, Mineral Resources and Ore Reserves.
General Disclaimer
The information in this presentation remains subject to change without notice. This presentation
may contain information (including information derived from publicly available sources) that has
not been independently verified by the Company.
Not an Offer
This presentation is for information purposes only. The presentation does not comprise a
prospectus, product disclosure statement or other offering document under Australian law. The
presentation does not constitute or form part of any invitation, offer for sale or subscription or
any solicitation for any offer to buy or subscribe for any shares in Boab Metals Limited.
No Liability
Boab Metals Limited has prepared this document based on information available at the time of
preparation. No representation or warranty, express or implied is made as to the fairness,
accuracy or completeness of the information, opinions and conclusions contained in this
presentation. To the maximum extent permitted by law, Boab Metals Limited, its related bodies
corporate and the officers, directors, employees, advisers and agents of those entities do not
accept any responsibility or liability for any loss arising from the use of the presentation or its
contents or otherwise arising in connection with it.
Information included in this presentation relating to Exploration Results has been extracted from
the ASX Announcements titled “Amended Drilling Announcement” dated 4 September 2023”,
“Assays Confirm Further Positive Outcome for Sorby” dated 23 January 2023, “High-Grade LeadSilver Confirmed at Beta Deposit” dated 1 February 2022, and “Sorby Hills DFS Metallurgical
Testwork Results” dated 19 November 2021 available to view at www.boabmetals.com.au. The
Company confirms that it is not aware of any new information or data that materially affects the
information included in these announcements. The Company confirms that the form and context
in which the Competent Person’s findings are presented have not been materially modified from
the form in which they were first presented.
Information included in this presentation relating to Mineral Resources has been extracted from
the Mineral Resource Estimate dated 17 December 2021, available to view at
www.boabmetals.com.au. The Company confirms that it is not aware of any new information or
data that materially affects the information included in the Mineral Resource Estimate and that all
material assumptions and technical parameters underpinning the estimates, continue to apply and
have not materially changed. The Company confirms that the form and context in which the
Competent Person’s findings are presented have not been materially modified from the Mineral
Resource Estimate.
Information included in this presentation relating to Ore Reserves, Production Targets and
Financial Forecasts has been extracted from the Sorby Hills Definitive Feasibility Study and dated
19 January 2023, available to view at www.boabmetals.com.au. The Company confirms that it is
not aware of any new information or data that materially affects the information included in the
Ore Reserve Statement and that all material assumptions and technical parameters underpinning
the estimates, production targets and financial forecasts continue to apply and have not materially
changed. The Company confirms that the form and context in which the Competent Person’s
findings are presented have not been materially modified from the Ore Reserves Statement.
2023 Year in Review
▪
High quality Sorby Hills Definitive Feasibility Study.
▪
Front-End Engineering & Design with Preferred EPC
Contractor GR Engineering Services (“GRES”).
▪
Project Optimisation workstreams ongoing:
o
o
▪
updated Tailings Strategy and Mining Schedule to
bring forward Project revenues.
22% - DFS vs PFS NPV
41% - Boab Share Price1
31% - Median ASX Materials2
updated Processing Plant, Mining and Bulk
Earthwork Tenders to refine costs.
7% - Lead Price1
o
updated metallurgical testwork at Norton to improve
metal recoveries and increase mine life.
21% - Silver Price1
o
updated Power strategy to maximise low-cost green
energy from the Ord Hydro Power Plant.
Potential New Discovery at the Keep Seismic Target 2km
from existing Reserves.
Boab Metals Limited ASX:BML
1. Bloomberg: 1 November 2022 – 31 October 2023
2. www.marketindex.com.au 2 November 2023
Sorby Hills Definitive Feasibility
Study
Highlights
A$245m preproduction Capex
underpinned 75% by
tendered pricing
C1 cash cost US$0.39/lb
payable Pb
Incl. net Silver credit of
US$0.38/lb payable Pb
Average Annual Production
103kt Lead-Silver concentrate 67kt
Lead and 2.2Moz Silver
NPV8 A$370m
IRR 35%
Strong pre-tax
economics
1. See Appendix for Revenue Assumptions
Boab Metals Limited ASX: BML
Lead
543 thousand payable tonnes
A$1,790 Million Revenue
2.25Mtpa
8.5 Year Mine
Life
A$1.0bn Operating Cash Flow
A$119m p.a. Average EBITDA
Silver
17.2 million payable ounces
A$692 Million Revenue
Sorby Hills confirmed as a
Low-Cost Project
2027 Lead Cost Curve (ex-works basis)
1st Quartile
2nd Quartile
3rd Quartile
4th Quartile
▪ Sorby Hills has been
independently confirmed
as a low-cost Project.
US$/t Lead
▪ Forecast Project Operating
Costs covered by a
historically non-volatile
Lead Price.
▪ Operating margin highly
leveraged to Silver price.
▪ Rare ASX exposure to
Silver Price movements
Sorby Hills
Project
CRU, Independent Market Consultant Report for Boab Metals’ Sorby Hills Pb-Ag Project (Sept 2023).
Boab Metals Limited ASX:BML
Boab Metals Limited ASX:BML
5
Looking Forward
• Demand growth underpinned by mature and emerging vehicle technologies.
• Supported by rapid growth in utility and renewable energy storage1.
1. www.batteryinnovation.org/resources/lead-battery-market-data/
Global Refined
Lead Demand (Mt)
Global Sales of light duty
vehicles (million units)
Forecast Light Vehicles Sales versus Lead Demand2
ICE Petrol
ICE Diesel
Hybrid EVs
Battery EVs
Other EVs
“…. low voltage 12V leadbased batteries will
continue to be used for
starter and auxiliary
functions in most internal
combustion engine
vehicles (ICE) and new
electric vehicles2 …..”
2. CRU, Independent Market
Consultant Report for Boab Metals’
Sorby Hills Pb-Ag Project (Sept 2023)
Lead Demand
Boab Metals Limited ASX:BML
Boab Metals Limited ASX:BML
6
Updated Tailings Strategy to Enhance Metal Production
20,000,000
1,000,000
Cumulative Payable Lead / Silver
900,000
High grade Silver from the
Norton deposit delivered earlier
in the production schedule.
16,000,000
800,000
14,000,000
700,000
12,000,000
600,000
10,000,000
500,000
8,000,000
400,000
6,000,000
300,000
4,000,000
200,000
2,000,000
100,000
-
1
3
5
7
9
11
13
15
17
19
21
23
25
27
29
31
33
35
37
39
41
43
-
Cumulative Payable Lead (tonnes)
Cumulative Payable Silver (ounces)
18,000,000
▪ The DFS tailings strategy incorporated both
above-ground tailings storage within an
integrated waste landform (“IWL”) and in-pit
tailings deposition.
▪ Value Engineering has determined that the
initial footprint of the proposed IWL is
sufficient to support additional raises that will
provide capacity for approximately 6 years of
above-ground tailings storage.
▪ The updated strategy allows for higher
grades from the Omega and Norton pits to
be mined earlier thus replacing the lower
grade ore from the Omega South pit in the
Mining Schedule
Production Quarter
Cumulative Payable Silver - Updated Schedule
Cumulative Payable Silver - DFS
Cumulative Payable Lead - Updated Schedule
Cumulative Payable Lead - DFS
See ASX announcement 19 January 2023
Boab Metals Limited ASX:BML
Boab Metals Limited ASX:BML
7
Detailed Design and Optimised Plant Layout
▪ GRES has completed FEED
Workstreams
Primary
Crusher
▪ FEED output has resulted in:
Flotation
Circuit
SAG Mill
Filter
Press
Ball Mill
Tailings
Thickene
r
•
detailed plant design;
•
optimised site layout;
•
the issue of tender packages
for long-lead items; and
•
updated EPC pricing
consistent with EPC pricing
adopted in the DFS.
•
Options to reduce costs have
been identified by GRES.
•
EPC Contract Award upon FID.
Concentrate Container Loading
Figure: 3D Model of the Sorby Hills Process Plant produce by GRES during
FEED.
Boab Metals Limited ASX:BML
Boab Metals Limited ASX:BML
8
Strategic Growth Opportunities
Keep Seismic Target.
▪
1st drill hole into a potential new discovery (2 km
south of existing Sorby Hills reserves).
▪
Possible New Zone with scope for extensive
development of mineralisation.
Intersected
Figures: Section of Keep
Seismic Target showing basin
margin faults and favourable
stratigraphic horizon. Massive
replacement style sphalerite
(ZnS) and galena (PbS)
▪
Upper Mineralised Zone: ~5m of stratiform bands
and disseminated mineralisation from 82.5m.
▪
Lower Mineralised Zone: ~14m of stratiform MVT
zinc and lead sulphides bands and disseminated
mineralisation from 242.5m.
Future
▪
Aggressive drill program to test the potential for an
economic mineral deposit.
Boab Metals Limited ASX:BML
Boab Metals Limited ASX:BML
9
Looking Forward
• Complete ongoing Optimisation Workstreams
and progress Project Approvals.
• Incorporate the results of Optimisation
workstreams into a FEED Study - Q1 2024.
• Continue engagement with potential
financers.
• Secure credit approved offer(s) from financiers.
• Execute Offtake Agreement(s).
• Reach a Final Investment Decision.
• Aggressive drill program to test potential for an
economic deposit at the Keep Seismic Target
Boab Metals Limited ASX:BML
Boab Metals Limited ASX:BML
10
Top 4 Shareholders
Volume
#
Holder Name
1
Villiers Queensland PL
8.75%
2
Zero Nominees Pty Limited
4.33%
3
Citicorp Nominees Pty Limited
3.31%
4
Brent Connolly
2.52%
Boab Metals Limited ASX: BML
9 October 2023
Nov-23
Oct-23
Sep-23
Aug-23
Jul-23
Jun-23
May-23
Performance Rights
8,300,000
Apr-23
Market Cap
A$18.3 million
Mar-23
Cash
A$3.0 million (30 September 2023)
0.40
0.35
0.30
0.25
0.20
0.15
0.10
0.05
0.00
Feb-23
Shares on Issue
174 million shares
4.0
3.5
3.0
2.5
2.0
1.5
1.0
0.5
0.0
Jan-23
Debt
Nil
Dec-22
Share Price
A$0.105 / share
Volume (million shares)
Capital Structure (3 November 2023)
Share Price (A$/sh)
Share Price History
Nov-22
Corporate Summary
Share Price
• ASX-listed base and
precious metals
developer and explorer.
• Board & Management
team with a proven track
record in development.
• Advancing toward Final
Investment Decision on
Sorby Hills.
• Top 20 shareholders hold
36% of issued capital.
Thank You
Simon Noon – Managing Director & CEO
info@BoabMetals.com
www.BoabMetals.com
www.linkedin.com/company/boab-metals
Appendix
Appendix
Boab Metals Limited ASX:BML
13
Board and
Management
Gary Comb
Board and Management
with a proven track
record in exploration and
development
Technical Team
Boab Metals
Limited ASX:BML
Boab Metals Limited
ASX:BML
Simon Noon
Richard Monti
Andrew Parker
Chairman
Managing Director
and CEO
Non-Exec. Director
Non-Exec. Director
Engineer with over 30
years’ experience in the
Australian mining
industry, with a strong
track record in
successfully
commissioning and
operating base metal
mines.
Experienced mining
executive with a strong
background in
management, capital
raising and operating
JV’s with mid to top tier
miners in a variety of
commodities.
Geologist with over 30
years’ experience in
technical, commercial,
marketing and finance
within the exploration
and mining industry.
Lawyer with significant
experience in the
exploration and mining
industry. Wealth of
expertise in corporate
advisory, strategic
consultancy and raising
capital.
Paul Hewitt – Project Director
Richard Flanagan – Project Engineer
Simon Dorling - Exploration Manager
Paul has over 25 years in providing senior project
delivery leadership within the Energy and Resource
sectors for process and non-process infrastructure
projects, for the full lifecycle from study phase
through to execution within Australia and
Internationally.
Mining engineer with extensive experience across a
wide range of commodities, including several world
class Silver-Lead-Zinc deposits and covers management
roles across feasibility studies, development,
commissioning and operations.
Geologist with more than 26 years’ experience in
exploration, development and the mining of base
metals, precious metals, energy minerals and
industrial minerals.
14
Sorby Hills Definitive Feasibility
Study Capital Costs
Tendered Pricing for 75% of
Capital Costs to reduce the
risk of pre-FID cost escalation.
Process Plant EPC comprises:
• $82.9M - Supply Cost
• $41.6M - Installation Cost
• $5.8M - Freight Cost
A$20M Contingency.
A$21M Owner Costs including
operational readiness items
such as critical spares and
build-up of owner’s team.
Pre-production
(A$M)
Sustaining
(A$M)
Total
(A$M)
Early Works / Bulk Earthworks / Road Construction
9.9
15.7
25.6
Process Plant and Non-Plant Infrastructure (NPI)
130.5
-
130.5
Tailings Storage and Evaporation Pond
18.0
1.9
19.9
Mine Water Settling Pond & Water Storage Facility
12.4
21.3
33.7
Accommodation refurbishment
4.1
-
4.1
Communications
0.9
-
0.9
Fuel Tanks
-
1.3
1.3
Concentrate Transport & Containers
7.9
-
7.9
Owners Cost
25.3
5.8
31.0
Project Development Contingency
20.9
-
20.9
Pre-Production Operating Costs
14.6
-
14.6
-
9.3
9.3
244.6
55.2
299.8
Item
Mine Closure
Total
Boab Metals Limited ASX:BML
Boab Metals Limited ASX:BML
15
Sorby Hills Definitive Feasibility Study Operating Costs
Competitive C1 cash cost of US$0.39/lb
payable Pb (including Silver Credits).
~80% of Mining Costs underpinned by
tendered pricing with opportunities for
further schedule and cost optimisation
through the contracting process.
Opportunity to reduce Process costs
through the optimisation of back-up
power requirements.
Opportunity to reduce Logistics costs
via application of concessional loading
for road haulage.
Unit Costs
Item
Total
(A$M)
A$/t ore
US$/lb payable Pb
Mining
591
32.4
0.34
Processing
391
21.4
0.22
G&A
88
4.8
0.05
Logistics
121
6.6
0.07
Lead Treatment
159
8.7
0.09
C1 Costs (ex Credits)
1,351
73.9
0.77
Net Silver Credits
(660)
(36.1)
(0.38)
C1 Costs
690
37.8
0.39
Royalties
94
5.2
0.05
Sustaining Capital
55
3.0
0.03
AISC
840
46.0
0.48
Unit Operating Costs based on 18.3Mt of Ore, 543kt of Payable
Lead, average exchange rate of AUD:USD 0.68 and average
Silver price of US$27.4/oz.
Boab Metals Limited ASX:BML
Boab Metals Limited ASX:BML
16
Sorby Hills Definitive Feasibility Study Life of Mine Physicals
PHYSICALS SUMMARY
Unit
Total
FY23
FY24
FY25
FY26
FY27
FY28
FY29
FY30
FY31
FY32
FY33
FY34
ROM Mined
Mt
18.3
-
-
2.1
2.1
2.3
2.5
1.9
2.2
1.8
3.3
-
-
Waste Mined
Mt
134.6
-
-
11.7
11.6
12.2
24.3
26.1
25.6
19.6
3.5
-
-
% Measured
%
56.7%
-
-
89.7%
66.7%
63.3%
89.4%
59.5%
45.9%
66.0%
-
-
-
% Indicated
%
26.5%
-
-
10.3%
33.3%
36.7%
9.7%
37.3%
50.7%
2.3%
28.6%
-
-
% Inferred
%
16.8%
-
-
-
-
-
1.0%
3.2%
3.4%
31.7%
71.4%
-
-
Lead Grade
%
3.4%
-
-
4.1%
3.2%
3.5%
2.8%
3.0%
3.6%
4.0%
3.4%
-
-
Silver Grade
g/t
39
-
-
38
28
39
23
38
42
64
42
-
-
Processed Tonnes
Mt
18.3
-
-
1.15
2.12
2.25
2.25
2.26
2.25
2.25
2.25
1.49
-
Lead Grade
%
3.4%
-
-
5.6%
3.6%
3.6%
2.9%
2.9%
3.6%
3.6%
3.8%
2.0%
-
Silver Grade
g/t
39
-
-
46
34
39
25
35
41
56
44
31
-
Lead Recovery
%
91.0%
-
-
90.3%
94.2%
94.1%
92.8%
93.7%
90.6%
83.1%
90.3%
90.3%
-
Silver Recovery
%
81.8%
-
-
87.3%
86.4%
87.1%
87.4%
87.2%
83.0%
78.5%
70.4%
72.9%
-
Concentrate Produced
kt
872
-
-
91
109
115
93
92
114
111
108
38
-
Lead Grade
%
65.5%
-
-
63.9%
65.6%
65.7%
66.1%
65.5%
63.8%
59.8%
72.3%
70.4%
-
Silver Grade
g/t
665
-
-
501
574
666
520
737
665
890
654
873
-
Payable Lead
kt
543
-
-
55
69
69
57
62
67
62
75
28
-
Payable Silver
Moz
17.2
-
-
1.3
1.9
2.2
1.4
2.1
2.1
3.0
2.1
1.1
-
Boab Metals Limited ASX:BML
Boab Metals Limited ASX:BML
17
Establishing Deep Roots within the
Community and supporting better outcomes
Boab is extremely proud to be the Naming Rights
Sponsor of the Ord Valley Muster for
2023 and beyond.
•
Sense of community plays a key role in economic
and social well-being of stakeholders across the
east Kimberley Region.
•
The Ord Valley Muster has been a highlight of
the Kimberley community calendar for 20 years.
Boab is an enthusiastic supporter and active
contributor to the Teach Learn Grow program.
•
Boab Metals has been partnering with Teach
Learn Grow (TLG) since 2021 in the delivery of
their Rural Program which supports one-on-one
tutoring and mentorship to students in East
Kimberley schools.
Images: Ord Valley Muster 2023 and Simon Noon - Managing Director/CEO with team at Teach Learn
Grow, East Kimberley
Boab Metals Limited ASX:BML
Boab Metals Limited ASX:BML
18
Metal Equivalent
Calculation
Macroeconomic
Assumptions
The contained metal equivalence formula
is based on the Sorby Hills DFS including:
It is Boab’s opinion that all elements included in the metal equivalent calculation have a reasonable
potential to be recovered and sold. The formula used to calculate lead equivalent grade is:
• Lead Price US$2,253/t; and
Metal Eq (percent) = Gpri + (Gpri × [∑i Ri Si Vi Gi ]/(Rpri Spri Vpri Gpri))
• Silver Price US$27.4/oz.
Pb
Ag
Lead Equivalent Calculations
where R is the respective metallurgical metal recovery rate, S is the respective smelter return
rate, V is metal price/tonne or ounce, and G is the metal commodity grade for the suite of
potentially recoverable commodities (i) relative to the primary metal (pri).
• Silver recovery of 82% (weighted
average of oxide and fresh Ag
recoveries); and
Metal equivalents are highly dependent on the metal prices used to derive the formula. Boab notes
that the metal equivalence method used above is a simplified approach. The metal prices are based
on the DFS values adopted and do not reflect the metal prices that a smelter would pay for
concentrate nor are any smelter penalties or charges included in the calculation.
• Silver Payability rate of 95%.
Owing to limited metallurgical data, zinc grades are not included at this stage in the lead equivalent
grade calculation.
Silver Equivalent Calculations
• Lead recovery of 91% (weighted
average of oxide and fresh Pb
recoveries); and
• Lead Payability rate of 95%.
Boab Metals Limited ASX:BML
Assumption
Unit
FY2023 FY2024 FY2025
FY2026 FY2027+
Lead Price
US$/t
2,259
2,268
2,269
2,254
2,251
Silver Price
US$/oz
24.8
25.8
26.4
27.3
27.5
Exchange Rate
A$:US$
0.70
0.70
0.70
0.69
0.68